1What is the main purpose of delaying a task manually in a project schedule?
Delaying Tasks Manually
Easy
A.To resolve a resource conflict
B.To remove the task permanently
C.To increase the task cost
D.To change the task name
Correct Answer: To resolve a resource conflict
Explanation:
Delaying a task manually can move its work to a later time and help resolve a resource conflict.
Incorrect! Try again.
2Which schedule element is changed when a task is delayed manually?
Delaying Tasks Manually
Easy
A.Project title
B.Resource skill level
C.Task start or finish date
D.Calendar color
Correct Answer: Task start or finish date
Explanation:
Manual delay changes when the task starts or finishes in the schedule.
Incorrect! Try again.
3What is the main goal of resource leveling?
Leveling Resources
Easy
A.Change all task names
B.Increase every task duration
C.Balance resource assignments
D.Remove all project resources
Correct Answer: Balance resource assignments
Explanation:
Resource leveling adjusts the schedule or assignments to reduce resource overallocations.
Incorrect! Try again.
4A resource is overallocated when the resource is assigned:
Leveling Resources
Easy
A.More work than available
B.No work during the project
C.Only to completed tasks
D.Less work than available
Correct Answer: More work than available
Explanation:
A resource is overallocated when assigned work exceeds the resource's available capacity.
Incorrect! Try again.
5What may resource leveling do to a task in order to remove an overallocation?
Leveling Resources Continued
Easy
A.Delete the project calendar
B.Hide the task from reports
C.Rename the assigned resource
D.Move the task to another time
Correct Answer: Move the task to another time
Explanation:
Leveling may delay or reschedule tasks so that the resource is not required for conflicting work.
Incorrect! Try again.
6Which information is useful before leveling resources?
Leveling Resources Continued
Easy
A.The document page color
B.The printer model
C.The resource assignments
D.The user's login name
Correct Answer: The resource assignments
Explanation:
Resource assignments show which resources are scheduled to perform each task.
Incorrect! Try again.
7What does the Leveling Gantt view help a project manager examine?
Using The Leveling Gantt View
Easy
A.Computer hardware settings
B.Employee vacation requests only
C.Email message contents
D.Resource conflicts and delays
Correct Answer: Resource conflicts and delays
Explanation:
The Leveling Gantt view displays scheduling information related to leveling, including delays and conflicts.
Incorrect! Try again.
8In a Leveling Gantt view, a leveling delay usually shows that a task was:
Using The Leveling Gantt View
Easy
A.Moved because of leveling
B.Marked as a milestone
C.Converted into a resource
D.Deleted by the system
Correct Answer: Moved because of leveling
Explanation:
A leveling delay indicates that the task was shifted to help resolve a resource overallocation.
Incorrect! Try again.
9What is one direct result of decreasing the work assigned to a task?
Decreasing Work Time
Easy
A.The resource becomes unavailable
B.The task loses its predecessor
C.The resource performs fewer hours
D.The project gains a new phase
Correct Answer: The resource performs fewer hours
Explanation:
Decreasing task work reduces the number of hours assigned to the resource for that task.
Incorrect! Try again.
10Which action can help reduce a resource overallocation?
Decreasing Work Time
Easy
A.Reduce the task work
B.Add unrelated resources
C.Increase the task work
D.Remove the project start date
Correct Answer: Reduce the task work
Explanation:
Reducing task work can lower the resource's total assigned hours and help resolve an overallocation.
Incorrect! Try again.
11What does splitting a task do?
Splitting Tasks
Easy
A.Removes all task constraints
B.Divides its work into separate periods
C.Changes it into a summary task
D.Doubles its assigned resources
Correct Answer: Divides its work into separate periods
Explanation:
Splitting allows task work to stop and resume later, creating separate work periods.
Incorrect! Try again.
12Why might a task be split during resource management?
Splitting Tasks
Easy
A.To pause work during a conflict
B.To eliminate the task duration
C.To hide the task from the schedule
D.To change the project currency
Correct Answer: To pause work during a conflict
Explanation:
A task can be split so work pauses while a resource handles another task.
Incorrect! Try again.
13What does slack indicate in a project schedule?
Viewing Slack In A Table View
Easy
A.The number of project phases
B.Available scheduling flexibility
C.The resource hourly rate
D.The task description length
Correct Answer: Available scheduling flexibility
Explanation:
Slack is the amount of time a task can be delayed without delaying a related project milestone or finish date.
Incorrect! Try again.
14Which table field is commonly used to display a task's scheduling flexibility?
