Correct Answer: To view how the project will look when printed
Explanation:
Print Preview displays the expected printed layout before the document is sent to a printer.
Incorrect! Try again.
2When should Print Preview normally be used?
Using Print Preview
Easy
A.Before assigning a resource
B.Before entering task durations
C.Before creating the first task
D.Before printing a project report
Correct Answer: Before printing a project report
Explanation:
Using Print Preview before printing helps identify layout and formatting problems.
Incorrect! Try again.
3Which layout problem can be identified using Print Preview?
Using Print Preview
Easy
A.A resource having insufficient skills
B.A milestone having no assigned resource
C.Content being cut off at a page edge
D.A task having an incorrect predecessor
Correct Answer: Content being cut off at a page edge
Explanation:
Print Preview helps reveal whether text, tables, or charts extend beyond the printable page.
Incorrect! Try again.
4Which page setting controls whether a report prints vertically or horizontally?
Using Print Preview
Easy
A.Task priority
B.Resource rate
C.Page orientation
D.Project baseline
Correct Answer: Page orientation
Explanation:
Page orientation determines whether the printed page uses portrait or landscape format.
Incorrect! Try again.
5Which orientation is usually suitable for a wide project table?
Using Print Preview
Easy
A.Portrait orientation
B.Reverse orientation
C.Landscape orientation
D.Default orientation
Correct Answer: Landscape orientation
Explanation:
Landscape orientation provides more horizontal space for wide tables and charts.
Incorrect! Try again.
6What do page margins control in a printed project report?
Using Print Preview
Easy
A.The blank space around page content
B.The cost assigned to each resource
C.The duration of each project task
D.The links between scheduled tasks
Correct Answer: The blank space around page content
Explanation:
Margins define the empty space between the report content and the edges of the printed page.
Incorrect! Try again.
7What does the page navigation feature in Print Preview allow a user to do?
Using Print Preview
Easy
A.Move resources between assignments
B.Move tasks between project phases
C.Move between previewed pages
D.Move costs between budget categories
Correct Answer: Move between previewed pages
Explanation:
Page navigation controls let the user inspect each page of a multi-page report.
Incorrect! Try again.
8What is the purpose of the zoom control in Print Preview?
Using Print Preview
Easy
A.To change the on-screen preview size
B.To enlarge the project team size
C.To increase every task's duration
D.To extend the project finish date
Correct Answer: To change the on-screen preview size
Explanation:
Zoom makes the preview appear larger or smaller on the screen without changing project data.
Incorrect! Try again.
9What should a user do after noticing an incorrect page orientation in Print Preview?
Using Print Preview
Easy
A.Change the page setup settings
B.Delete the project summary task
C.Replace the project calendar
D.Remove all resource assignments
Correct Answer: Change the page setup settings
Explanation:
Page setup contains printing options such as orientation, margins, and scaling.
Incorrect! Try again.
10Which information can commonly be checked in Print Preview?
Using Print Preview
Easy
A.Task dependency logic
B.Team communication quality
C.Headers and footers
D.Resource skill levels
Correct Answer: Headers and footers
Explanation:
Print Preview shows page elements such as headers, footers, margins, and report content.
Incorrect! Try again.
11What is the primary purpose of the Project Summary Report?
Using The Project Summary Report
Easy
A.To record notes for each assignment
B.To present an overview of the project
C.To edit individual resource calendars
D.To create links between every task
Correct Answer: To present an overview of the project
Explanation:
The Project Summary Report presents important project information in a concise, high-level form.
Incorrect! Try again.
12Which information is commonly included in a Project Summary Report?
Using The Project Summary Report
Easy
A.Overall project start and finish dates
B.Email messages sent by team members
C.Source code for the project software
D.Personal passwords of project resources
Correct Answer: Overall project start and finish dates
Explanation:
A Project Summary Report commonly includes major schedule information such as start and finish dates.
Incorrect! Try again.
13Which project value may appear in a Project Summary Report?
