Correct Answer: A temporary effort with a specific goal
Explanation:
A project is a temporary effort undertaken to achieve a specific objective or deliverable.
Incorrect! Try again.
2Which characteristic is normally associated with a project?
Meaning of project
Easy
A.It continues without any target
B.It has a definite beginning and end
C.It repeats exactly every day
D.It has no assigned resources
Correct Answer: It has a definite beginning and end
Explanation:
Projects are temporary and therefore have a defined start and finish.
Incorrect! Try again.
3Why are software projects often different from construction projects?
Software project versus other types
Easy
A.Software products cannot be changed
B.Software projects never need planning
C.Software always requires physical materials
D.Software is created mainly through intellectual work
Correct Answer: Software is created mainly through intellectual work
Explanation:
Software production depends largely on analysis, design, coding, and other intellectual activities.
Incorrect! Try again.
4Which feature makes software projects difficult to visualize?
Software Project Versus Other Types
Easy
A.Software is mostly intangible
B.Software uses construction machines
C.Software has a physical weight
D.Software requires factory storage
Correct Answer: Software is mostly intangible
Explanation:
Unlike many physical products, software cannot usually be seen or measured directly in physical form.
Incorrect! Try again.
5What is a major activity in software production?
Nature of software production
Easy
A.Packaging physical furniture
B.Mining raw construction materials
C.Manufacturing mechanical engines
D.Writing and testing program code
Correct Answer: Writing and testing program code
Explanation:
Software production includes activities such as coding, testing, debugging, and maintenance.
Incorrect! Try again.
6Software development is generally considered a form of:
Nature of software production
Easy
A.Repetitive physical assembly
B.Creative and intellectual work
C.Material extraction
D.Agricultural production
Correct Answer: Creative and intellectual work
Explanation:
Developing software requires problem-solving, design, creativity, and technical knowledge.
Incorrect! Try again.
7Which activity is normally performed by software project management?
Activities by Software Project Management
Easy
A.Planning project tasks and resources
B.Manufacturing computer hardware
C.Operating a public transport system
D.Designing office furniture
Correct Answer: Planning project tasks and resources
Explanation:
Software project management includes planning tasks, allocating resources, scheduling work, and monitoring progress.
Incorrect! Try again.
8Which activity helps a project manager track project progress?
Activities by Software Project Management
Easy
A.Raw material extraction
B.Building maintenance
C.Product advertising
D.Project monitoring
Correct Answer: Project monitoring
Explanation:
Monitoring compares actual progress with the project plan and identifies deviations.
Incorrect! Try again.
9What is a key objective of effective software project management?
Key objectives of effective management
Easy
A.Avoiding all communication
B.Delivering the project within agreed constraints
C.Removing the project schedule
D.Increasing requirements without approval
Correct Answer: Delivering the project within agreed constraints
Explanation:
Effective management aims to meet scope, time, cost, and quality expectations.
Incorrect! Try again.
10Which constraint is commonly managed in a software project?
Key objectives of effective management
Easy
A.Road traffic only
B.Time
C.Building height only
D.Weather only
Correct Answer: Time
Explanation:
Time is a common project constraint, along with cost, scope, quality, and resources.
Incorrect! Try again.
11Which problem commonly affects software projects?
Problems with software projects
Easy
A.Guaranteed customer agreement
B.Fixed technology for every project
C.Unlimited development time
D.Unclear requirements
Correct Answer: Unclear requirements
Explanation:
Unclear or changing requirements can cause rework, delays, and increased costs.
Incorrect! Try again.
12What can happen when a software project is poorly planned?
Problems with software projects
Easy
A.Permanent removal of risks
B.Fewer project activities
C.Delays and cost overruns
D.Automatic quality improvement
Correct Answer: Delays and cost overruns
Explanation:
Poor planning can lead to missed deadlines, increased expenses, and difficulty controlling the project.
Incorrect! Try again.
13What is the main purpose of risk reduction?
Risk reduction
Easy
A.To increase uncertainty
B.To lower the chance or impact of problems
C.To avoid documenting decisions
D.To remove all project objectives
Correct Answer: To lower the chance or impact of problems
Explanation:
Risk reduction uses suitable actions to decrease the likelihood or effect of possible problems.
