1What is the main purpose of resource allocation in a software project?
Resource allocation introduction
Easy
A.To define programming language syntax rules
B.To assign available resources to project tasks
C.To replace all project status meetings
D.To remove completed tasks from the schedule
Correct Answer: To assign available resources to project tasks
Explanation:
Resource allocation assigns people, equipment, funds, and other available resources to project tasks.
Incorrect! Try again.
2Which activity is part of identifying resource requirements?
Identifying resource requirements
Easy
A.Removing all dependencies from the schedule
B.Recording only the completed project tasks
C.Estimating the skills and people needed
D.Selecting colors for the progress dashboard
Correct Answer: Estimating the skills and people needed
Explanation:
Identifying resource requirements includes estimating the people, skills, tools, and materials needed for the project.
Incorrect! Try again.
3What should a project manager check before scheduling a team member for a task?
Scheduling resources
Easy
A.The order of names in the team directory
B.The team member's availability during the task
C.The color used for the task label
D.The number of pages in the project report
Correct Answer: The team member's availability during the task
Explanation:
A resource should be scheduled only after checking whether it is available for the required period.
Incorrect! Try again.
4What is resource over-allocation?
Resource allocation
Easy
A.Keeping resources available for future activities
B.Completing a task before its planned deadline
C.Assigning more work than a resource can handle
D.Assigning one resource to one suitable task
Correct Answer: Assigning more work than a resource can handle
Explanation:
Over-allocation occurs when a resource is assigned more work than it can complete within the available time.
Incorrect! Try again.
5Why is the resource and cost schedule published?
Publishing the resource & cost schedule
Easy
A.To communicate planned assignments and expenses
B.To define coding standards for developers
C.To hide budget changes from project stakeholders
D.To replace the software requirements document
Correct Answer: To communicate planned assignments and expenses
Explanation:
Publishing the schedule helps stakeholders understand planned resource use, timing, and project costs.
Incorrect! Try again.
6What usually determines the sequence of project activities?
Scheduling sequence
Easy
A.Employment dates of the team members
B.File sizes of the project documents
C.Alphabetical order of the activity names
D.Dependencies between the project activities
Correct Answer: Dependencies between the project activities
Explanation:
Activity dependencies show which tasks must occur before or after other tasks.
Incorrect! Try again.
7What does a monitoring framework mainly define?
Creating frameworks
Easy
A.Which programming language must be used
B.Where source files will be physically printed
C.What will be measured and reported
D.How employee salaries will be deposited
Correct Answer: What will be measured and reported
Explanation:
A monitoring framework defines the measures, responsibilities, methods, and reporting arrangements used to track a project.
Incorrect! Try again.
8Which item is useful for collecting project progress data?
Data collection
Easy
A.Completed task records and timesheets
B.Personal messages outside the project
C.Archived files from another organization
D.Unrelated advertisements and brochures
Correct Answer: Completed task records and timesheets
Explanation:
Task records and timesheets provide useful data about completed work and resource effort.
Incorrect! Try again.
9Which chart commonly shows project tasks against time?
Visualizing progress
Easy
A.Organization chart
B.Pie chart
C.Scatter plot
D.Gantt chart
Correct Answer: Gantt chart
Explanation:
A Gantt chart displays project tasks along a timeline, making planned and actual progress easier to view.
Incorrect! Try again.
10What is the primary purpose of a project status report?
Status reports
Easy
A.To list every source-code statement in order
B.To replace the approved project budget
C.To advertise the project to new customers
D.To summarize progress, issues, and next steps
Correct Answer: To summarize progress, issues, and next steps
Explanation:
A status report keeps stakeholders informed about progress, current issues, and upcoming activities.
Incorrect! Try again.
11What is a milestone in a project schedule?
Milestone analysis
Easy
A.A payment made for office utilities
B.A detailed list of programming variables
C.A daily record of employee attendance
D.A significant event or achievement
Correct Answer: A significant event or achievement
Explanation:
A milestone marks an important event, decision, or achievement and usually has no duration.
Incorrect! Try again.
12What does cost monitoring compare most directly?
