Unit 4: Task Linkages - Practice Quiz

INT416 — Software Project Management Laboratory 60 Questions
0 Correct 0 Wrong 60 Left
0/60

1 Why are project tasks arranged in a logical sequence?

Creating A Logical Sequence Easy
A. To assign identical task names
B. To show the correct order of work
C. To remove all project resources
D. To increase every task duration

2 Which task information can commonly be viewed or edited on the General tab of a Task Information dialog box?

Using The General Tab Easy
A. Printer model and paper size
B. Task name and duration
C. Project password and license
D. Application theme and language

3 What is a predecessor task?

Understanding Task Predecessors Easy
A. A task that controls a related later task
B. A task that is always completed last
C. A task that summarizes project costs
D. A task that has no assigned name

4 What does assigning a resource to a task indicate?

Understanding Task Resources Easy
A. How the project file will be printed
B. Which task must be deleted first
C. Where the task name will appear
D. Who or what will perform the work

5 Which setting is typically considered an advanced task option?

Understanding Advanced Task Options Easy
A. Project filename
B. Page orientation
C. Task calendar
D. Toolbar color

6 What does a task constraint do?

Understanding Task Constraints Easy
A. Selects the color of a task bar
B. Restricts when a task can start or finish
C. Creates a copy of the project file
D. Changes the spelling of a task name

7 Which of the following is a standard task type in project scheduling software?

Understanding Task Types Easy
A. Fixed Duration
B. Fixed Description
C. Fixed Predecessor
D. Fixed Summary

8 What is the main purpose of adding a note to a task?

Using Task Notes Easy
A. To convert the task into a resource
B. To automatically complete the entire task
C. To record extra information about the task
D. To permanently remove the task duration

9 What does indenting a task usually do in a project outline?

Outlining A Task Easy
A. Removes its link to every other task
B. Makes it the first task in the project
C. Changes it into a project resource
D. Makes it a subtask of the task above

10 What does a summary task represent?

Understanding Summary Tasks Easy
A. A group of related subtasks
B. A single project constraint
C. A list of available resources
D. A note attached to a milestone

11 How many standard task linkage types are commonly used in project scheduling?

Understanding Linkage Types Easy
A. Five
B. Two
C. Three
D. Four

12 In a Finish-to-Start relationship, when can the successor task begin?

Using A Finish To Start Relationship Easy
A. When the predecessor begins
B. After the predecessor finishes
C. When the successor finishes
D. Before the predecessor begins

13 What does a Start-to-Start relationship link?

Using A Start To Start Relationship Easy
A. The finish of one task to the finish of another
B. The start of one task to the start of another
C. The start of one task to the finish of another
D. The finish of one task to the start of another

14 What does a Finish-to-Finish relationship control?

Using A Finish To Finish Relationship Easy
A. Which resource receives a note
B. When the predecessor may start
C. Which summary task is displayed
D. When the successor may finish

15 In a Start-to-Finish relationship, what must happen before the successor can finish?

Using A Start To Finish Relationship Easy
A. The successor must become a summary task
B. The predecessor must finish
C. The predecessor must start
D. The successor must start again

16 Which relationship is most commonly used for simple task linkage?

Understanding Simple Linkage Easy
A. Finish-to-Start
B. Start-to-Start
C. Start-to-Finish
D. Finish-to-Finish

17 How are linked tasks commonly shown on a Gantt chart?

Spotting Linkages On A Gantt Chart Easy
A. By identical names for every task
B. By hiding the successor task bars
C. By connector lines between task bars
D. By notes placed above the timescale

18 What is lag time in a task relationship?

Understanding Lag And Lead Time Easy
A. A waiting period between linked tasks
B. An overlap period between linked tasks
C. The total duration of all tasks
D. The working time assigned to a resource

19 How does lead time affect two linked tasks on a Gantt chart?

Understanding Lead Time On The Gantt Chart Easy
A. It assigns both tasks the same resource
B. It removes the bars for both tasks
C. It forces both tasks to become milestones
D. It allows the tasks to overlap

20 Which action creates a summary task with subtasks in an outline?

Outline tasks into subtasks and summary tasks Easy
A. Delete the task above the lower tasks
B. Apply the same constraint to all tasks
C. Indent the lower tasks beneath a task
D. Assign one resource to every task

21 A project contains the tasks "Design interface," "Code module," "Test module," and "Deploy module." Which sequence best represents their logical order?