Viewing Slack In A Table View
Easy
A.Resource Initials
B.Fixed Cost
C.Total Slack
D.Task Mode
Correct Answer: Total Slack
Explanation:
The Total Slack field shows how much a task can be delayed without delaying the project finish.
Incorrect! Try again.
15How is slack commonly shown in a Gantt view?
Viewing Slack In A Gantt View
Easy
A.As a bar beside the task bar
B.As a project password
C.As a hidden task name
D.As a resource pay rate
Correct Answer: As a bar beside the task bar
Explanation:
Gantt views can display slack visually as an additional bar extending from the task bar.
Incorrect! Try again.
16What does reassigning a resource mean?
Reassigning Resources
Easy
A.Changing the project finish date
B.Assigning the task to another resource
C.Deleting the task from the schedule
D.Removing the task description
Correct Answer: Assigning the task to another resource
Explanation:
Reassigning transfers task responsibility from one resource to another.
Incorrect! Try again.
17Why might a project manager reassign a task to another resource?
Reassigning Resources
Easy
A.To change the file format
B.To reduce an overallocation
C.To increase the number of calendars
D.To remove all task dependencies
Correct Answer: To reduce an overallocation
Explanation:
A task can be reassigned to a resource with available capacity, reducing the original resource's workload.
Incorrect! Try again.
18What is the effect of increasing a resource's working hours?
Increasing Working Hours
Easy
A.The task becomes a milestone
B.The resource is removed from the project
C.The project loses its calendar
D.The resource has more available capacity
Correct Answer: The resource has more available capacity
Explanation:
Increasing working hours gives the resource more scheduled time to perform assigned work.
Incorrect! Try again.
19What is overtime work?
Assigning Overtime To A Task
Easy
A.Work performed only by managers
B.Work performed beyond regular hours
C.Work removed from the schedule
D.Work assigned before project approval
Correct Answer: Work performed beyond regular hours
Explanation:
Overtime is work scheduled outside a resource's regular working time.
Incorrect! Try again.
20What does resource contouring control?
Contouring Resources
Easy
A.The spelling of resource names
B.The distribution of work over time
C.The color of task labels
D.The number of project files
Correct Answer: The distribution of work over time
Explanation:
Resource contouring changes how assigned work is spread across the duration of a task.
Incorrect! Try again.
21A noncritical task conflicts with another task assigned to the same resource. The task has 4 days of total slack. Which manual action is most appropriate if the conflict lasts 2 days?
Delaying Tasks Manually
Medium
A.Change the task's priority to 1000
B.Increase the task's duration by 2 days
C.Move the task's start date 2 days later
D.Reduce the resource's assignment units by half
Correct Answer: Move the task's start date 2 days later
Explanation:
Moving the task within its available slack resolves the conflict without delaying the project finish date.
Incorrect! Try again.
22A task has 3 days of total slack before it is manually delayed by 2 working days. Assuming no other schedule changes occur, how much total slack remains?
Delaying Tasks Manually
Medium
A.1 day
B.3 days
C.5 days
D.2 days
Correct Answer: 1 day
Explanation:
The delay consumes 2 of the 3 available slack days, leaving day.
Incorrect! Try again.
23A resource is assigned at 100% to two concurrent tasks. What does resource leveling normally do to resolve this overallocation?
Leveling Resources
Medium
A.Reduce the scope of both tasks
B.Replace the resource on both tasks
C.Increase the resource's standard rate
D.Delay or split one of the tasks
Correct Answer: Delay or split one of the tasks
Explanation:
Resource leveling resolves overallocations primarily by delaying or splitting tasks according to the leveling settings.
Incorrect! Try again.
24Task A has priority 1000, while Task B has priority 500. Both tasks require the same resource at the same time. Under priority-based leveling, what is the expected result?
Leveling Resources
Medium
A.Task A is considered for delay
B.Both tasks are always split equally
C.Both task priorities are reset
D.Task B is considered for delay
Correct Answer: Task B is considered for delay
Explanation:
A priority of 1000 means that a task should not be delayed or split by leveling, so Task B is the likely task to move.
Incorrect! Try again.
25What is the likely result of selecting the leveling option "Level only within available slack" when a resource conflict requires a 4-day delay but the affected task has only 2 days of slack?
Leveling Resources Continued
Medium
A.Some overallocation may remain unresolved
B.The project finish date moves by 4 days
C.The resource's working time increases automatically
D.The task's work decreases by 2 days
Correct Answer: Some overallocation may remain unresolved
Explanation:
Leveling is restricted to the available slack, so it cannot apply the full delay required to remove the conflict.