Cost monitoring
Easy
A.Source-code length with document length
B.Team size with the number of customers
C.Meeting duration with office working hours
D.Actual spending with planned spending
Correct Answer: Actual spending with planned spending
Explanation:
Cost monitoring compares actual costs with budgeted costs to identify overspending or underspending.
Incorrect! Try again.
13What is the first appropriate action when a project change is requested?
Change control
Easy
A.Ignore the request until project closure
B.Implement the requested change immediately
C.Remove the original project objectives
D.Record and evaluate the requested change
Correct Answer: Record and evaluate the requested change
Explanation:
Change control requires a requested change to be documented and evaluated before approval or implementation.
Incorrect! Try again.
14Which of the following is usually a direct project cost?
Cost (direct and indirect)
Easy
A.Insurance covering the entire organization
B.Rent for the organization's main office
C.Utilities shared by all company departments
D.Wages paid to project developers
Correct Answer: Wages paid to project developers
Explanation:
Developer wages are directly attributable to the project, while shared organizational expenses are generally indirect costs.
Incorrect! Try again.
15Which of the following is usually an indirect project cost?
Cost (direct and indirect)
Easy
A.License purchased only for the project
B.Travel required for a project meeting
C.Payment for a project-specific tester
D.Rent for a shared corporate office
Correct Answer: Rent for a shared corporate office
Explanation:
Shared office rent supports multiple projects or departments, so it is usually treated as an indirect cost.
Incorrect! Try again.
16In earned value analysis, what does Earned Value (EV) represent?
Earned value analysis
Easy
A.Planned value of all scheduled future work
B.Total budget approved for the project
C.Budgeted value of work actually completed
D.Actual amount paid for completed work
Correct Answer: Budgeted value of work actually completed
Explanation:
Earned Value is the budgeted cost of the work that has actually been completed.
Incorrect! Try again.
17Which formula gives the Cost Performance Index (CPI)?
Performance ratio
Easy
A.
B.
C.
D.
Correct Answer:
Explanation:
The Cost Performance Index is calculated as Earned Value divided by Actual Cost: .
Incorrect! Try again.
18What is a key benefit of using AI in a real-time project status dashboard?
AI in Monitoring: Use of AI for real-time project status dashboards
Easy
A.It can guarantee that costs never increase
B.It can remove the need for project data
C.It can identify emerging delays quickly
D.It can eliminate every project uncertainty
Correct Answer: It can identify emerging delays quickly
Explanation:
AI can analyze current project data and highlight possible delays or risks as they emerge.
Incorrect! Try again.
19What is the purpose of an intelligent project notification?
Intelligent notifications
Easy
A.To prevent stakeholders from viewing progress
B.To alert relevant users about important conditions
C.To replace all project plans with messages
D.To send identical messages at random times
Correct Answer: To alert relevant users about important conditions
Explanation:
Intelligent notifications use project data to send timely, relevant alerts about risks, delays, or required actions.
Incorrect! Try again.
20Which visual element is suitable for showing the percentage of a task completed?
Progress visualization
Easy
A.Contact list
B.Progress bar
C.Text editor
D.File browser
Correct Answer: Progress bar
Explanation:
A progress bar provides a simple visual representation of how much of a task has been completed.
Incorrect! Try again.
21A project manager assigns the same database specialist to two critical tasks scheduled for the same week. The specialist can work only 40 hours, but the tasks require a total of 64 hours. What should the project manager do first?
Resource allocation introduction
Medium
A.Mark both tasks complete based on planned effort
B.Increase the project budget without changing the schedule
C.Remove the specialist from the resource calendar
D.Apply resource leveling to resolve the over-allocation
Correct Answer: Apply resource leveling to resolve the over-allocation
Explanation:
Resource leveling adjusts task dates or assignments to resolve demand that exceeds a resource's available capacity.
Incorrect! Try again.
22A testing activity requires 240 person-hours and must be completed in 10 working days. If each tester can contribute 6 productive hours per day, what is the minimum number of testers required?
Identifying resource requirements
Medium
A.4 testers
B.6 testers
C.5 testers
D.3 testers
Correct Answer: 4 testers
Explanation:
One tester provides hours. Therefore, the requirement is testers.
Incorrect! Try again.