Using The Project Summary Report
Easy
A.Printer purchase date
B.Office room number
C.Total project cost
D.Monitor screen size
Correct Answer: Total project cost
Explanation:
The report may display total cost along with other overall project statistics.
Incorrect! Try again.
14Who is most likely to use a Project Summary Report?
Using The Project Summary Report
Easy
A.A designer selecting office furniture
B.A visitor requesting network access
C.A technician repairing a printer
D.A manager reviewing project status
Correct Answer: A manager reviewing project status
Explanation:
Managers and stakeholders use the report to review overall progress, schedule, work, and cost.
Incorrect! Try again.
15What level of information does the Project Summary Report mainly provide?
Using The Project Summary Report
Easy
A.Hardware installation commands
B.Individual employee passwords
C.Detailed programming instructions
D.High-level project information
Correct Answer: High-level project information
Explanation:
The report summarizes the project rather than presenting every scheduling detail.
Incorrect! Try again.
16Which measure in a Project Summary Report can indicate overall progress?
Using The Project Summary Report
Easy
A.Screen brightness level
B.Project percentage complete
C.Printer toner percentage
D.Network signal strength
Correct Answer: Project percentage complete
Explanation:
The project percentage complete gives a simple indication of overall project progress.
Incorrect! Try again.
17Where does a Project Summary Report obtain its information?
Using The Project Summary Report
Easy
A.From an unrelated spreadsheet file
B.From the printer configuration memory
C.From the computer's desktop wallpaper
D.From the current project schedule data
Correct Answer: From the current project schedule data
Explanation:
The report summarizes dates, work, costs, and progress stored in the current project plan.
Incorrect! Try again.
18Why should project data be updated before generating a Project Summary Report?
Using The Project Summary Report
Easy
A.To make the report reflect current status
B.To make the printer operate more quietly
C.To change the computer operating system
D.To improve the monitor's display resolution
Correct Answer: To make the report reflect current status
Explanation:
Updated project data helps ensure that the summary shows accurate schedule, cost, and progress information.
Incorrect! Try again.
19Which item is more suitable for the Project Summary Report than a detailed task report?
Using The Project Summary Report
Easy
A.Every task assignment note
B.Each resource's daily entry
C.Every dependency explanation
D.Overall project duration
Correct Answer: Overall project duration
Explanation:
Overall duration is a summary value, while detailed reports are better for individual task or assignment information.
Incorrect! Try again.
20What should be done before printing a Project Summary Report?
Using The Project Summary Report
Easy
A.Remove every assigned resource
B.Review the report in Print Preview
C.Delete all completed project tasks
D.Clear all recorded project costs
Correct Answer: Review the report in Print Preview
Explanation:
Print Preview helps confirm that the summary report is readable and properly arranged on each page.
Incorrect! Try again.
21A project schedule occupies two pages horizontally because a small portion of the Gantt chart extends onto the second page. Which Print Preview adjustment is most appropriate?
Using Print Preview
Medium
A.Change the orientation to portrait
B.Fit the content to one page wide
C.Increase the left and right margins
D.Increase the paper size setting
Correct Answer: Fit the content to one page wide
Explanation:
Fitting the content to one page wide reduces horizontal page breaks while allowing the schedule to continue across multiple pages vertically.
Incorrect! Try again.
22In Print Preview, task names are cut off even though unused space appears on the right side of the page. What should be adjusted before printing?
Using Print Preview
Medium
A.The project finish date
B.The resource assignment units
C.The report calculation mode
D.The Task Name column width
Correct Answer: The Task Name column width
Explanation:
Adjusting the Task Name column width uses the available page space and makes task descriptions more readable in the printed output.
Incorrect! Try again.
23A manager wants every printed page of a long schedule to identify the project and page number. Which feature should be configured?
Using Print Preview
Medium
A.Resource calendar settings
B.Header and footer settings
C.Task dependency settings
D.Baseline display settings
Correct Answer: Header and footer settings
Explanation:
Headers and footers can repeat information such as the project title, date, and page number on every printed page.