Incorrect! Try again.
14What is risk identification?
Risk identification
Easy
A.Assigning office seating arrangements
B.Writing the final user manual
C.Closing the project account
D.Finding possible events that may harm the project
Correct Answer: Finding possible events that may harm the project
Explanation:
Risk identification involves recognizing and documenting uncertainties that could affect project success.
Incorrect! Try again.
15What does project scope describe?
Project scope
Easy
A.The work and deliverables included in a project
B.The office location of the development team
C.The personal interests of the project manager
D.The annual income of every employee
Correct Answer: The work and deliverables included in a project
Explanation:
Project scope defines what the project will and will not deliver.
Incorrect! Try again.
16What is a project objective?
Objectives
Easy
A.A list of unrelated personal activities
B.A record of past employee holidays
C.A desired result the project aims to achieve
D.A replacement for project requirements
Correct Answer: A desired result the project aims to achieve
Explanation:
An objective states the result or outcome that the project is intended to accomplish.
Incorrect! Try again.
17Why are business objectives determined before starting development?
Business Planning: determining objectives
Easy
A.To clarify the purpose and expected benefits
B.To eliminate the need for users
C.To guarantee unlimited funding
D.To prevent project evaluation
Correct Answer: To clarify the purpose and expected benefits
Explanation:
Business objectives explain why the project is needed and what benefits it should provide.
Incorrect! Try again.
18In software project planning, infrastructure may include:
Infrastructure
Easy
A.Hardware, networks, and development tools
B.Only customer opinions
C.Only legal contracts
D.Only project advertisements
Correct Answer: Hardware, networks, and development tools
Explanation:
Infrastructure provides the technical environment and facilities needed to develop and operate software.
Incorrect! Try again.
19What is the purpose of forecasting demand for a software product?
Forecasting demand for product
Easy
A.To estimate how many users may want it
B.To remove all product features
C.To avoid studying the market
D.To select the programming language automatically
Correct Answer: To estimate how many users may want it
Explanation:
Demand forecasting helps an organization estimate likely customer interest and market needs.
Incorrect! Try again.
20What is the main purpose of a software project proposal?
Proposal writing
Easy
A.To replace all project testing
B.To present the planned solution and its benefits
C.To hide the estimated project cost
D.To record unrelated personal information
Correct Answer: To present the planned solution and its benefits
Explanation:
A proposal communicates the project idea, objectives, approach, costs, schedule, and expected benefits.
Incorrect! Try again.
21A company is developing a mobile banking application with a defined budget, a planned completion date, and specific deliverables. Why is this work considered a project?
What is project?
Medium
A.It involves routine daily operations
B.It continues indefinitely without milestones
C.It has a temporary goal and defined constraints
D.It uses only technical employees
Correct Answer: It has a temporary goal and defined constraints
Explanation:
A project is a temporary effort undertaken to create a specific product, service, or result within constraints such as time, cost, and scope.
Incorrect! Try again.
22Which characteristic most clearly distinguishes a software project from a construction project?
Software project versus other types
Medium
A.Software projects require customer involvement
B.Software requires project planning
C.Software progress is difficult to measure physically
D.Construction projects have defined budgets
Correct Answer: Software progress is difficult to measure physically
Explanation:
Software has no physical form, so progress cannot be assessed by observing completed physical structures. It must be evaluated through artifacts, functionality, and quality measures.
Incorrect! Try again.
23A development team spends most of its effort creating a new algorithm, but the algorithm can be copied repeatedly at almost no additional production cost. Which nature of software production does this illustrate?
Nature of software production
Medium
A.Software is mainly manufactured in factories
B.Software requires identical physical components
C.Software production is primarily intellectual
D.Software production depends mainly on raw materials
Correct Answer: Software production is primarily intellectual
Explanation:
Software is created mainly through analysis, design, programming, and testing. Its major cost is intellectual effort rather than physical manufacturing.
Incorrect! Try again.