23A developer is available only from Monday to Wednesday. A 24-hour task is initially scheduled from Tuesday to Thursday, with 8 hours of work per day. Which scheduling adjustment best respects the resource calendar without changing the effort?
Scheduling resources
Medium
A.Schedule the task entirely on Wednesday
B.Schedule the task from Wednesday to Friday
C.Schedule the task from Tuesday to Thursday
D.Schedule the task from Monday to Wednesday
Correct Answer: Schedule the task from Monday to Wednesday
Explanation:
Monday through Wednesday provides three available workdays and accommodates all 24 hours without violating the developer's calendar.
Incorrect! Try again.
24Two activities need the same analyst. Activity X is on the critical path, while Activity Y has five days of total float. If both are scheduled simultaneously, what is the most appropriate allocation decision?
Resource allocation
Medium
A.Assign the analyst to X and delay Y within its float
B.Assign the analyst to Y and delay X by five days
C.Cancel Y and remove it from the project scope
D.Split the analyst equally and keep both durations fixed
Correct Answer: Assign the analyst to X and delay Y within its float
Explanation:
Prioritizing the critical activity protects the project completion date, while Y can be shifted within its available float.
Incorrect! Try again.
25Before publishing a resource and cost schedule as the project baseline, which review is most important?
Publishing the resource & cost schedule
Medium
A.Confirm resource availability, rates, assumptions, and approvals
B.Replace estimated costs with the maximum possible costs
C.Remove contingency reserves from every scheduled activity
D.Publish only the activities assigned to internal employees
Correct Answer: Confirm resource availability, rates, assumptions, and approvals
Explanation:
A publishable baseline should use validated availability and cost information and should be approved by the relevant stakeholders.
Incorrect! Try again.
26Task B can begin only after Task A is completed, while Task C may start when Task A starts. Which dependency combination represents this scheduling sequence?
B has a Finish-to-Start dependency on A, whereas C has a Start-to-Start dependency on A.
Incorrect! Try again.
27A project manager is creating a monitoring framework for a six-month software project. Which design provides the clearest basis for control?
Creating frameworks
Medium
A.Define metrics, owners, thresholds, frequency, and escalation rules
B.Allow each team member to select independent reporting periods
C.Create reports only when a major schedule delay occurs
D.Collect all available data without assigning metric owners
Correct Answer: Define metrics, owners, thresholds, frequency, and escalation rules
Explanation:
An effective monitoring framework specifies what is measured, who owns it, when it is reviewed, and how exceptions are handled.
Incorrect! Try again.
28A manager needs reliable weekly data for comparing actual effort with planned effort. Which collection method is most appropriate?
Data collection
Medium
A.Planned effort copied into the actual-effort data fields
B.Unstructured comments gathered from public discussion boards
C.Informal estimates collected at the project closing meeting
D.Approved time entries linked to work packages
Correct Answer: Approved time entries linked to work packages
Explanation:
Approved time entries tied to work packages provide traceable actual-effort data that can be compared with the plan.
Incorrect! Try again.
29A team wants to show how much work remains in a sprint each day and whether completion is trending toward the sprint deadline. Which visualization is most suitable?
Visualizing progress
Medium
A.Burndown chart
B.Resource histogram
C.Responsibility matrix
D.Network diagram
Correct Answer: Burndown chart
Explanation:
A burndown chart plots remaining work over time and makes progress against the expected completion trend visible.
Incorrect! Try again.
30A project is two weeks behind schedule because an external interface was delivered late. Which status report entry is most useful to decision-makers?
Status reports
Medium
A.State that the team is busy and omit the forecasted impact
B.List all completed tasks without describing the current delay
C.Report the original baseline dates as the latest expected dates
D.State the variance, cause, impact, corrective action, and owner
Correct Answer: State the variance, cause, impact, corrective action, and owner
Explanation:
A useful status report connects the current variance to its cause, expected impact, response, and accountable owner.
Incorrect! Try again.
31At the current status date, a design-approval milestone was planned for day 30 but is now forecast for day 36. The milestone was forecast for day 34 in the previous report. What does the latest analysis indicate?