Creating A Logical Sequence Medium
A. Test module, Code module, Design interface, Deploy module
B. Design interface, Test module, Code module, Deploy module
C. Code module, Design interface, Deploy module, Test module
D. Design interface, Code module, Test module, Deploy module

22 In a task information dialog, which setting would most directly identify the task's name, duration, and scheduling status?

Using The General Tab Medium
A. The Notes tab
B. The General tab
C. The Resources tab
D. The Predecessors tab

23 Task B cannot begin until Task A has been completed. In a scheduling tool, how should Task A be identified for Task B?

Understanding Task Predecessors Medium
A. As Task B's constraint
B. As Task B's resource
C. As Task B's predecessor
D. As Task B's summary

24 A developer is assigned to a task and has a maximum availability of 50% during the task period. Which scheduling factor does this represent?

Understanding Task Resources Medium
A. Resource availability
B. Task constraint
C. Linkage duration
D. Task predecessor

25 A task must remain scheduled for exactly five working days even if additional resources are assigned. Which task type is most appropriate?

Understanding Advanced Task Options Medium
A. Fixed duration
B. Fixed units
C. Fixed work
D. Fixed sequence

26 A task is scheduled to begin only after a specified calendar date, regardless of predecessor dates. What is being applied?

Understanding Task Constraints Medium
A. A linkage label
B. A summary level
C. A task resource
D. A task constraint

27 If the amount of work remains constant while the number of assigned resources changes, which task type is generally suitable?

Understanding Task Types Medium
A. Fixed milestone
B. Fixed units
C. Fixed duration
D. Fixed work

28 A project manager wants to record testing assumptions without changing task dates or assignments. Which feature should be used?

Using Task Notes Medium
A. Task predecessors
B. Task constraints
C. Task notes
D. Resource calendars

29 What is the main purpose of indenting a task beneath another task in a project outline?

Outlining A Task Medium
A. To mark it complete
B. To make it a subtask
C. To remove its duration
D. To assign it a resource

30 A summary task displays a duration that spans all of its subtasks. What does this duration generally represent?

Understanding Summary Tasks Medium
A. The span from first start to last finish
B. The duration of the longest subtask
C. The sum of every subtask duration
D. The average duration of all subtasks

31 Which linkage type requires the predecessor to finish before the successor can start?

Understanding Linkage Types Medium
A. Start-to-finish
B. Finish-to-start
C. Finish-to-finish
D. Start-to-start

32 Task A is "Prepare build" and Task B is "Install build." If Task B should start only after Task A finishes, which relationship should be selected?

Using A Finish To Start Relationship Medium
A. Finish-to-finish
B. Start-to-start
C. Finish-to-start
D. Start-to-finish

33 Documentation may begin as soon as development begins, although development continues afterward. Which relationship best models this situation?

Using A Start To Start Relationship Medium
A. Finish-to-start
B. Finish-to-finish
C. Start-to-start
D. Start-to-finish

34 The review task must finish when the testing task finishes, but both tasks may start at different times. Which relationship is appropriate?

Using A Finish To Finish Relationship Medium
A. Finish-to-start
B. Start-to-finish
C. Finish-to-finish
D. Start-to-start

35 An old support shift can finish only after the new support shift has started. Which relationship represents this dependency?

Using A Start To Finish Relationship Medium
A. Finish-to-finish
B. Start-to-finish
C. Start-to-start
D. Finish-to-start

36 A simple linkage between two tasks is primarily used to represent what?

Understanding Simple Linkage Medium
A. A change in task hierarchy
B. A dependency between task dates
C. A permanent resource assignment
D. A note attached to a task

37 On a Gantt chart, dependency lines connect the end of one task bar to the beginning of another task bar. Which relationship is most likely shown?

Spotting Linkages On A Gantt Chart Medium
A. Finish-to-finish
B. Finish-to-start
C. Start-to-finish
D. Start-to-start

38 Task B has a two-day lag after Task A finishes. When can Task B start relative to Task A's finish?

Understanding Lag And Lead Time Medium
A. At the same time
B. Two working days earlier
C. Two working days later
D. At the next project milestone

39 A successor task has 25% lead time on a finish-to-start link with a predecessor lasting eight working days. Approximately how much overlap does this create?

Understanding Lead Time On The Gantt Chart Medium
A. Six working days
B. Two working days
C. Eight working days
D. Four working days

40 Which constraint type gives the scheduler the greatest flexibility because it does not force a task to a specific date?

Understanding The Types Of Constraints Medium
A. As soon as possible
B. Finish no later than
C. Start no earlier than
D. Must start on

41 A project contains these tasks: approve architecture, provision test environment, develop module, deploy module, and execute system tests. Development may begin only after architecture approval. Environment provisioning may occur in parallel with development. Deployment requires both development and provisioning to finish, and testing begins after deployment. Which dependency structure best represents the logical sequence?

Creating A Logical Sequence Hard
A. Approval → Provisioning; Provisioning → Development; Development → Deployment; Deployment → Testing
B. Approval → Deployment; Development → Deployment; Provisioning → Testing; Deployment → Testing
C. Approval → Development; Provisioning → Deployment; Development → Deployment; Deployment → Testing
D. Approval → Development; Development → Provisioning; Provisioning → Deployment; Deployment → Testing

42 A 10-day task is reported as 50% complete, but only 3 days of actual duration have been recorded. A manager wants the schedule to reflect the reported completion directly without creating or editing resource assignments. Which change on the task's General tab most directly addresses the request?

Using The General Tab Hard
A. Set the task as a milestone
B. Set Percent Complete to 50%
C. Set Priority to 500
D. Set Duration to 5 days

43 Task D has two predecessors: A with FS+2d and B with SS+1d. A finishes on day 8, B starts on day 10, and calendars introduce no nonworking time. What is the earliest day on which D can start?

Understanding Task Predecessors Hard
A. Day 12
B. Day 11
C. Day 10
D. Day 9

44 A fixed-work task has hours of work, a duration of working days, and one resource assigned at 100%, assuming 8-hour days. A second equally capable resource is added at 100%, and effort-driven scheduling applies. What is the expected result?

Understanding Task Resources Hard
A. Work remains 80 hours and duration becomes 5 days
B. Work becomes 160 hours and duration remains 10 days
C. Work remains 80 hours and duration remains 10 days
D. Work becomes 40 hours and duration becomes 5 days

45 A task should remain automatically scheduled from its dependencies, but management wants a visible warning if it finishes after 30 June. Which advanced task setting should be used?

Understanding Advanced Task Options Hard
A. Enter 30 June as the actual finish
B. Set a Finish No Later Than constraint
C. Set a 30 June deadline
D. Set a Must Finish On constraint

46 A successor has an FS dependency that would schedule it on 12 August, but it also has a Start No Earlier Than constraint dated 15 August. Assuming no other restrictions, when will the successor start?

Understanding Task Constraints Hard
A. The project start date
B. 12 August
C. 15 August
D. 13 August

47 A task is configured as Fixed Duration with a duration of 5 days. It initially has one resource at 100%, producing 40 hours of work under an 8-hour calendar. If the assignment is changed to 50%, what values should result?

Understanding Task Types Hard
A. Duration 10 days and work 40 hours
B. Duration 2.5 days and work 20 hours
C. Duration 5 days and work 40 hours
D. Duration 5 days and work 20 hours

48 A scheduler must retain the reason for a task-duration estimate so that it travels with the project file but does not alter scheduling calculations or appear as a dependency. Where should the information be stored?

Using Task Notes Hard
A. In the task's Notes field
B. In the task's constraint type
C. In the task's resource names field
D. In the task's predecessor field

49 Tasks 4 through 7 are selected and indented beneath task 3. Task 3 was previously an ordinary scheduled task with its own entered duration. What structural and scheduling change should be expected?

Outlining A Task Hard
A. Task 3 becomes a summary task whose span is derived from tasks 4 through 7
B. Task 3 becomes a milestone whose date equals the start of task 4
C. Tasks 4 through 7 become predecessors of task 3 automatically
D. Task 7 becomes a summary task containing tasks 3 through 6

50 A summary task contains three subtasks: X runs Monday through Wednesday, Y runs Tuesday through Friday, and Z runs the following Monday through Tuesday. The weekend is nonworking time. What does the summary task represent?

Understanding Summary Tasks Hard
A. The average start and finish dates of the subtasks
B. A span from Monday through the following Tuesday, including the gap
C. A span from Tuesday through Friday, excluding task Z
D. The sum of all subtask durations, scheduled consecutively

51 Task B must start 2 days after Task A starts, while Task C must finish at the same time Task A finishes. Which pair of dependency specifications correctly models these requirements?

Understanding Linkage Types Hard
A. A→B FF+2d; A→C SS
B. A→B SS-2d; A→C FS
C. A→B FS+2d; A→C SF
D. A→B SS+2d; A→C FF

52 Coding finishes at the end of Tuesday. Testing has an FS+1d dependency on coding. Wednesday is a normal working day, and there are no calendar exceptions. When can testing begin?

Using A Finish To Start Relationship Hard
A. At the start of Thursday
B. At the start of Friday
C. At the start of Wednesday
D. At the end of Thursday

53 Excavation lasts 8 days. Inspection is linked to excavation with SS+75%, where the percentage lag is based on the predecessor's duration. Assuming continuous working days, when can inspection start?

Using A Start To Start Relationship Hard
A. 4 days after excavation starts
B. 2 days after excavation starts
C. 6 days after excavation starts
D. 8 days after excavation starts

54 Task A is scheduled to finish on day 20. Task B has an FF-3d relationship with A and is 5 days long. With no other restrictions, what schedule is implied for Task B?

Using A Finish To Finish Relationship Hard
A. Start on day 18 and finish on day 23
B. Start on day 12 and finish on day 17
C. Start on day 15 and finish on day 20
D. Start on day 17 and finish on day 22

55 A legacy monitoring shift must not finish until the replacement monitoring shift begins. Which dependency correctly represents this handover if the legacy shift is the successor task?

Using A Start To Finish Relationship Hard
A. Replacement → Legacy using FS
B. Replacement → Legacy using SF
C. Legacy → Replacement using FF
D. Legacy → Replacement using SS

56 Tasks A, B, C, and D are selected in that order and linked using the standard Link Tasks command. No links existed previously. Which dependency network is normally created?

Understanding Simple Linkage Hard
A. A→B, A→C, and A→D using FS links
B. A→B, B→C, and C→D using FS links
C. A→B, B→C, and C→D using SS links
D. A→D, B→D, and C→D using FF links

57 On a Gantt chart, a dependency line leaves the right edge of Task A's bar and enters the right edge of Task B's bar. Ignoring lag and arrow-rendering variations, which linkage type does this geometry indicate?

Spotting Linkages On A Gantt Chart Hard
A. Finish-to-Start
B. Finish-to-Finish
C. Start-to-Finish
D. Start-to-Start

58 Task B has an FS-25% dependency on Task A. Task A has a duration of 12 working days. Assuming percentage lead is calculated from the predecessor's duration, what does the link permit?

Understanding Lag And Lead Time Hard
A. B may start 3 working days after A finishes
B. B may finish 3 working days before A starts
C. B may start 3 working days before A finishes
D. B may finish 9 working days after A finishes

59 A Gantt chart shows Task B beginning while Task A is still in progress. The dependency is FS-2d, and removing the link causes B to move earlier rather than later because another constraint then controls it. Which interpretation is correct?

Understanding Lead Time On The Gantt Chart Hard
A. The overlap proves the tasks have a Start-to-Start link and no constraint
B. The negative lag delays B until two days after A finishes
C. The chart proves Task A is manually scheduled and has no predecessor
D. The overlap represents two days of lead, but the link is not necessarily B's only scheduling driver

60 In a project scheduled from its start date, which ordering correctly ranks these constraints from least restrictive to most restrictive: As Soon As Possible, Start No Earlier Than, and Must Start On?

Understanding The Types Of Constraints Hard
A. Must Start On → Start No Earlier Than → As Soon As Possible
B. Start No Earlier Than → As Soon As Possible → Must Start On
C. As Soon As Possible → Must Start On → Start No Earlier Than
D. As Soon As Possible → Start No Earlier Than → Must Start On