24A project manager creates a schedule, assigns developers to tasks, tracks progress, and updates stakeholders. Which management activity is being demonstrated most directly?
Activities by Software Project Management
Medium
A.User-interface prototyping
B.Source-code compilation
C.Project coordination and control
D.Database normalization
Correct Answer: Project coordination and control
Explanation:
Scheduling, resource assignment, progress tracking, and stakeholder communication are core activities of coordinating and controlling a software project.
Incorrect! Try again.
25A project is delivered on time but fails to meet essential user requirements. Which management objective was most clearly neglected?
Key objectives of effective management
Medium
A.Maximizing documentation volume
B.Meeting agreed product quality and scope
C.Using the newest programming language
D.Increasing the number of project meetings
Correct Answer: Meeting agreed product quality and scope
Explanation:
Effective management balances time, cost, scope, and quality. Delivering on schedule alone does not indicate success if important requirements are unmet.
Incorrect! Try again.
26During development, stakeholders frequently request new features, causing repeated schedule delays. What problem is primarily affecting this project?
Problems with software projects
Medium
A.Insufficient hardware capacity
B.Excessive code reuse
C.Uncontrolled scope growth
D.Overly stable requirements
Correct Answer: Uncontrolled scope growth
Explanation:
Frequent additions or changes to agreed requirements can cause scope creep, which often increases effort, cost, and schedule duration.
Incorrect! Try again.
27A team is uncertain whether a proposed technology can support the expected transaction volume. Which action would reduce this risk most effectively?
Risk reduction
Medium
A.Increase the number of status meetings
B.Remove performance requirements
C.Build an early technical prototype
D.Postpone testing until final delivery
Correct Answer: Build an early technical prototype
Explanation:
An early prototype or proof of concept tests technical feasibility before major resources are committed, reducing uncertainty and potential rework.
Incorrect! Try again.
28Two projects use similar technologies, but one has clear responsibilities, realistic estimates, and regular risk reviews. Why is this project more likely to succeed?
Importance of software project management
Medium
A.Management eliminates the need for skilled developers
B.Management reduces the need for software testing
C.Management provides structure for controlling uncertainty
D.Management guarantees that requirements never change
Correct Answer: Management provides structure for controlling uncertainty
Explanation:
Software projects involve uncertainty in requirements, technology, effort, and resources. Effective management provides planning, monitoring, and corrective actions.
Incorrect! Try again.
29A customer asks a team to add multilingual support to a system, although the approved project statement includes only English support. What should the project manager do first?
Project scope
Medium
A.Assess the change against the agreed scope
B.Add the feature immediately
C.Remove another feature without approval
D.Reject the customer without analysis
Correct Answer: Assess the change against the agreed scope
Explanation:
The request should be evaluated through scope and change-control procedures to determine its effect on cost, schedule, resources, and objectives.
Incorrect! Try again.
30Which project objective is most suitable because it is measurable and time-bound?
Objectives
Medium
A.Develop the best system available
B.Reduce average response time to seconds by release
C.Make users happier eventually
D.Improve the application substantially
Correct Answer: Reduce average response time to seconds by release
Explanation:
A strong objective specifies a measurable outcome and a time frame, making it possible to evaluate project performance objectively.
Incorrect! Try again.
31Before estimating the cost of a proposed inventory system, the organization should first determine which information?
Business Planning: determining objectives
Medium
A.The number of comments in source code
B.The preferred editor for developers
C.The final color scheme of the interface
D.The business problem and expected outcomes
Correct Answer: The business problem and expected outcomes
Explanation:
Business planning begins by clarifying why the project is needed and what benefits or outcomes it must achieve.
Incorrect! Try again.
32A project depends on cloud services, test devices, secure networks, and a configuration-management system. These resources are collectively part of the project's:
Infrastructure
Medium
A.Legal contract
B.Scope baseline
C.Infrastructure
D.Market forecast
Correct Answer: Infrastructure
Explanation:
Project infrastructure includes the technical environment, tools, facilities, networks, and support resources needed to perform the work.
Incorrect! Try again.
33A company plans a software product for a market expected to grow rapidly, but it has only informal customer opinions. What should improve the demand forecast?