Milestone analysis
Medium
A.The milestone is four days late and has recovered two days
B.The milestone is two days late and remains on its baseline
C.The milestone is six days late and has slipped two more days
D.The milestone is six days early and has improved two days
Correct Answer: The milestone is six days late and has slipped two more days
Explanation:
The current forecast is days later than baseline and days later than the previous forecast.
Incorrect! Try again.
32A work package has a planned cost of $50,000 for the work scheduled to date, but actual spending is $58,000. Before judging cost performance, what additional information is most important?
Cost monitoring
Medium
A.The budgeted value of the work actually completed
B.The original duration of every completed project activity
C.The total number of employees in the performing organization
D.The number of meetings held during the reporting period
Correct Answer: The budgeted value of the work actually completed
Explanation:
Earned value is needed to determine whether the higher actual cost reflects overspending or simply more work being completed than planned.
Incorrect! Try again.
33A customer requests an additional reporting feature after the project scope baseline has been approved. What should the project manager do next?
Change control
Medium
A.Document the request and assess its scope, schedule, and cost impacts
B.Reject the request because approved baselines cannot be modified
C.Direct the team to implement the feature before evaluating it
D.Update the baseline immediately without obtaining authorization
Correct Answer: Document the request and assess its scope, schedule, and cost impacts
Explanation:
Formal change control begins by documenting and evaluating the proposed change before approval, rejection, or baseline revision.
Incorrect! Try again.
34A project incurs $80,000 in developer wages, $12,000 in project-specific cloud charges, and $8,000 as its allocated share of corporate office rent. What are the direct and indirect costs?
Cost (direct and indirect)
Medium
A.Direct: $88,000; Indirect: $12,000
B.Direct: $100,000; Indirect: $0
C.Direct: $92,000; Indirect: $8,000
D.Direct: $80,000; Indirect: $20,000
Correct Answer: Direct: $92,000; Indirect: $8,000
Explanation:
Developer wages and project-specific cloud charges are traceable to the project, while allocated corporate rent is an indirect cost.
Incorrect! Try again.
35At the end of a month, a project has planned value , earned value , and actual cost . What are the schedule variance and cost variance?
Earned value analysis
Medium
A. and
B. and
C. and
D. and
Correct Answer: and
Explanation:
Using and , the results are and . The project is behind schedule and over budget.
Incorrect! Try again.
36A project has earned value , actual cost , and planned value . Which interpretation is correct?
Performance ratio
Medium
A. and ; over budget and behind schedule
B. and ; under budget but behind schedule
C. and ; over budget but ahead of schedule
D. and ; under budget and ahead of schedule
Correct Answer: and ; over budget but ahead of schedule
Explanation:
and . A CPI below 1 indicates cost inefficiency, while an SPI above 1 indicates schedule progress ahead of plan.
Incorrect! Try again.
37A project has a budget at completion of and a current cost performance index of . If the same cost efficiency is expected to continue, what is the estimate at completion?
Earned value analysis
Medium
A.
B.
C.
D.
Correct Answer:
Explanation:
If current cost efficiency continues, .
Incorrect! Try again.
38An AI dashboard shows a sudden 25% drop in project completion after data is synchronized from several tools. What should the project manager do before initiating corrective action?
AI in Monitoring: Use of AI for real-time project status dashboards
Medium
A.Accept the AI result because automated outputs are always current
B.Validate source mappings, timestamps, and calculation rules
C.Disable historical data to prevent comparison with prior periods
D.Reset the baseline so that it matches the displayed completion
Correct Answer: Validate source mappings, timestamps, and calculation rules
Explanation:
Real-time dashboards depend on data quality and correct integration. An unexpected change should be validated before decisions are made.
Incorrect! Try again.
39A project team receives hundreds of automated alerts each day and begins ignoring them. Which configuration would best reduce alert fatigue while preserving useful warnings?
Intelligent notifications
Medium
A.Use risk-based thresholds, deduplication, and role-based routing
B.Disable alerts for schedule and cost variances until project closure
C.Send every event to all stakeholders at the highest priority
D.Trigger notifications whenever any project data field is updated
Correct Answer: Use risk-based thresholds, deduplication, and role-based routing
Explanation:
Thresholds, duplicate suppression, and targeted routing help ensure that notifications are relevant, actionable, and sent to the right people.