Incorrect! Try again.
26A project was leveled using unsuitable settings, producing several unwanted delays and splits. What should the manager do before applying revised leveling settings?
Leveling Resources Continued
Medium
A.Delete every affected assignment
B.Reset all resource calendars
C.Clear the previous leveling results
D.Convert all tasks to milestones
Correct Answer: Clear the previous leveling results
Explanation:
Clearing leveling removes delays and splits created by the previous leveling operation, allowing the schedule to be leveled again.
Incorrect! Try again.
27What is the main benefit of using the Leveling Gantt view after leveling resources?
Using The Leveling Gantt View
Medium
A.It compares preleveled and current task positions
B.It compares planned and actual resource costs
C.It replaces resources with available alternatives
D.It displays only tasks on the critical path
Correct Answer: It compares preleveled and current task positions
Explanation:
The Leveling Gantt view shows how task timing changed as a result of leveling.
Incorrect! Try again.
28In the Leveling Gantt view, a task's current bar begins 2 working days after its preleveled bar, while both bars have the same duration. What does this indicate?
Using The Leveling Gantt View
Medium
A.The task finished 2 days early
B.Leveling delayed the task by 2 days
C.The task gained 2 days of work
D.Leveling reduced the task by 2 days
Correct Answer: Leveling delayed the task by 2 days
Explanation:
The difference between the preleveled and current bar positions represents a 2-day leveling delay.
Incorrect! Try again.
29A fixed-units task has one resource assigned at 100%, a duration of 5 days, and 40 hours of work. If the work is reduced to 24 hours under an 8-hour calendar, what is the new duration?
Decreasing Work Time
Medium
A.5 days
B.3 days
C.4 days
D.8 days
Correct Answer: 3 days
Explanation:
At 100% assignment units, the duration is working days.
Incorrect! Try again.
30A specialist must pause a 6-day task after day 2 to handle an urgent assignment, then resume the original task three days later. Which scheduling technique best represents this situation?
Splitting Tasks
Medium
A.Add free slack to the task
B.Split the original task
C.Increase the task priority
D.Convert the task to a milestone
Correct Answer: Split the original task
Explanation:
Splitting creates an interruption between completed and remaining portions while retaining a single task.
Incorrect! Try again.
31A task contains 32 hours of work and is split into two segments because the assigned resource is temporarily unavailable. If no work is removed, what happens to the task's total work?
Splitting Tasks
Medium
A.It becomes 16 hours
B.It becomes equal to elapsed time
C.It increases by the gap duration
D.It remains 32 hours
Correct Answer: It remains 32 hours
Explanation:
A split changes when the work occurs, not the total amount of work assigned to the task.
Incorrect! Try again.
32A task has an early finish on day 15 and a late finish on day 18. What value should appear in its Total Slack field?
Viewing Slack In A Table View
Medium
A.18 days
B.33 days
C.3 days
D.15 days
Correct Answer: 3 days
Explanation:
Total slack can be calculated as , so days.
Incorrect! Try again.
33A schedule table shows a task with total slack of days. What does this value indicate?
Viewing Slack In A Table View
Medium
A.The task may be delayed safely by 2 days
B.The task completed 2 days under budget
C.The schedule misses a requirement by 2 days
D.The resource has 2 days of unused capacity
Correct Answer: The schedule misses a requirement by 2 days
Explanation:
Negative slack indicates that the current schedule exceeds a constraint, deadline, or required finish by the stated amount.
Incorrect! Try again.
34A manager wants to inspect task bars and graphical slack indicators together. Which view is most suitable?
Viewing Slack In A Gantt View
Medium
A.Network Diagram view
B.Detail Gantt view
C.Resource Sheet view
D.Calendar view
Correct Answer: Detail Gantt view
Explanation:
The Detail Gantt view graphically displays task timing and slack, making schedule flexibility easier to inspect.
Incorrect! Try again.
35Two simultaneous tasks overload a database administrator. Another administrator with equivalent skills and availability is unassigned. What is the most direct resolution?
Reassigning Resources
Medium
A.Delay both tasks by the same amount
B.Remove the tasks' dependencies
C.Replace the resource on one task
D.Increase both task durations
Correct Answer: Replace the resource on one task
Explanation:
Reassigning one task to a qualified and available resource removes the conflict without unnecessarily delaying the schedule.
Incorrect! Try again.
36Before replacing an overallocated resource with another resource, which factors are most important to verify?
Reassigning Resources
Medium
A.Project title, author, and file size
B.Skills, availability, and assignment cost
C.Task color, font, and row number
D.Milestone shape, zoom, and gridlines
Correct Answer: Skills, availability, and assignment cost
Explanation:
A replacement should be capable of performing the work, available during the required period, and acceptable within the project budget.
Incorrect! Try again.
37Only one resource has agreed to work 10-hour days for a particular week. How should the schedule be updated without affecting everyone else?
Increasing Working Hours
Medium
A.Increase every task's assignment units
B.Modify the project calendar for the week
C.Change the project's status date
D.Modify that resource's calendar for the week
Correct Answer: Modify that resource's calendar for the week
Explanation:
A resource calendar exception changes the working time of only that resource during the specified period.
Incorrect! Try again.
38A resource has 40 hours of total work on a task. The manager enters 8 hours in the Overtime Work field. How should those 8 hours be interpreted?
Assigning Overtime To A Task
Medium
A.They replace all 40 regular hours
B.They reduce total work to 32 hours
C.They are part of the 40 total hours
D.They are added to make 48 total hours
Correct Answer: They are part of the 40 total hours
Explanation:
Overtime work identifies the portion of total assignment work performed as overtime; it does not automatically add extra scope.
Incorrect! Try again.
39A 5-day assignment contains 40 hours of work. Which daily distribution represents a front-loaded resource contour?
Contouring Resources
Medium
A.4, 10, 12, 10, and 4 hours
B.12, 10, 8, 6, and 4 hours
C.4, 6, 8, 10, and 12 hours
D.8, 8, 8, 8, and 8 hours
Correct Answer: 12, 10, 8, 6, and 4 hours
Explanation:
A front-loaded contour assigns more work near the beginning and progressively less work later while preserving 40 total hours.
Incorrect! Try again.
40A resource is heavily loaded early in a task but has more availability near the end. Which contouring action best addresses this pattern without changing the task's total work?
Contouring Resources
Medium
A.Move all assignment work to the first period
B.Delete the assignment's remaining work
C.Add the same amount of work to every period
D.Shift more assignment work toward later periods
Correct Answer: Shift more assignment work toward later periods
Explanation:
A back-loaded or manually adjusted contour redistributes work toward later periods while retaining the required total work.
Incorrect! Try again.
41A resource is assigned full-time to Task A and Task B, both scheduled Monday through Wednesday. Task B has 2 days of total slack, while Task A is critical. Assuming no constraints prevent movement, which manual adjustment resolves the overallocation without changing the project finish date?
Delaying Tasks Manually
Hard
A.Add 2 elapsed days to Task B
B.Delay Task B by 2 working days
C.Delay Task A until Thursday
D.Reduce both assignments to 50%
Correct Answer: Delay Task B by 2 working days
Explanation:
Task B can consume its 2 days of slack without delaying the project. Delaying critical Task A would move the project finish date.
Incorrect! Try again.
42Task X has a Start No Earlier Than constraint and 3 days of free slack. You enter a 2-day leveling delay manually. Which outcome is most accurate?
Delaying Tasks Manually
Hard
A.Its duration increases by exactly 2 working days
B.Its successors move because any leveling delay consumes total slack
C.Its constraint is deleted when the leveling delay is entered
D.Its successors remain unaffected if the delay stays within free slack
Correct Answer: Its successors remain unaffected if the delay stays within free slack
Explanation:
Free slack is the time a task may slip without delaying an immediate successor. A delay within that amount changes the task's timing but not its successors.
Incorrect! Try again.
43A resource is assigned at 100% to two concurrent tasks. Both assignments are fixed-work, and automatic leveling is applied with splitting disabled. What is the leveling engine expected to change?
Leveling Resources
Hard
A.Convert one task from fixed-work to fixed-duration
B.Reduce both assignment units to 50% for the overlap
C.Increase the resource's maximum units to 200%
D.Delay one task according to leveling priorities and dependencies
Correct Answer: Delay one task according to leveling priorities and dependencies
Explanation:
Resource leveling primarily delays tasks when splitting is unavailable. It does not normally change assignment units, task types, or resource capacity.
Incorrect! Try again.
44Two tasks competing for one resource have identical dependencies and dates. Task A has priority 900 and Task B has priority 100. Under the standard Priority, Standard leveling order, which task is generally protected from delay?