Forecasting demand for product
Medium
A.Base demand only on developer preferences
B.Ignore competing products
C.Use market evidence and customer research
D.Assume demand equals development capacity
Correct Answer: Use market evidence and customer research
Explanation:
Demand forecasting should use evidence such as customer research, market trends, competitor analysis, and historical data rather than unsupported assumptions.
Incorrect! Try again.
34A software project has uncertain requirements, changing technology, and dependencies on several teams. Which characteristic of software projects does this situation best demonstrate?
Characteristics
Medium
A.Minimal dependence on stakeholders
B.Fixed production procedures
C.High uncertainty and complexity
D.Low communication requirements
Correct Answer: High uncertainty and complexity
Explanation:
Software projects are often complex because they combine evolving requirements, technical uncertainty, human coordination, and organizational dependencies.
Incorrect! Try again.
35A proposal claims that a system will reduce processing time by 60% but provides no measurement method or supporting evidence. What is the main weakness?
Proposal writing
Medium
A.The proposal contains too many milestones
B.The proposal identifies a target customer
C.The proposal lacks a verifiable benefit basis
D.The proposal uses a technical vocabulary
Correct Answer: The proposal lacks a verifiable benefit basis
Explanation:
A credible proposal should support claimed benefits with assumptions, evidence, and measurable evaluation criteria.
Incorrect! Try again.
36A manager estimates effort only from the number of lines of code expected. Why is this approach risky?
Effort estimation
Medium
A.Effort also depends on complexity and other activities
B.Effort is determined only by the project budget
C.Lines of code cannot be recorded after testing
D.Lines of code always measure user satisfaction
Correct Answer: Effort also depends on complexity and other activities
Explanation:
Effort depends on factors such as requirements complexity, team capability, tools, integration, testing, and project constraints, not only code size.
Incorrect! Try again.
37Users describe a system as needing to be "fast" and "easy to use." What should the analyst do next?
Requirement analysis
Medium
A.Discard the statements as technically irrelevant
B.Wait until coding reveals their meaning
C.Implement the most advanced interface
D.Convert the statements into measurable requirements
Correct Answer: Convert the statements into measurable requirements
Explanation:
Vague requirements should be clarified and expressed in testable terms, such as response-time targets and usability criteria.
Incorrect! Try again.
38A project relies on a single supplier for a critical software library, and the supplier may discontinue support. How should this issue be recorded?
Risk identification
Medium
A.As a project opportunity
B.As a user-interface requirement
C.As a technical and supplier risk
D.As a completed project milestone
Correct Answer: As a technical and supplier risk
Explanation:
Dependence on a potentially unavailable supplier creates a risk that can affect technology continuity, maintenance, schedule, and cost.
Incorrect! Try again.
39A development team plans to include an open-source library in a commercial product. Which issue should be examined before adoption?
Legal issues
Medium
A.The office seating arrangement
B.The library's license obligations
C.The developers' preferred font
D.The number of project meetings
Correct Answer: The library's license obligations
Explanation:
Open-source licenses may impose conditions on attribution, redistribution, modification, or source-code disclosure, so legal review is necessary.
Incorrect! Try again.
40A software team discovers during development that a requirement interpreted incorrectly will affect several modules. Why can this be more disruptive than a similar late change in a physical production process?
Software Project Versus Other Types
Medium
A.Software requirements are always completely fixed
B.Software changes require no design decisions
C.Physical products never have dependencies
D.Software components are often highly interconnected
Correct Answer: Software components are often highly interconnected
Explanation:
A change in one software requirement can affect architecture, interfaces, code, tests, documentation, and dependent components.
Incorrect! Try again.
41A company continuously releases minor security patches while separately developing a one-time migration tool that will be retired after moving all customers to a new platform. Which classification is most defensible?
What is project?
Hard
A.Patching is operations, while the migration tool is a project
B.Both activities are projects because each produces software outputs
C.Patching is a project, while the migration tool is operations
D.Both activities are operations because each supports the same platform
Correct Answer: Patching is operations, while the migration tool is a project
Explanation:
A project is temporary and produces a specific result. Routine patching is ongoing operational work, whereas the migration tool has a defined objective and endpoint.
Incorrect! Try again.
42A construction project and a software project have equal budgets and durations. Midway through each, the client requests a major functional change. Why is the software project's cost impact usually harder to predict?
Software project versus other types
Hard
A.Software materials fluctuate more sharply in price than construction materials
B.Software teams cannot use formal models to estimate revised completion dates
C.Software deliverables cannot be divided into independently testable components
D.Software dependencies are less visible and changes may propagate nonlinearly
Correct Answer: Software dependencies are less visible and changes may propagate nonlinearly
Explanation:
Software has many logical and architectural dependencies that are difficult to observe directly. A small requirement change can affect design, code, tests, interfaces, and documentation.
Incorrect! Try again.
43A manager responds to a six-month schedule delay by doubling the development team during the final integration phase. Under which condition is this intervention most likely to delay the project further?
Nature of software production
Hard
A.The remaining modules are independent and require little domain knowledge
B.The integration tests are automated and partitioned across isolated environments
C.The new members replace unavailable staff with equivalent system knowledge
D.The work is tightly coupled and requires extensive onboarding communication
Correct Answer: The work is tightly coupled and requires extensive onboarding communication
Explanation:
In tightly coupled work, additional staff increase training and communication overhead. Late staffing can therefore reduce existing developers' productivity and worsen the delay.
Incorrect! Try again.
44A project is within budget and all planned tasks are complete, but acceptance testing shows that the delivered system does not support a critical business workflow. Which management activity most directly failed?
Activities by Software Project Management
Hard
A.Procurement monitoring and supplier invoice reconciliation
B.Requirement validation and scope-to-deliverable traceability
C.Schedule compression and milestone progress reporting
D.Resource leveling and development environment provisioning
Correct Answer: Requirement validation and scope-to-deliverable traceability
Explanation:
Completing scheduled tasks is insufficient when deliverables do not satisfy business needs. Validation and traceability should connect approved requirements to implementation and acceptance tests.
Incorrect! Try again.
45A sponsor demands simultaneous reductions in cost and delivery time while prohibiting scope or quality changes. The current plan already uses resources at sustainable capacity. What is the most appropriate managerial response?
Key objectives of effective management
Hard
A.Add developers immediately because staffing always reduces elapsed duration
B.Present the constraint conflict and negotiate a feasible priority trade-off
C.Reduce internal reviews because they do not create customer-visible features
D.Accept both targets and recover the difference during system testing
Correct Answer: Present the constraint conflict and negotiate a feasible priority trade-off
Explanation:
Effective management makes constraints and trade-offs explicit. When scope, quality, cost, and time cannot all remain fixed, the sponsor must prioritize or authorize a changed approach.
Incorrect! Try again.
46A project reports 90% completion for eight consecutive weeks because most modules are coded, although integration defects and unresolved requirements continue to grow. Which underlying problem best explains the misleading status?
Problems with software projects
Hard
A.The project uses iterative delivery instead of a sequential life cycle
B.The defect database contains both functional and performance issues
C.The team performs integration before completing user documentation
D.Progress is measured by activity completion instead of validated outcomes
Correct Answer: Progress is measured by activity completion instead of validated outcomes
Explanation:
Code completion does not establish usable progress. Outcome-based evidence such as integrated, tested, accepted functionality provides a more reliable measure.
Incorrect! Try again.
47A team must integrate an unfamiliar payment API whose performance and regulatory behavior are uncertain. Which early action provides the greatest direct reduction of technical and compliance uncertainty?
Risk reduction
Hard
A.Defer integration until all internally controlled features are completed
B.Increase the contingency reserve without changing the development plan
C.Assign additional developers to produce the full integration in parallel
D.Build a focused prototype and review its behavior with compliance specialists
Correct Answer: Build a focused prototype and review its behavior with compliance specialists
Explanation:
A targeted prototype creates evidence about the API, while specialist review tests regulatory assumptions. This reduces uncertainty rather than merely reserving funds for its consequences.
Incorrect! Try again.
48An organization authorizes an initiative with a dedicated team and budget but gives it no completion condition, unique deliverable, or measurable outcome. Which conclusion is most accurate?
Meaning of project
Hard
A.It is necessarily a project because it has dedicated resources
B.It is a program because every program lacks a fixed completion condition
C.It resembles operations because temporary purpose and closure are undefined
D.It is a project because measurable outcomes are optional at authorization
Correct Answer: It resembles operations because temporary purpose and closure are undefined
Explanation:
Dedicated resources alone do not define a project. A project requires a temporary endeavor directed toward a unique and sufficiently defined result.
Incorrect! Try again.
49A contract requires a mobile banking application with biometric login. During development, the sponsor asks for facial recognition, claiming it is already included under biometric login. Which artifact provides the strongest basis for deciding whether this is a scope change?
Project scope
Hard
A.The project calendar with release milestones and dependencies
B.The detailed scope baseline with requirements and acceptance criteria
C.The current risk register with security threat ratings
D.The original effort estimate with developer-day allocations
Correct Answer: The detailed scope baseline with requirements and acceptance criteria
Explanation:
The scope baseline and acceptance criteria define what the approved deliverable includes. A broad phrase in isolation cannot determine whether a specific biometric method was committed.
Incorrect! Try again.
50Which objective is best formulated for controlling a software project?
Objectives
Hard
A.Optimize application performance wherever the team finds bottlenecks
B.Improve response time significantly before the product is released
C.Create a highly reliable service that satisfies important users
D.Reduce the measured 95th-percentile latency to ms by release
Correct Answer: Reduce the measured 95th-percentile latency to ms by release
Explanation:
This objective specifies a measurable performance threshold and a deadline. The other choices use subjective terms or leave the target and completion condition unclear.
Incorrect! Try again.
51A proposed analytics platform has the objectives "use artificial intelligence," "increase revenue," and "launch this year." What is the most important correction before detailed project planning begins?
Business Planning: determining objectives
Hard
A.Convert each statement directly into a fixed-price supplier contract
B.Replace business objectives with a complete list of preferred technologies
C.Translate the statements into measurable outcomes linked to business strategy
D.Estimate development effort before stakeholders revise the stated objectives
Correct Answer: Translate the statements into measurable outcomes linked to business strategy
Explanation:
The current statements mix a possible solution, a vague benefit, and a broad deadline. Planning requires measurable objectives tied to a justified business outcome.
Incorrect! Try again.
52A distributed team repeatedly produces environment-specific defects because development, testing, and production use different configurations. Which infrastructure decision best addresses the root cause?
Infrastructure
Hard
A.Schedule more defect review meetings during the integration phase
B.Move final acceptance testing to the development team's local environment
C.Require developers to document their local configuration after each release
D.Standardize reproducible environments through version-controlled configuration
Correct Answer: Standardize reproducible environments through version-controlled configuration
Explanation:
Version-controlled, reproducible environments reduce configuration drift and make defects repeatable. Meetings or manual documentation do not reliably enforce consistency.
Incorrect! Try again.
53A subscription product forecasts first-year demand from a survey in which of 10,000 respondents expressed interest. Historical evidence shows that only of interested respondents become customers, with a plausible range of to . Which planning approach is most defensible?
Forecasting demand for product
Hard
A.Ignore the survey because uncertain forecasts provide no planning value
B.Plan only for 6,000 customers because stated interest directly measures demand
C.Model 600 to 1,800 customers and test capacity and cash-flow sensitivity
D.Plan only for 1,200 customers because historical conversion is certain
Correct Answer: Model 600 to 1,800 customers and test capacity and cash-flow sensitivity
Explanation:
Interested respondents number . Applying the conversion range gives to , which should be evaluated through scenario and sensitivity analysis.
Incorrect! Try again.
54A project uses emerging technology, serves multiple departments, and has a fixed regulatory deadline. Which project characteristic most strongly justifies incremental validation with stakeholders?
Characteristics
Hard
A.The project has a formally allocated budget and reporting structure
B.The departments share access to the same organizational infrastructure
C.The deadline is fixed by an external regulatory authority
D.The product contains intangible and progressively understood requirements
Correct Answer: The product contains intangible and progressively understood requirements
Explanation:
Software requirements and behavior are often difficult to understand fully before users interact with working increments. Incremental validation exposes misunderstandings early.
Incorrect! Try again.
55A vendor proposal promises delivery in six months at a fixed price but omits assumptions about client data quality, interface availability, and acceptance responsibilities. What is the greatest project risk created by these omissions?
Proposal writing
Hard
A.The proposal prevents the vendor from selecting a development methodology
B.The proposal cannot include a persuasive description of the vendor's experience
C.The customer must automatically accept every deliverable upon submission
D.The parties may interpret obligations differently and dispute resulting changes
Correct Answer: The parties may interpret obligations differently and dispute resulting changes
Explanation:
Unstated assumptions create ambiguity about dependencies and responsibility. When those assumptions fail, cost, schedule, and contractual disputes can follow.
Incorrect! Try again.
56A team estimates a project at 1,000 person-days. It expects 25 developers to complete the work in 40 working days by computing . Why is this schedule estimate most likely invalid?
Effort estimation
Hard
A.The calculation ignores task dependencies, communication, and limited parallelism
B.Person-days cannot be used to estimate any software development activity
C.The calculation assumes that developers work fewer than eight hours per day
D.A valid schedule must always equal twice the estimated development effort
Correct Answer: The calculation ignores task dependencies, communication, and limited parallelism
Explanation:
Effort is not perfectly divisible across workers. Dependencies, onboarding, coordination, and sequential tasks prevent a simple conversion from person-days to elapsed duration.
Incorrect! Try again.
57Two approved requirements state that every transaction must be permanently auditable and that customers may request complete deletion of all personal data. What should the analyst do first?
Requirement analysis
Hard
A.Resolve the conflict using legal constraints and data-retention rules
B.Prioritize the deletion requirement because customer requests occur later
C.Remove audit data from scope because nonfunctional requirements rank lower
D.Implement both literally and allow testing to reveal any inconsistency
Correct Answer: Resolve the conflict using legal constraints and data-retention rules
Explanation:
The requirements conflict where audit records contain personal data. The analyst should clarify applicable law and define retention, anonymization, or deletion rules before implementation.
Incorrect! Try again.
58A risk register lists "database," "security," and "staff" as its three highest risks. Which revision would most improve its usefulness for management?
Risk identification
Hard
A.Convert each label into a task and remove it from the risk register
B.Assign each label the same probability to simplify portfolio comparison
C.Rank the labels alphabetically and review them only after an incident
D.Replace each label with a cause-event-impact statement and an owner
Correct Answer: Replace each label with a cause-event-impact statement and an owner
Explanation:
Broad categories do not describe uncertain events or consequences. A cause-event-impact formulation supports probability assessment, response planning, triggers, and accountability.
Incorrect! Try again.
59A development team incorporates a library licensed under a strong copyleft license into a proprietary product distributed to customers. What should project management do before release?
Legal issues
Hard
A.Remove the copyright notice while retaining the compiled library
B.Proceed because open-source components never affect proprietary licensing
C.Assess license obligations and obtain legal approval for the distribution model
D.Delay review until a customer formally requests the corresponding source code
Correct Answer: Assess license obligations and obtain legal approval for the distribution model
Explanation:
Strong copyleft terms may impose source-disclosure or licensing obligations when software is distributed. The exact effect depends on the license and integration, so review is required before release.
Incorrect! Try again.
60A technically skilled team argues that formal project management is unnecessary because automated tests ensure software quality. Which response best identifies the flaw in that argument?
Importance of software project management
Hard
A.Automated tests address product behavior, not scope, resources, risks, or stakeholders
B.Project management is required only when a team lacks automated testing tools
C.Project management replaces technical practices by independently assuring quality
D.Automated tests eliminate defects but cannot calculate the project's final cost
Correct Answer: Automated tests address product behavior, not scope, resources, risks, or stakeholders
Explanation:
Testing is one quality-control mechanism. Project management also coordinates objectives, scope, schedule, resources, communication, dependencies, and risk throughout the project.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →