Unit 3: Tasks - Practice Quiz

INT416 — Software Project Management Laboratory 60 Questions
0 Correct 0 Wrong 60 Left
0/60

1 In a project management application, where is a new task name commonly entered?

Entering Tasks Easy
A. Task Name column
B. Resource Name column
C. Project Summary field
D. Status Bar field

2 Which entry represents a task duration of five working days?

Entering A Task Duration Easy
A. 5m
B. 5h
C. 5w
D. 5d

3 Which source is most useful when estimating the duration of a familiar task?

Estimating Durations Easy
A. Project file name
B. Toolbar position
C. Task font color
D. Past project records

4 What does a milestone usually represent in a project schedule?

Understanding Milestones And Phases Easy
A. A significant event
B. A resource payment
C. A detailed and continuously updated record of every activity performed by all team members
D. A daily work period

5 What is a project phase?

Understanding Milestones And Phases Easy
A. A group of related tasks
B. A project calendar exception
C. A task completion value
D. A single resource assignment

6 Which activity is best entered as a recurring task?

Using Recurring Tasks Easy
A. Weekly team meeting
B. Initial software installation
C. One-time project approval
D. Final product delivery

7 Which setting determines how often a recurring task occurs?

Using Recurring Tasks Continued Easy
A. Recurrence pattern
B. Task priority
C. Resource rate
D. Completion percentage

8 Which action changes the name of an existing task?

Editing Tasks Easy
A. Change the project calendar
B. Edit the Task Name field
C. Open the resource cost table and modify the standard hourly payment rate
D. Insert a recurring milestone

9 What does a higher task priority generally indicate?

Changing Task Priority Easy
A. The task must always become a milestone
B. The task has no assigned duration
C. The task should be protected from delay
D. The task has already been deleted

10 What usually happens when a task is inserted between two existing tasks?

Inserting A Task Easy
A. A new task row is added
B. All resources are removed
C. Every existing task is converted into an automatically scheduled recurring task
D. The project file is closed

11 What is the result of deleting a task?

Deleting Tasks Easy
A. The task is changed into a milestone
B. The task is moved to another project phase
C. The task is removed from the schedule
D. The task is assigned a higher priority

12 Why would a project manager move a task?

Moving Tasks Easy
A. To convert every task into a milestone
B. To permanently remove all task dependencies, assignments, notes, and calendar settings
C. To calculate the total resource cost
D. To change its position in the task list

13 Which field is used to arrange tasks according to their importance?

Arranging tasks using priority Easy
A. Actual Cost
B. Priority
C. Duration
D. Task Name

14 Who directly controls the scheduling information of a manually scheduled task?

Manually scheduled tasks Easy
A. The printing service
B. The project user
C. The operating system
D. The resource cost report

15 What commonly determines the dates of an automatically scheduled task?

Automatically scheduled tasks Easy
A. File name and location
B. Dependencies and calendars
C. Font size and color
D. Report margins and orientation

16 What does switching task mode change?

Switch task modes Easy
A. How all completed projects are permanently stored in an external database
B. How resource costs are paid
C. How the project is printed
D. How the task is scheduled

17 What is the main purpose of making a task inactive?

Simplified planning with inactive tasks Easy
A. To keep it without affecting the current schedule
B. To assign it the highest priority
C. To duplicate it across every available project file
D. To mark it as fully completed

18 What does tracking a project as scheduled usually indicate?

Tracking a Project as Scheduled Easy
A. Work is progressing according to the plan
B. No task has an assigned resource
C. Every task has been permanently deleted
D. The project schedule has been replaced with a detailed financial accounting statement

19 Which completion percentage means that a task is finished?

Entering a Task’s Completion Percentage Easy
A. 0%
B. 50%
C. 100%
D. 75%

20 What does the actual duration of a task record?

Entering Actual Values for Tasks Easy
A. The original name of the task
B. The total time planned for every task and resource in all phases of the project
C. The time already spent on the task
D. The priority assigned to the task

21 A project manager is creating a schedule before reliable duration estimates are available. What is the most appropriate initial action?

Entering Tasks Medium
A. Enter task names and refine their scheduling details later
B. Enter only resources and allow tasks to appear automatically
C. Enter milestones and omit all supporting activities
D. Enter completion percentages instead of individual task names

22 A task requires three working days, but a weekend occurs between its start and finish. If the project calendar treats weekends as nonworking time, which duration should be entered?

Entering A Task Duration Medium
A. 72 hours
B. 1 week
C. 3 days
D. 5 days

23 An optimistic estimate is 4 days, a most likely estimate is 7 days, and a pessimistic estimate is 10 days. Using the PERT weighted average, what is the estimated duration?