Incorrect! Try again.
40A steering committee wants to compare baseline dates with current forecast dates for major activities and quickly identify schedule slippage. Which visualization best supports this need?
Progress visualization
Medium
A.Cost allocation pie chart
B.Risk probability histogram
C.Resource skills matrix
D.Tracking Gantt chart
Correct Answer: Tracking Gantt chart
Explanation:
A tracking Gantt chart displays baseline and current activity dates together, making delays and forecast changes easy to identify.
Incorrect! Try again.
41A project has three non-critical activities that require the same specialist during the same week. Delaying any activity by one week has no immediate effect on the completion date, but their remaining total floats are 1, 3, and 5 weeks. If no other information is available, which allocation rule best protects the schedule from future disruption?
Resource allocation introduction
Hard
A.Assign the specialist first to the activity with 1 week of float
B.Assign the specialist first to the activity with 5 weeks of float
C.Divide the specialist equally among all three activities
D.Assign the specialist to the activity with the largest budget
Correct Answer: Assign the specialist first to the activity with 1 week of float
Explanation:
The activity with the least remaining float has the smallest tolerance for delay. Prioritizing it reduces the risk that resource contention will create a new critical path.
Incorrect! Try again.
42A work package requires 240 productive analyst-hours within three weeks. Each analyst is available for 40 hours per week, but historical data shows that meetings and support work consume 25% of available time. Assuming work is perfectly divisible, what is the minimum number of analysts required?
Identifying resource requirements
Hard
A.4 analysts
B.3 analysts
C.5 analysts
D.2 analysts
Correct Answer: 3 analysts
Explanation:
Each analyst supplies productive hours. Therefore, , so at least 3 analysts are required.
Incorrect! Try again.
43Activities A and B may start immediately and require the same sole engineer. A lasts 4 days and B lasts 3 days. Activity C lasts 2 days, uses another resource, and starts after A. The project finishes when both B and C are complete. Which resource-feasible sequence gives the earliest finish?
Scheduling resources
Hard
A.Execute C, then A, then B; the project finishes on day 9
B.Execute A and B together; the project finishes on day 5
C.Execute B, then A; the project finishes on day 9
D.Execute A, then B; the project finishes on day 7
Correct Answer: Execute A, then B; the project finishes on day 7
Explanation:
Scheduling A first allows C to run in parallel with B from day 4. B ends on day 7 and C on day 6, so the resource-feasible project finish is day 7.
Incorrect! Try again.
44Two projects compete for one specialist. Project X gains if assigned now and loses per week of delay. Project Y gains if assigned now and loses per week of delay. Each assignment occupies the specialist for one week. Which sequence maximizes the combined realized benefit?
Resource allocation
Hard
A.Assign X first, producing a combined benefit of
B.Assign X first, producing a combined benefit of
C.Assign Y first, producing a combined benefit of
D.Split the specialist between both projects so each project retains its entire immediate benefit despite the one-week capacity constraint
Correct Answer: Assign Y first, producing a combined benefit of
Explanation:
If Y is first, the benefit is 80,000-$10,000) = $140,000$. If X is first, it is $80,000 + (25,000) = .
Incorrect! Try again.
45A resource and cost schedule has been approved, but procurement rates are commercially sensitive. Which publication approach best preserves control while meeting stakeholder information needs?
Publishing the resource & cost schedule
Hard
A.Maintain separate editable schedules for finance, delivery, and suppliers
B.Publish one unrestricted schedule containing all rates and named resources
C.Remove all cost data and publish only milestone completion dates
D.Publish role-based views derived from one version-controlled baseline
Correct Answer: Publish role-based views derived from one version-controlled baseline
Explanation:
Role-based views protect sensitive details while retaining a single controlled source. Separate editable schedules risk inconsistent baselines and reconciliation errors.
Incorrect! Try again.
46A technically valid network schedule becomes infeasible after scarce-resource limits are applied. Which sequence of scheduling operations most reliably preserves traceability between technical dependencies and resource-driven delays?
Scheduling sequence
Hard
A.Allocate resources, define scope, establish logic, and calculate dates
B.Calculate costs, assign milestones, and then infer activity dependencies
C.Level resources, remove constraints, and then identify the critical path
D.Establish logic, calculate the unconstrained schedule, then level resources
Correct Answer: Establish logic, calculate the unconstrained schedule, then level resources
Explanation:
The logic-driven schedule should be calculated before resource leveling. This makes it possible to distinguish delays caused by dependencies from those introduced by resource constraints.
Incorrect! Try again.
47A monitoring framework defines metrics and reporting frequencies but repeatedly fails to trigger timely corrective action. Which missing element most directly explains the failure?
Creating frameworks
Hard
A.A larger number of performance indicators
B.A common color palette for all dashboards
C.Defined thresholds, owners, and escalation decisions
D.Daily replacement of the approved baseline
Correct Answer: Defined thresholds, owners, and escalation decisions
Explanation:
Metrics alone do not create control. A usable framework must specify when variance requires action, who owns the response, and how unresolved issues are escalated.
Incorrect! Try again.
48Three teams report weekly progress. Team A records status every Friday, Team B updates retrospectively on Monday, and Team C streams transactions continuously. Which control most improves comparability without discarding useful detail?
Data collection
Hard
A.Apply a common reporting cutoff and preserve event timestamps
B.Allow each team to select the period that shows its most current status
C.Average all values across the calendar month
D.Convert every transaction into an estimated completion percentage using a manager-selected weighting model before retaining any source records
Correct Answer: Apply a common reporting cutoff and preserve event timestamps
Explanation:
A common cutoff creates period consistency, while event timestamps preserve traceability and permit later reconciliation. Retrospective or selectively timed reporting can distort comparisons.
Incorrect! Try again.
49A dashboard shows 90% of activities complete, yet the forecast completion date is slipping. Which visualization would best reveal why activity-count progress is misleading?
Visualizing progress
Hard
A.A pie chart of completed and incomplete activity counts
B.A time-phased critical-path view weighted by remaining duration
C.A table ranking departments by total number of activities
D.A histogram of employee utilization percentages
Correct Answer: A time-phased critical-path view weighted by remaining duration
Explanation:
Activity counts treat small and large tasks equally. A duration-weighted critical-path view exposes whether the remaining work lies on schedule-driving activities.
Incorrect! Try again.
50A project reports and at the status date, but a critical supplier has announced a probable four-week delay that is not yet reflected in actual performance. What should the status report communicate?
Status reports
Hard
A.Schedule variance should immediately be recorded as four weeks
B.Current variances are zero, but the forecast and risk exposure have worsened
C.The baseline completion date should be moved before reporting the issue
D.The project is on plan, so the supplier issue should wait until variance occurs
Correct Answer: Current variances are zero, but the forecast and risk exposure have worsened
Explanation:
Earned value variances describe performance to date, not all future risk. The report should distinguish current status from the forecast impact of the supplier threat.
Incorrect! Try again.
51A milestone was originally planned for day 80. Successive monthly forecasts predict completion on days 82, 86, and 91. The latest baseline still shows day 80. Which conclusion is best supported?
Milestone analysis
Hard
A.The baseline should automatically be revised to day 91
B.The milestone has a current variance of zero because the baseline is unchanged
C.The milestone exhibits a worsening forecast trend requiring root-cause analysis
D.The milestone must be 11 days late in actual terms at the latest status date
Correct Answer: The milestone exhibits a worsening forecast trend requiring root-cause analysis
Explanation:
The sequence of forecasts shows progressive deterioration from 2 to 11 days. It signals a trend, but does not prove that the milestone is already late or justify automatic rebaselining.
Incorrect! Try again.
52A project has paid , accrued unpaid work of , and issued non-cancellable purchase orders for of undelivered equipment. Which amount best represents the project's current cost exposure?
Cost monitoring
Hard
A.
B.
C.
D.
Correct Answer:
Explanation:
Cost exposure includes paid costs, accruals, and firm commitments: . Monitoring only cash paid would materially understate exposure.
Incorrect! Try again.
53An approved scope change adds of work and two weeks to the schedule. Before approval, the project had unfavorable variances against the original baseline. How should the revised baseline be established?