Incorrect! Try again.
24Print Preview shows a detailed schedule in portrait orientation with several columns continuing onto additional pages. Which change is most likely to improve horizontal readability?
Using Print Preview
Medium
A.Switch to landscape orientation
B.Change to a daily calendar
C.Increase the row height
D.Add more summary tasks
Correct Answer: Switch to landscape orientation
Explanation:
Landscape orientation provides more horizontal space, which is useful when printing views containing several columns.
Incorrect! Try again.
25A schedule must be printed for a meeting, but completed tasks from earlier months should not appear. What should be done before opening Print Preview?
Using Print Preview
Medium
A.Apply a filter to the current view
B.Clear the actual finish dates
C.Delete the completed task records
D.Remove the project baseline
Correct Answer: Apply a filter to the current view
Explanation:
Print Preview reflects the active view and its filters, so filtering hides unwanted tasks without deleting project data.
Incorrect! Try again.
26After selecting a printer with a smaller paper size, Print Preview displays additional page breaks. What is the most likely cause?
Using Print Preview
Medium
A.Less printable area is available
B.The project calendar was changed
C.Task durations were recalculated
D.Resource costs were reformatted
Correct Answer: Less printable area is available
Explanation:
A smaller paper size provides less printable space, so the same schedule may require more horizontal or vertical pages.
Incorrect! Try again.
27A printed Gantt Chart contains the required task table, but the chart portion consumes too much space. Which action best addresses the problem?
Using Print Preview
Medium
A.Change all tasks to milestones
B.Increase the number of task constraints
C.Replace resources with generic resources
D.Adjust the timescale shown in the view
Correct Answer: Adjust the timescale shown in the view
Explanation:
Changing the timescale can compress the visible date range and reduce the horizontal space required by the Gantt chart.
Incorrect! Try again.
28Print Preview shows the legend alone on an almost empty final page. Which print setting should be reviewed first?
Using Print Preview
Medium
A.Resource leveling priority
B.Cost accrual method
C.Task scheduling mode
D.Legend placement or display
Correct Answer: Legend placement or display
Explanation:
Changing where the legend appears, or disabling it when unnecessary, can prevent it from occupying a separate page.
Incorrect! Try again.
29A user changes the active schedule view after checking Print Preview and then prints without previewing again. Why might the output differ from the earlier preview?
Using Print Preview
Medium
A.Printing removes inactive resources
B.Printing automatically restores the baseline
C.Printing recalculates all fixed costs
D.Printing uses the currently active view
Correct Answer: Printing uses the currently active view
Explanation:
The printed content is based on the current view, including its columns, filters, grouping, and timescale.
Incorrect! Try again.
30A schedule preview is readable at normal scaling but becomes difficult to read after being forced onto one page. What is the best response?
Using Print Preview
Medium
A.Remove all task names from the schedule
B.Convert every summary task to a milestone
C.Allow multiple pages and use suitable scaling
D.Reduce all durations to whole days
Correct Answer: Allow multiple pages and use suitable scaling
Explanation:
Excessive scaling can make text unreadable. Printing across multiple pages preserves useful detail while maintaining legibility.
Incorrect! Try again.
31A sponsor needs a concise overview of project dates, total duration, work, cost, and progress. Which report should be selected?
Using The Project Summary Report
Medium
A.Resource Usage report
B.Task Assignment report
C.Project Summary report
D.Calendar Working Days report
Correct Answer: Project Summary report
Explanation:
The Project Summary report consolidates high-level schedule, work, cost, and progress information for the entire project.
Incorrect! Try again.
32The Project Summary report shows an unexpected project finish date. Which schedule element should be investigated first?
Using The Project Summary Report
Medium
A.The footer font and page margins
B.The report title and print orientation
C.The resource names and initials
D.The critical path and task dependencies
Correct Answer: The critical path and task dependencies
Explanation:
The project finish date is driven primarily by scheduled tasks, dependencies, constraints, and the critical path.
Incorrect! Try again.
33The Project Summary report shows costs but provides insufficient detail to identify which resource caused an overrun. What should the manager do next?
Using The Project Summary Report
Medium
A.Add a page number to the footer
B.Change the report to landscape orientation
C.Reduce the displayed project duration
D.Open a detailed resource cost report
Correct Answer: Open a detailed resource cost report
Explanation:
The Project Summary report presents aggregated values. A detailed resource cost report is needed to investigate individual cost contributions.
Incorrect! Try again.
34A Project Summary report indicates that actual cost is high while percent complete is low. What is the most appropriate interpretation?
Using The Project Summary Report
Medium
A.All remaining tasks have zero cost
B.Cost performance may require investigation
C.The project is necessarily ahead of schedule
D.The baseline has automatically been deleted
Correct Answer: Cost performance may require investigation
Explanation:
High actual cost combined with low completion can indicate poor cost performance, although detailed reports are needed to confirm the cause.
Incorrect! Try again.
35Before generating a Project Summary report for a weekly review, which action most improves the accuracy of its progress information?
Using The Project Summary Report
Medium
A.Rename all project resources
B.Update actual work and task completion
C.Increase the printed page margins
D.Change the report color theme
Correct Answer: Update actual work and task completion
Explanation:
The report summarizes current project data, so actual work and completion values should be updated before it is generated.
Incorrect! Try again.
36Two versions of a Project Summary report show different total costs even though task durations are unchanged. Which change could reasonably explain the difference?
Using The Project Summary Report
Medium
A.The task table font was reduced
B.Resource rates or fixed costs were updated
C.The page orientation was changed
D.The report header text was modified
Correct Answer: Resource rates or fixed costs were updated
Explanation:
Total project cost depends on resource rates, work, fixed costs, and other cost data, not only on task duration.
Incorrect! Try again.
37A manager wants to compare current project performance with the approved plan. What must exist for meaningful baseline comparisons in summary reporting?
Using The Project Summary Report
Medium
A.A landscape print layout
B.A saved project baseline
C.A hidden resource sheet
D.A customized page footer
Correct Answer: A saved project baseline
Explanation:
A baseline stores the approved schedule, work, and cost values needed to compare planned results with current performance.
Incorrect! Try again.
38The Project Summary report shows zero actual work even though team members have started several tasks. What is the most likely reason?
Using The Project Summary Report
Medium
A.Progress data has not been entered
B.The project title is not displayed
C.The print margins are too narrow
D.The report is using portrait orientation
Correct Answer: Progress data has not been entered
Explanation:
The report can summarize only recorded project data. Work performed by the team must be entered as actual work or progress.
Incorrect! Try again.
39A stakeholder asks for the names and daily assignments of every team member. Why is the Project Summary report insufficient?
Using The Project Summary Report
Medium
A.It presents aggregated project-level information
B.It is restricted to projects without resources
C.It excludes all schedule and cost information
D.It can display only completed milestones
Correct Answer: It presents aggregated project-level information
Explanation:
The Project Summary report provides a high-level overview rather than detailed, time-phased assignments for individual resources.
Incorrect! Try again.
40A project manager notices that the summary report's total duration is not equal to the sum of all task durations. What best explains this result?
Using The Project Summary Report
Medium
A.The report is printed in landscape format
B.All task costs are entered as fixed costs
C.Some tasks are scheduled to overlap
D.Resource names use different abbreviations
Correct Answer: Some tasks are scheduled to overlap
Explanation:
Project duration is based on the elapsed schedule from project start to finish. Overlapping tasks prevent individual durations from being simply added together.
Incorrect! Try again.
41A project prints on three pages when Printer X is selected, but the same unchanged project prints on four pages when Printer Y is selected. What is the most likely explanation?
Using Print Preview
Hard
A.Print Preview recalculates task durations according to the selected printer speed
B.The project file stores a separate schedule for every configured printer
C.Each printer driver exposes a different printable area and pagination boundary
D.Changing the printer automatically modifies the project timescale and task dates
Correct Answer: Each printer driver exposes a different printable area and pagination boundary
Explanation:
Pagination depends on the selected printer driver, paper size, resolution, and nonprintable margins. The underlying project schedule is not changed.
Incorrect! Try again.
42A Gantt view contains many columns, and Print Preview shows that fitting the output to one page wide makes all text unreadable. Which action best preserves both readability and useful content?
Using Print Preview
Hard
A.Change the paper source while keeping the same orientation and scaling
B.Remove nonessential columns, adjust widths, and then apply moderate scaling
C.Reduce the font to the minimum size and force one-page-wide output
D.Increase the timescale detail while retaining every displayed project column
Correct Answer: Remove nonessential columns, adjust widths, and then apply moderate scaling
Explanation:
Content reduction should precede aggressive scaling. Removing unnecessary columns and resizing the remaining ones usually produces a readable report with fewer pages.
Incorrect! Try again.
43Print Preview shows dozens of mostly empty horizontal pages because the displayed timescale extends far beyond the period management wants to review. What is the most targeted correction?
Using Print Preview
Hard
A.Apply resource leveling before opening Print Preview again
B.Change all task constraints to occur within the reporting period
C.Specify the required print date range and choose a compatible timescale
D.Delete tasks scheduled outside the management reporting period
Correct Answer: Specify the required print date range and choose a compatible timescale
Explanation:
The print date range and timescale control the horizontal time window. They can limit printed output without changing valid schedule data.
Incorrect! Try again.
44The final page in Print Preview contains only a legend, and the distribution requirement explicitly excludes legends. Which change directly eliminates that page without modifying the schedule?
Using Print Preview
Hard
A.Move the project finish date to the previous page
B.Hide all milestone tasks from the active schedule
C.Reduce every task bar to a single printed character
D.Set the print layout so that no legend is printed
Correct Answer: Set the print layout so that no legend is printed
Explanation:
A legend can be configured to print on each page, on a separate page, or not at all. Disabling it removes the legend-only page.
Incorrect! Try again.
45Management needs a readable printout of only the next 12 weeks, while the active project spans four years. Which configuration is most appropriate?
Using Print Preview
Hard
A.Save a baseline at week 12 and print only baseline task information
B.Temporarily shorten all tasks that finish beyond the 12-week boundary
C.Use a 12-week print range and select a timescale suitable for that interval
D.Fit the entire four-year schedule onto one landscape-oriented sheet
Correct Answer: Use a 12-week print range and select a timescale suitable for that interval
Explanation:
A bounded print range focuses the output, while a suitable timescale keeps the selected interval legible. No schedule dates need to be altered.
Incorrect! Try again.
46A confidential custom field appears in Print Preview because it is displayed as a column in the active view. What is the safest preparation for printing while retaining the field's stored values?
Using Print Preview
Hard
A.Replace every confidential value with a temporary blank value
B.Delete the custom field and restore it after printing the report
C.Create a print-specific view that omits the confidential column
D.Restrict the print range to dates containing no confidential values
Correct Answer: Create a print-specific view that omits the confidential column
Explanation:
A dedicated print view controls displayed columns without deleting or overwriting the underlying field data.
Incorrect! Try again.
47A detailed Gantt printout is required, but Print Preview displays only summary tasks because the outline is collapsed. What should be done before printing?
Using Print Preview
Hard
A.Expand the required outline levels and verify the resulting preview
B.Save a new baseline so collapsed subtasks are restored automatically
C.Increase the print resolution until hidden subtasks become visible
D.Change the report date range to include all summary task dates
Correct Answer: Expand the required outline levels and verify the resulting preview
Explanation:
Printing a view generally reflects its current outline state. Required subtasks must be expanded before the output is previewed and printed.
Incorrect! Try again.
48After a footer containing an approval block is added, Print Preview moves several task rows onto an additional page. Why can this occur even though no project data changed?
Using Print Preview
Hard
A.The project calendar reserves working time for the approval information
B.The footer consumes printable page height and changes vertical pagination
C.The approval text becomes an additional task in the active project view
D.The footer increases each task's duration by the height of one printed row
Correct Answer: The footer consumes printable page height and changes vertical pagination
Explanation:
Headers and footers reduce the area available for task rows. A smaller printable body can therefore increase the number of pages.
Incorrect! Try again.
49A project view has an active filter that excludes completed tasks. Print Preview also excludes them, but the auditor requires all tasks. Which action is most appropriate?
Using Print Preview
Hard
A.Recalculate resource costs so the filter no longer affects the output
B.Clear or replace the filter in the print view, then inspect the preview again
C.Change completed tasks back to zero percent complete before printing
D.Increase the page count manually so completed tasks receive reserved pages
Correct Answer: Clear or replace the filter in the print view, then inspect the preview again
Explanation:
Print Preview reflects the active view's filtering. The filter should be removed or replaced rather than corrupting completion data.
Incorrect! Try again.
50A PDF export and a physical printout paginate differently even though both originate from the same previewed view. What should be standardized first to obtain consistent pagination?
Using Print Preview
Hard
A.Baseline dates, status dates, earned value methods, and accrual rules
B.Task priorities, resource rates, calendars, and leveling parameters
C.Printer or PDF driver, paper size, orientation, margins, and scaling
D.Constraint types, deadline fields, task modes, and dependency lags
Correct Answer: Printer or PDF driver, paper size, orientation, margins, and scaling
Explanation:
Pagination is controlled primarily by output-device and page-layout settings. Schedule calculation settings do not normally determine physical page boundaries.
Incorrect! Try again.
51Three sequential-looking tasks have durations of 5, 8, and 7 days, but the Project Summary Report shows a project duration of 15 days rather than 20 days. Which explanation is most plausible?
Using The Project Summary Report
Hard
A.Project duration excludes every task that has assigned resources
B.The report converts task duration into elapsed weeks before summing
C.Some tasks overlap, so project duration is based on the schedule span
D.Summary reports always subtract the shortest task from total duration
Correct Answer: Some tasks overlap, so project duration is based on the schedule span
Explanation:
Project duration is governed by the scheduled start-to-finish span and working calendars, not by simply adding all task durations. Overlap can reduce the total span.
Incorrect! Try again.
52The Project Summary Report shows a baseline cost of $100,000 and a current total cost of $118,000. Using the application's cost-variance convention , what should the report indicate?
Using The Project Summary Report
Hard
A.A zero variance because actual cost has not been separately provided
B.A positive variance representing an unfavorable overrun
C.A positive variance representing total committed funding
D.A negative variance representing an unfavorable overrun
Correct Answer: A positive variance representing an unfavorable overrun
Explanation:
The calculation is . Under this field convention, a positive cost variance means the current cost exceeds the baseline.
Incorrect! Try again.
53A Project Summary Report lists 480 hours of actual work and 320 hours of remaining work. Assuming the standard work relationship, what total work should be reported?
Using The Project Summary Report
Hard
A. hours
B. hours
C. hours
D. hours
Correct Answer: hours
Explanation:
Total work is calculated as hours.
Incorrect! Try again.
54A delayed project shows almost no finish variance in the Project Summary Report. Investigation reveals that the baseline was saved only after the delay had already been incorporated. What is the best diagnosis?
Using The Project Summary Report
Hard
A.The report automatically removes all variance from projects with a baseline
B.The late baseline captured the delayed schedule, masking the earlier slippage
C.The delayed tasks were excluded because summary reports ignore critical tasks
D.Finish variance is calculated only for tasks with material resources assigned
Correct Answer: The late baseline captured the delayed schedule, masking the earlier slippage
Explanation:
Variance compares the current schedule with the saved baseline. If the baseline already contains the delay, little or no variance will appear.
Incorrect! Try again.
55Two tasks are reported as 90% and 10% complete, yet the project summary is not 50% complete. Which principle best explains the difference?
Using The Project Summary Report
Hard
A.The report averages percentages only after converting them into calendar dates
B.Summary completion is a weighted rollup rather than a simple percentage average
C.Project completion is fixed at zero until every task has started
D.The report always uses the smaller task percentage as the project percentage
Correct Answer: Summary completion is a weighted rollup rather than a simple percentage average
Explanation:
Tasks can contribute differently because of their durations, work, and scheduling structure. Their percentages should not be expected to form an unweighted arithmetic mean.
Incorrect! Try again.
56Several task estimates were edited, but the Project Summary Report continues to display the old totals while the file is operating in manual calculation mode. What should be done first?
Using The Project Summary Report
Hard
A.Increase print scaling so the revised totals fit into the report
B.Remove task dependencies and reopen the existing printed report
C.Save another baseline and replace the current project status date
D.Recalculate the project and regenerate or refresh the summary report
Correct Answer: Recalculate the project and regenerate or refresh the summary report
Explanation:
In manual calculation mode, dependent totals can remain stale until recalculation occurs. The report should then be refreshed from the recalculated project.
Incorrect! Try again.
57An auditor needs an immutable record of the Project Summary Report exactly as it appeared at month-end. Which approach best satisfies the requirement?
Using The Project Summary Report
Hard
A.Delete post-month-end actuals before opening the summary report again
B.Recalculate at month-end and archive a dated PDF or controlled print copy
C.Rely on reopening the live report because it permanently stores old values
D.Change the current date whenever the historical report must be reproduced
Correct Answer: Recalculate at month-end and archive a dated PDF or controlled print copy
Explanation:
A live summary report reflects current project data and may change later. A dated, controlled PDF or print copy preserves the month-end state.
Incorrect! Try again.
58A project contains one summary task showing 120 hours and three subtasks totaling the same 120 hours. A spreadsheet export that sums every row reports 240 hours, while the Project Summary Report reports 120 hours. Why?
Using The Project Summary Report
Hard
A.The spreadsheet converted each subtask hour into two project-calendar hours
B.The Project Summary Report excludes all work assigned beneath summary tasks
C.The Project Summary Report discarded half the work because it exceeded one level
D.The spreadsheet double-counted rolled-up summary work and underlying subtask work
Correct Answer: The spreadsheet double-counted rolled-up summary work and underlying subtask work
Explanation:
Summary-task values already roll up their subtasks. Adding both the parent value and the child values counts the same work twice.
Incorrect! Try again.
59A deadline is added to a major task, but the Project Summary Report's scheduled finish remains unchanged. Which interpretation is correct?
Using The Project Summary Report
Hard
A.A deadline changes only project cost and therefore cannot affect reporting
B.The scheduled finish changes only when the deadline is assigned to a resource
C.The summary report ignores deadlines until the project baseline is deleted
D.A deadline warns about lateness but does not itself constrain scheduled dates
Correct Answer: A deadline warns about lateness but does not itself constrain scheduled dates
Explanation:
A deadline provides an indicator when a task finishes late, but it does not normally force the task or project finish to move.
Incorrect! Try again.
60Two managers submit Project Summary Reports for comparison, but they used different baselines, status dates, and calculation states. What should occur before drawing performance conclusions?
Using The Project Summary Report
Hard
A.Remove all baseline fields and compare current costs without recalculation
B.Compare only page counts because schedule fields are not directly comparable
C.Average the two reports so differences in configuration cancel each other
D.Standardize the baseline, status date, calculation state, and reporting conventions
Correct Answer: Standardize the baseline, status date, calculation state, and reporting conventions
Explanation:
Reports are comparable only when their reference baseline, reporting cutoff, calculation state, and field conventions are aligned.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →