Unit 11: Tracking Progress - Subjective Questions

INT416 — Software Project Management Laboratory • Practice Questions with Detailed Answers

20 questions

1

Define a project baseline and explain its purpose in tracking project progress.

2

Describe the procedure for saving a baseline in a project management application.

3

Distinguish between a baseline plan, a current plan, and actual project data.

4

Explain how actual start, actual finish, actual work, and actual cost values are used to track a task.

5

Define schedule variance and cost variance. Show how each can be calculated from baseline and current or actual values.

6

A task has a baseline duration of 8 days and a baseline cost of . Its current duration is 11 days, and its actual or forecast cost is . Calculate and interpret the duration and cost variances.

7

Why should a baseline not be replaced every time the project schedule changes? Explain when resetting a baseline may be justified.

8

Explain the meaning of the status date and its role in updating a project schedule.

9

Describe the main steps involved in updating a project schedule during a regular reporting cycle.

10

Compare updating a task by percentage complete with updating it by actual and remaining work.

11

Differentiate between task-level updating and project-level updating.

12

What happens to successor tasks when the actual finish of a predecessor is later than its baseline finish? Explain the factors that determine the result.

13

Explain how to handle incomplete work that appears before the status date in an updated schedule.

14

Describe how a tracking Gantt chart helps compare actual progress with the baseline.

15

Explain how project managers should analyze a task that shows a large finish variance.

16

What are custom fields in project management software, and how can they support progress tracking? Give suitable examples.

17

Describe the steps for creating and using a custom variance indicator field.

18

Explain the purpose and process of customizing toolbars or the quick-access interface for progress tracking.

19

Compare the Update Task command with the Update Project command in schedule-tracking software.

20

Develop a complete progress-tracking workflow for a weekly software project review, covering baseline comparison, schedule updating, task and project updates, and interface customization.