Change control
Hard
A.Reset all historical variances to zero and restart earned value measurement
B.Add the approved change prospectively while retaining prior variances in performance history
C.Leave the baseline unchanged and manage approved work entirely as contingency
D.Add the change retroactively so earlier performance appears aligned with plan
Correct Answer: Add the approved change prospectively while retaining prior variances in performance history
Explanation:
Approved changes should update future baseline scope, time, and cost without erasing historical performance. Retroactive changes would conceal earlier execution variance.
Incorrect! Try again.
54A project can be shortened by up to three weeks. Each week of crashing adds in direct cost and saves in project-level indirect cost. After the second week, an additional coordination charge is incurred if a third week is crashed. Ignoring other effects, how many weeks should be crashed to minimize total cost?
Cost (direct and indirect)
Hard
A.Three weeks
B.Two weeks
C.One week
D.No weeks
Correct Answer: Two weeks
Explanation:
Each of the first two weeks saves a net . The third week adds while saving only , increasing cost by .
Incorrect! Try again.
55A project has $BAC = $800,000$, $PV = , $EV = $360,000$, and $AC = . If current cost efficiency is expected to continue for the remaining work, what is the most appropriate estimate at completion?
Earned value analysis
Hard
A.
B.
C.
D.
Correct Answer:
Explanation:
The cost performance index is . If that efficiency continues, .
Incorrect! Try again.
56A project has $BAC = $1,000,000$, $EV = , and $AC = $650,000$. What to-complete performance index is required to finish within the original budget?
Performance ratio
Hard
A.
B.
C.
D.
Correct Answer:
Explanation:
Using the original budget, . The remaining work must therefore achieve substantially better cost efficiency.
Incorrect! Try again.
57An AI dashboard predicts completion dates from live issue, commit, and timesheet data. After the organization changes its issue-closing policy, predicted delays fall sharply even though delivery throughput is unchanged. What is the most likely control failure?
AI in Monitoring: Use of AI for real-time project status dashboards
Hard
A.The model lacks monitoring for feature and concept drift
B.The system should accept the apparent improvement and automatically revise every milestone because live operational data is more reliable than approved plans
C.The dashboard uses too many real-time data sources
Correct Answer: The model lacks monitoring for feature and concept drift
Explanation:
The policy change altered the meaning and distribution of an input without improving actual delivery. Drift monitoring should detect that the model's learned relationship is no longer reliable.
Incorrect! Try again.
58An AI notification system detects 95% of genuine schedule threats but sends so many false alerts that managers ignore it. Which redesign most directly addresses the operational failure while retaining risk sensitivity?
Intelligent notifications
Hard
A.Suppress all alerts below 100% model confidence
B.Replace predictive alerts with a fixed weekly reminder
C.Send every detected anomaly to all managers with its full event history, model feature values, and raw probability trace so no potentially relevant information is omitted
D.Prioritize alerts by expected impact and confidence, with escalation thresholds
Correct Answer: Prioritize alerts by expected impact and confidence, with escalation thresholds
Explanation:
Impact- and confidence-based prioritization reduces alert fatigue while preserving attention to high-risk threats. Requiring certainty would miss genuine risks, and indiscriminate alerts would preserve the problem.
Incorrect! Try again.
59A project completion forecast is generated from a probabilistic model, but executives interpret the displayed date as a commitment. Which visualization best communicates forecast uncertainty without hiding the central estimate?
Progress visualization
Hard
A.A green indicator whenever the median precedes the target
B.A confidence band with percentile dates and a median forecast
C.A single completion date displayed in a large font
D.A cumulative count of tasks closed during the current week
Correct Answer: A confidence band with percentile dates and a median forecast
Explanation:
A confidence band displays the forecast distribution, while percentile dates and the median provide interpretable reference points. A single date conceals uncertainty.
Incorrect! Try again.
60A project has $BAC = $2,000,000$, $EV = , $AC = $1,000,000$, and $PV = . Management expects the remaining work to be affected by both the observed cost and schedule inefficiencies. Using , what is the approximate estimate at completion?
Earned value analysis
Hard
A. million
B. million
C. million
D. million
Correct Answer: million
Explanation:
Here, and . Thus, million.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →