Notice: Due to an ongoing migration of our storage and publishing system, material requested since last month will not be uploaded for the time being, and new requests are paused. All existing notes remain available.

Unit 12 subjective questions Use a PERT analysis to estimate task durations

INT416 — Software Project Management Laboratory 20 questions with model answers. Write yours first, then compare.

Read the notes Practice MCQs
  1. Question 1 of 20

    Define PERT analysis and state its purpose in software project management.

  2. Question 2 of 20

    Explain the three duration estimates used in a PERT analysis with a suitable software project example.

  3. Question 3 of 20

    Derive the default PERT expected-duration formula and explain the significance of its weights.

  4. Question 4 of 20

    Calculate the expected duration of a task using the default PERT weights if days, days, and days. Interpret the result.

  5. Question 5 of 20

    Describe the procedure for performing a PERT analysis using the default duration-estimate weights in project management software.

  6. Question 6 of 20

    Distinguish between deterministic task-duration estimation and PERT-based task-duration estimation.

  7. Question 7 of 20

    Explain why the most likely estimate is assigned a weight of in the default PERT calculation.

  8. Question 8 of 20

    A task has estimates hours, hours, and hours. Calculate its expected duration, standard deviation, and variance using conventional PERT formulas.

  9. Question 9 of 20

    What are PERT weights? Explain how changing them affects the calculated task duration.

  10. Question 10 of 20

    Calculate and compare the duration of a task with days, days, and days using (a) default weights and (b) risk-averse weights .

  11. Question 11 of 20

    Describe how to change the way project management software weights PERT duration estimates.

  12. Question 12 of 20

    Compare the effects of optimistic, balanced, and pessimistic PERT weighting strategies.

  13. Question 13 of 20

    Explain the importance of saving a backup or baseline before calculating PERT durations in a project schedule.

  14. Question 14 of 20

    Discuss the factors a software project manager should consider while selecting optimistic, most likely, and pessimistic task durations.

  15. Question 15 of 20

    For three sequential tasks, the estimates are Task A: days, Task B: days, and Task C: days, where each tuple represents . Calculate the expected project duration using default PERT weights.

  16. Question 16 of 20

    Explain how PERT analysis can affect a project's critical path and completion date.

  17. Question 17 of 20

    Differentiate between changing the three duration estimates and changing the PERT weights.

  18. Question 18 of 20

    Analyze the advantages and limitations of using PERT analysis for software task-duration estimation.

  19. Question 19 of 20

    How should a project manager interpret a task whose optimistic and pessimistic durations are very far apart?

  20. Question 20 of 20

    Design a complete PERT-based workflow for estimating, calculating, validating, and monitoring software project tasks.

That's unit 12

Long answers stick best when they're tested again soon. Run the MCQs on this unit, then come back to the questions you found hardest.