Estimating Durations Medium
A. 6 days
B. 9 days
C. 8 days
D. 7 days

24 Which schedule structure best represents a testing phase that ends with formal customer approval?

Understanding Milestones And Phases Medium
A. A testing summary task containing activities and a zero-duration approval milestone
B. An inactive testing task containing a manually scheduled approval activity
C. A recurring testing task followed by an automatically completed approval task
D. A testing milestone containing activities and a five-day approval summary task

25 A status meeting must occur every Monday from project start until project completion. Which approach creates the clearest schedule?

Using Recurring Tasks Medium
A. Create one recurring task with a weekly Monday pattern
B. Create one long task covering the entire project period
C. Create one milestone and assign every Monday as work
D. Create one summary task with no individual occurrences

26 A monthly review is scheduled for the first Friday of each month, but one occurrence falls on a company holiday. What primarily determines how that occurrence is scheduled?

Using Recurring Tasks Continued Medium
A. The project summary task duration
B. The task's completion percentage
C. The applicable working-time calendar
D. The resource's leveling priority

27 A task was entered as "Prepare report" but should be renamed without changing its dates, duration, or links. Which edit is most appropriate?

Editing Tasks Medium
A. Convert the task into a project milestone
B. Delete the task and create a replacement task
C. Move the task beneath a different summary task
D. Edit only the value in the Task Name field

28 Two tasks compete for the same resource during resource leveling. Task X has priority 900 and Task Y has priority 300. What is the expected effect of these values?

Changing Task Priority Medium
A. Task X is less likely to be delayed than Task Y
B. Task Y receives more resource units than Task X
C. Task Y becomes inactive until Task X is completed
D. Task X automatically starts before every linked task

29 A missing review activity must be added between two existing tasks in a schedule. What should the project manager verify after inserting it?

Inserting A Task Medium
A. Its baseline is automatically copied from both neighbors
B. Its priority is higher than all nearby tasks
C. Its actual work equals the preceding task's work
D. Its dependencies and outline level are correct

30 A linked task is deleted from the middle of a schedule. What is the most important immediate check?

Deleting Tasks Medium
A. Whether completed tasks have returned to zero percent
B. Whether the project calendar has changed to elapsed time
C. Whether all remaining tasks now have identical priorities
D. Whether predecessor and successor relationships still represent the workflow

31 A task is moved from one phase to another by cutting and pasting its entire row. Which result should be checked first?

Moving Tasks Medium
A. Whether its duration has automatically changed to zero
B. Whether its completion percentage matches the new phase
C. Whether its assigned resource has been permanently deleted
D. Whether its outline position and task links remain appropriate

32 A manager wants critical deployment work protected from leveling delays while allowing documentation work to move. Which priority assignment is most suitable?

Arranging tasks using priority Medium
A. Deployment 0 and documentation 1000
B. Deployment 200 and documentation 900
C. Deployment 900 and documentation 200
D. Deployment 500 and documentation 500

33 A manually scheduled task has a typed start date and duration but is linked to a predecessor that finishes later. What should the manager expect?

Manually scheduled tasks Medium
A. The predecessor is deleted to preserve the typed start date
B. The task is automatically converted into a recurring task
C. The task may retain its entered dates and show a scheduling warning
D. The task must always move automatically after the predecessor

34 An automatically scheduled task has a finish-to-start predecessor and no restrictive constraint. The predecessor moves two working days later. What usually happens?

Automatically scheduled tasks Medium
A. The successor becomes manually scheduled
B. The successor's duration becomes two days
C. The successor keeps its original start date
D. The successor is recalculated to start later

35 A manually scheduled task contains incomplete planning information. Before switching it to automatic scheduling, what should be checked?

Switch task modes Medium
A. Its font, row color, gridline style, and note icon
B. Its duration, dependencies, constraints, and calendar information
C. Its baseline cost, status report title, and zoom level
D. Its recurring pattern, report theme, and print margins

36 A team wants to compare a schedule with and without an optional training activity while keeping the activity's details available. What should it do?

Simplified planning with inactive tasks Medium
A. Delete the training task permanently
B. Convert the training task into a summary task
C. Make the training task inactive
D. Set the training task to 100 percent complete

37 Several tasks were completed exactly according to the baseline through the current status date. Which tracking action is most efficient?

Tracking a Project as Scheduled Medium
A. Increase every completed task's priority to 1000
B. Delete completed tasks from the active project schedule
C. Update the completed work as scheduled through the status date
D. Re-enter every baseline start and finish as actual values

38 A task has a duration of 10 days and progress is recorded as 40 percent complete. Assuming progress is distributed according to duration, how much actual duration is represented?

Entering a Task’s Completion Percentage Medium
A. 6 days
B. 2 days
C. 4 days
D. 8 days

39 A task actually started one day late and has used 18 hours of work so far. Which entries best capture this progress?

Entering Actual Values for Tasks Medium
A. Actual Start and Actual Work
B. Baseline Start and Remaining Cost
C. Deadline and Baseline Duration
D. Constraint Date and Planned Work

40 A task was planned for 8 days. After 3 actual days of work, the team estimates that 6 more days are required. What duration is the task now expected to have?

Entering Actual Values for Tasks Medium
A. 11 days
B. 8 days
C. 6 days
D. 9 days

41 A project manager enters three tasks and links them Finish-to-Start: Design, Build, and Test. Before durations are entered, all three are manually scheduled. Which result is most likely?

Entering Tasks Hard
A. The tasks become milestones because their durations have not been specified
B. The tasks retain incomplete scheduling information until dates or durations are supplied
C. The tasks immediately receive calculated one-day durations and sequential dates
D. The tasks automatically switch to automatic scheduling when they are linked

42 A task starts at 8:00 AM Monday on a calendar with 8-hour working days and weekends off. Ignoring holidays, how does a duration of 3ed differ from 3d?

Entering A Task Duration Hard
A. 3ed ends Wednesday at 5:00 PM, while 3d ends Thursday at 8:00 AM
B. 3ed ends Thursday at 8:00 AM, while 3d ends Wednesday at 5:00 PM
C. Both durations end Thursday at 8:00 AM because calendars do not affect durations
D. Both durations end Wednesday at 5:00 PM because a day always means 24 hours

43 Using the PERT weighted-average estimate , what duration should be entered when the optimistic, most likely, and pessimistic estimates are 4, 7, and 16 days?

Estimating Durations Hard
A. 8 days
B. 9 days
C. 7 days
D. 10 days

44 A five-day approval task must be displayed as a milestone without losing its duration. Which configuration best preserves both the schedule calculation and the milestone symbol?

Understanding Milestones And Phases Hard
A. Assign a deadline equal to the finish date and remove the duration
B. Change the duration to zero and retain the original start date
C. Convert the task into a summary task containing no subtasks
D. Keep the five-day duration and set the task's milestone property

45 A weekly inspection is created as a recurring task for 12 Mondays. A holiday calendar exception makes one Monday nonworking. What should the manager verify instead of assuming the series is correct?

Using Recurring Tasks Hard
A. Whether every occurrence was deleted because one date became nonworking
B. Whether the affected occurrence moved or conflicts with the applicable calendar
C. Whether all occurrences automatically changed into elapsed-duration tasks
D. Whether the recurring summary inherited a mandatory finish constraint

46 A recurring status meeting creates a summary task with 20 occurrence subtasks. The manager changes only the duration of the fifth occurrence. What is the expected scope of that edit?

Using Recurring Tasks Continued Hard
A. The recurring summary changes duration but its occurrences remain unchanged
B. All 20 occurrences change because the summary controls every duration
C. All later occurrences change because they inherit from the edited occurrence
D. Only the fifth occurrence changes unless the recurring series is redefined

47 An automatically scheduled task has a duration of 10 days, is 40% complete, and has no resource-driven recalculation. Its duration is edited to 15 days while its completion percentage remains unchanged. Which duration values are consistent afterward?

Editing Tasks Hard
A. Actual duration 6 days and remaining duration 11 days
B. Actual duration 4 days and remaining duration 11 days
C. Actual duration 4 days and remaining duration 9 days
D. Actual duration 6 days and remaining duration 9 days

48 Two otherwise equivalent resource-overallocated tasks can be delayed by leveling. Task X has priority 900 and Task Y has priority 200. Under priority-sensitive leveling, which outcome is expected?

Changing Task Priority Hard
A. Both tasks are protected equally because only priority 1000 is evaluated
B. Both tasks are delayed equally because priority affects sorting only
C. Task Y is more likely to be delayed because its priority is lower
D. Task X is more likely to be delayed because its priority is higher

49 A new task is inserted between tasks with IDs 18 and 19. Existing dependencies were created by task links rather than by typing dates. What is the most accurate statement?

Inserting A Task Hard
A. The lower task IDs change, but dependency references continue to identify their tasks
B. The predecessor links break because task IDs are permanent dependency keys
C. The inserted task automatically joins every dependency that crossed the insertion point
D. The inserted task inherits the predecessor and successor links of task 18

50 A phase summary task contains six subtasks, including linked and resource-assigned work. What is the principal consequence of deleting the summary task row?

Deleting Tasks Hard
A. Only the summary is deleted and all subtasks become top-level tasks
B. The summary and all of its subtasks are deleted from the plan
C. The summary becomes inactive while all subtasks remain normally scheduled
D. Only unlinked subtasks are deleted while linked subtasks are retained

51 A summary task with four subtasks is moved below another phase using a row-move operation. Which result best preserves the work breakdown structure?

Moving Tasks Hard
A. The subtasks move but become independent top-level tasks automatically
B. Only the summary row moves while the subtasks remain at their old IDs
C. The summary moves and all dependency links to external tasks are removed
D. The summary moves together with all four subtasks as one hierarchy

52 A manager sorts a task table by the Priority field in descending order and selects the option to keep the outline structure. Which effect should be expected?

Arranging tasks using priority Hard
A. Task priorities are rewritten to match the resulting top-to-bottom row order
B. Low-priority tasks are delayed until every high-priority task has finished
C. Tasks are reordered for display within the outline, but dates are not recalculated merely by sorting
D. High-priority tasks receive earlier starts even when dependencies prohibit those dates

53 A manually scheduled successor is set to start on June 10, but its automatically scheduled predecessor slips and finishes on June 14. No explicit edit is made to the successor. What is the key scheduling risk?

Manually scheduled tasks Hard
A. The successor must move to June 15 because every link enforces movement
B. The successor must become inactive until the conflict is manually resolved
C. The predecessor must shorten so that it finishes before June 10
D. The successor may remain on June 10 and expose a dependency conflict

54 An automatically scheduled task has two Finish-to-Start predecessors that finish on May 8 and May 12. It has no lag, constraint, or calendar exception. What determines its earliest start?

Automatically scheduled tasks Hard
A. The average of both predecessor finish dates, rounded to a working day
B. The task's original typed start, because automatic scheduling preserves it
C. The later predecessor finish, adjusted to the next available working time
D. The earlier predecessor finish, because the first entered link controls the task

55 A manually scheduled task has typed dates that conflict with its predecessor link. The task is switched to automatic scheduling. Which outcome is most likely?

Switch task modes Hard
A. Project deletes the predecessor link before recalculating the task dates
B. Project preserves both typed dates and ignores every existing dependency
C. Project recalculates the task from links, constraints, calendars, and duration
D. Project converts the typed dates into actual start and actual finish values

56 A proposed task lies between Design and Deployment in a linked chain. The manager inactivates the proposed task to evaluate the plan without deleting it. What is the intended result?

Simplified planning with inactive tasks Hard
A. The task remains scheduled and contributes work but is hidden from reports
B. The task becomes a zero-duration milestone that still controls Deployment
C. The task remains recorded but no longer affects the active schedule or assignments
D. The task is permanently deleted while its predecessor links remain visible

57 At the status date, several tasks were completed exactly as originally scheduled, while future tasks have not started. Which tracking action most directly records the elapsed scheduled work without individually entering every actual value?

Tracking a Project as Scheduled Hard
A. Update the project as complete through the status date
B. Reschedule every uncompleted task before the status date
C. Set the project finish constraint to the status date
D. Replace the current schedule with a new baseline

58 A task has a duration of 12 days and is marked 75% complete. Under duration-based percent-complete tracking, what values should Project derive before other constraints or actual entries intervene?

Entering a Task’s Completion Percentage Hard
A. Actual duration 9 days and remaining duration 4 days
B. Actual duration 8 days and remaining duration 4 days
C. Actual duration 9 days and remaining duration 3 days
D. Actual duration 3 days and remaining duration 9 days

59 A task was planned to start Monday, but the manager enters an Actual Start of Wednesday. No earlier actual work exists. What is the most defensible interpretation?

Entering Actual Values for Tasks Hard
A. The task is set to 100% complete because an actual date was entered
B. The baseline start automatically changes to Wednesday to remove the variance
C. The task's recorded actual start becomes Wednesday and tracking variance may increase
D. The actual start remains Monday because planned dates cannot be overridden

60 A fixed-duration task has Duration = 10 days, Actual Duration = 6 days, and Remaining Duration = 5 days after an update. What does this combination imply?

Entering Actual Values for Tasks Hard
A. The remaining duration must be rejected because it exceeds the original four days
B. The current duration remains 10 days because actual values never affect task duration
C. The actual duration must fall to five days so the original duration is preserved
D. The current duration has become 11 days because actual and remaining duration are combined