Leveling Resources
Hard
A.Task B because its priority is lower
B.Task B because shorter tasks are always protected
C.Task A because its priority is higher
D.Task A because its numeric ID is irrelevant
Correct Answer: Task A because its priority is higher
Explanation:
Under Priority, Standard leveling, a higher task priority makes a task less likely to be delayed, subject to constraints and scheduling logic.
Incorrect! Try again.
45A schedule is leveled with the option to level only within available slack enabled. An overallocation remains afterward. What is the strongest interpretation?
Leveling Resources Continued
Hard
A.Resolving it would require delay beyond available slack
B.The project calendar has excess working time
C.The resource's standard rate is too low
D.The tasks contain no assignment work values
Correct Answer: Resolving it would require delay beyond available slack
Explanation:
Slack-limited leveling avoids moves that would extend the project. An overallocation can therefore remain when no feasible delay exists within available slack.
Incorrect! Try again.
46A manager clears leveling after reviewing a leveled schedule. Which changes should normally be removed by that action?
Leveling Resources Continued
Hard
A.All manually entered assignment units
B.Leveling delays and leveling-created task splits
C.All baseline dates and baseline costs
D.All task constraints and deadline dates
Correct Answer: Leveling delays and leveling-created task splits
Explanation:
Clearing leveling reverses adjustments introduced by the leveling process, such as delays and eligible splits. It does not erase ordinary schedule data or baselines.
Incorrect! Try again.
47In a Leveling Gantt view, a task's preleveling bar starts Monday, while its current scheduled bar starts Thursday. Its duration is unchanged. What does this comparison most directly reveal?
Using The Leveling Gantt View
Hard
A.The assignment units were increased
B.The task calendar was deleted
C.The task's work was reduced
D.The task was delayed by leveling
Correct Answer: The task was delayed by leveling
Explanation:
The Leveling Gantt compares preleveling and current positions. A later current bar with unchanged duration indicates that leveling shifted the task.
Incorrect! Try again.
48After leveling, a manager sees that a task moved 3 days, but only 1 day appears in the Leveling Delay field. Which explanation is most plausible?
Using The Leveling Gantt View
Hard
A.Leveling delay excludes all working days
B.The remaining movement must be overtime work
C.Part of the movement came from dependency recalculation
D.The field displays duration instead of delay
Correct Answer: Part of the movement came from dependency recalculation
Explanation:
The visible date shift can include both direct leveling delay and indirect movement caused by predecessor changes. The Leveling Delay field records only the direct leveling adjustment.
Incorrect! Try again.
49A fixed-units task has 40 hours of work assigned at 100%, giving a 5-day duration on an 8-hour calendar. Scope is reduced to 24 hours while units remain unchanged. What is the resulting duration?
Decreasing Work Time
Hard
A.4 working days
B.8 working days
C.5 working days
D.3 working days
Correct Answer: 3 working days
Explanation:
For fixed units, . Thus working days.
Incorrect! Try again.
50A task is fixed-duration with effort-driven scheduling enabled. Its duration is 4 days, and two resources each have 32 hours of work. One resource is removed. What is the expected effect on the remaining resource, assuming availability permits it?
Decreasing Work Time
Hard
A.Its assignment work remains exactly 32 hours
B.Its assignment work increases to about 64 hours
C.The task duration rises to about 8 days
D.The task duration falls to about 2 days
Correct Answer: Its assignment work increases to about 64 hours
Explanation:
On an effort-driven fixed-duration task, removing a resource redistributes the task's work while preserving duration. The remaining resource absorbs the removed assignment's work.
Incorrect! Try again.
51A 5-day task is split after 2 days of work, with the remaining 3 days resumed one week later. Which schedule quantity is directly increased by the split?
Splitting Tasks
Hard
A.The task's elapsed span
B.The task's active duration
C.The resource's maximum units
D.The task's assignment work
Correct Answer: The task's elapsed span
Explanation:
A split inserts an interruption between working segments. The task spans more calendar time, while its scheduled working duration and work need not increase.
Incorrect! Try again.
52A resource is overallocated only on Wednesday. Task B runs Monday through Friday and can be interrupted; Task A requires the resource only on Wednesday. Which adjustment best preserves Task B's work and avoids delaying its first two days?
Splitting Tasks
Hard
A.Raise the resource's units for Wednesday
B.Reduce Task B's total work by 20%
C.Delay all of Task B until Thursday
D.Split Task B around Wednesday
Correct Answer: Split Task B around Wednesday
Explanation:
Splitting Task B allows Monday and Tuesday work to remain scheduled, pauses it during the conflict, and resumes it afterward without reducing scope.
Incorrect! Try again.
53A task displays 4 days of total slack and 1 day of free slack. Which statement is correct?
Viewing Slack In A Table View
Hard
A.It may slip 1 day without delaying its immediate successor
B.It may slip 1 day before delaying the project finish
C.It is critical because free slack is less than total slack
D.It may slip 4 days without delaying its immediate successor
Correct Answer: It may slip 1 day without delaying its immediate successor
Explanation:
Free slack protects the immediate successor, whereas total slack measures movement allowed before the project finish or a constrained milestone is delayed.
Incorrect! Try again.
54A task shows days of total slack in a schedule table. What does this usually indicate?
Viewing Slack In A Table View
Hard
A.The task finishes 3 days before its deadline
B.The task can be delayed freely for 3 days
C.The schedule misses a required date by about 3 days
D.The task has 3 days of unused resource capacity
Correct Answer: The schedule misses a required date by about 3 days
Explanation:
Negative total slack signals that the current schedule cannot satisfy a constraint, deadline, or required project finish without recovering approximately that amount of time.
Incorrect! Try again.
55A Gantt view shows a slack bar extending 2 days beyond a task's finish, but the task's successor is scheduled only 1 day later. Why can the displayed slack exceed the visible gap to that successor?
Viewing Slack In A Gantt View
Hard
A.The successor link is ignored in every Gantt view
B.The bar measures resource units rather than time
C.The bar may represent total slack rather than free slack
D.The bar includes the task's completed work
Correct Answer: The bar may represent total slack rather than free slack
Explanation:
Total slack is measured against the controlling project or constraint date, so it can exceed the gap before an immediate successor. That smaller gap is related to free slack.
Incorrect! Try again.
56An 80-hour fixed-work task is assigned to Resource A at 100%. Resource A is replaced by Resource B, who is available at only 50%. Assuming no other assignments and unchanged work, what duration should be expected on an 8-hour-per-day calendar?
Reassigning Resources
Hard
A.20 working days
B.5 working days
C.8 working days
D.10 working days
Correct Answer: 20 working days
Explanation:
At 50%, Resource B supplies 4 hours per working day. The duration is therefore working days.
Incorrect! Try again.
57A replacement resource has the same availability as the original resource but a different working calendar with Friday marked nonworking. Which schedule effect must be evaluated even when assignment units are unchanged?
Reassigning Resources
Hard
A.The task may finish later because working times intersect differently
B.The task automatically becomes fixed-duration
C.The original resource's calendar replaces the new calendar
D.The task must retain identical start and finish dates
Correct Answer: The task may finish later because working times intersect differently
Explanation:
Assignment scheduling uses the applicable project, task, and resource calendars. Reassignment can change valid working periods even when units and work are identical.
Incorrect! Try again.
58A resource calendar is changed from 8 to 10 working hours per day for one week. A fixed-work task has 40 hours remaining and is assigned at 100% during that week. Ignoring other constraints, what happens?
Increasing Working Hours
Hard
A.Its remaining duration can fall from 5 days to 4 days
B.Its remaining cost always decreases by exactly 20%
C.Its assignment units automatically fall from 100% to 80%
D.Its remaining work automatically rises from 40 to 50 hours
Correct Answer: Its remaining duration can fall from 5 days to 4 days
Explanation:
Increasing available working time provides 10 hours per day at 100%. Completing 40 remaining hours then requires working days.
Incorrect! Try again.
59A resource has 40 hours of work on a fixed-work task. Of this amount, 8 hours is designated as overtime work. The resource performs 8 regular hours plus 2 overtime hours per day. Approximately how long will the assignment take?
Assigning Overtime To A Task
Hard
A.4 working days
B.5 working days
C.6 working days
D.3 working days
Correct Answer: 4 working days
Explanation:
The assignment contains 32 regular hours and 8 overtime hours. At 8 regular plus 2 overtime hours daily, both portions complete in 4 working days.
Incorrect! Try again.
60A task assignment has 80 hours of work over 10 days. The manager wants low effort at the beginning, peak effort near the middle, and low effort again at the end without changing total work. Which contour best matches this requirement?
Contouring Resources
Hard
A.Front Loaded
B.Bell
C.Back Loaded
D.Early Peak
Correct Answer: Bell
Explanation:
A Bell contour increases assignment work toward the middle and then decreases it. The contour redistributes timephased work without inherently changing total work.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →