1What does the critical path represent in a project schedule?
Setting The Critical Path
Easy
A.The shortest sequence of independent tasks
B.The longest sequence of dependent tasks
C.The list of tasks with the highest costs
D.The group of tasks assigned to one resource
Correct Answer: The longest sequence of dependent tasks
Explanation:
The critical path is the longest sequence of dependent tasks that determines the project's earliest possible completion date.
Incorrect! Try again.
2Which task information is most important when calculating a project's critical path?
Setting The Critical Path
Easy
A.Colors and text styles
B.Notes and file attachments
C.Resource names and initials
D.Durations and task dependencies
Correct Answer: Durations and task dependencies
Explanation:
Task durations and dependencies determine the sequence and total length of the critical path.
Incorrect! Try again.
3What is the total slack of a critical task normally set to?
Setting The Critical Path
Easy
A.One week
B.One month
C.Two days
D.Zero time
Correct Answer: Zero time
Explanation:
A critical task normally has zero total slack, so delaying it can delay the project.
Incorrect! Try again.
4Which relationship helps establish the order of tasks on the critical path?
Setting The Critical Path
Easy
A.Cost category
B.Task dependency
C.Text formatting
D.Resource calendar
Correct Answer: Task dependency
Explanation:
Task dependencies define which tasks must precede or follow other tasks in the schedule.
Incorrect! Try again.
5What may happen to the critical path when a task duration is changed?
Setting The Critical Path
Easy
A.It must remain permanently fixed
B.It automatically removes all resources
C.It may change to another sequence
D.It converts every task into a milestone
Correct Answer: It may change to another sequence
Explanation:
Changing a task duration can make a different sequence of tasks the longest path through the project.
Incorrect! Try again.
6What is the main purpose of using a critical path view?
Using The Critical Path View
Easy
A.To identify tasks affecting the finish date
B.To rename all assigned resources
C.To create notes for every task
D.To display only project cost categories
Correct Answer: To identify tasks affecting the finish date
Explanation:
A critical path view highlights tasks that directly influence the project's completion date.
Incorrect! Try again.
7In many project management tools, how are critical tasks commonly distinguished in a Gantt view?
Using The Critical Path View
Easy
A.By highlighted task bars
B.By hidden task names
C.By deleted dependency lines
D.By blank duration fields
Correct Answer: By highlighted task bars
Explanation:
Critical tasks are commonly shown with highlighted or specially colored bars so they are easy to recognize.
Incorrect! Try again.
8Which chart commonly displays task bars along a project timeline?
Using The Critical Path View
Easy
A.Pie chart
B.Gantt chart
C.Radar chart
D.Scatter chart
Correct Answer: Gantt chart
Explanation:
A Gantt chart displays tasks as horizontal bars positioned along a project timeline.
Incorrect! Try again.
9What should a project manager monitor closely in the critical path view?
Using The Critical Path View
Easy
A.Progress of critical tasks
B.Color of resource labels
C.Number of project notes
D.Font size of task names
Correct Answer: Progress of critical tasks
Explanation:
Critical tasks require close monitoring because their delays can affect the project's finish date.
Incorrect! Try again.
10What does a dependency line between two task bars indicate?
Using The Critical Path View
Easy
A.An identical task cost
B.A completed project phase
C.A scheduling relationship
D.A shared formatting style
Correct Answer: A scheduling relationship
Explanation:
A dependency line shows that the timing of one task is related to the timing of another.
Incorrect! Try again.
11What does applying a critical-task filter display?
Filtering For Critical Tasks Only
Easy
A.Only tasks with assigned resources
B.Only tasks that have fixed costs
C.Only tasks completed this week
D.Only tasks classified as critical
Correct Answer: Only tasks classified as critical
Explanation:
The critical-task filter limits the displayed task list to tasks currently classified as critical.
Incorrect! Try again.
12Why would a project manager filter for critical tasks?
Filtering For Critical Tasks Only
Easy
A.To focus on schedule-sensitive work
B.To increase every task duration
C.To remove all task dependencies
D.To replace every assigned resource
Correct Answer: To focus on schedule-sensitive work
Explanation:
Filtering helps the manager concentrate on tasks whose delays may affect the project finish date.
Incorrect! Try again.
13What normally happens to noncritical tasks when a critical-task filter is applied?
Filtering For Critical Tasks Only
Easy
A.They are temporarily hidden
B.They are changed into milestones
C.They are permanently deleted
D.They are marked as completed
Correct Answer: They are temporarily hidden
Explanation:
A filter changes what is displayed; it does not delete or modify the hidden tasks.
Incorrect! Try again.
14What happens when the critical-task filter is cleared?
Filtering For Critical Tasks Only
Easy
A.All durations become zero
B.All dependencies are removed
C.All critical tasks are deleted
D.All relevant tasks appear again
Correct Answer: All relevant tasks appear again
Explanation:
Clearing the filter restores the normal view and displays tasks that were temporarily hidden.
Incorrect! Try again.
15Does filtering for critical tasks change the underlying project schedule?
Filtering For Critical Tasks Only
Easy
A.Yes, it shortens every task
B.Yes, it removes all constraints
C.No, it changes only the display
D.No, it permanently hides resources
Correct Answer: No, it changes only the display
Explanation:
Filtering controls which tasks are visible without changing task dates, durations, or dependencies.
Incorrect! Try again.
16Which action can directly shorten a project's critical path?
Shortening The Project
Easy
A.Adding notes to a summary task
B.Changing a noncritical task's color
C.Reducing a critical task's duration
D.Renaming an available resource
Correct Answer: Reducing a critical task's duration
Explanation:
Reducing the duration of a critical task can reduce the total duration of the critical path.
Incorrect! Try again.
17What is project crashing?
Shortening The Project
Easy
A.Adding resources to reduce task duration
B.Deleting tasks without reviewing scope
C.Moving every task to a later date
D.Stopping all work on the schedule
Correct Answer: Adding resources to reduce task duration
Explanation:
Crashing shortens a schedule by adding resources or cost to reduce the duration of suitable critical tasks.
Incorrect! Try again.
18What is fast tracking in project scheduling?
Shortening The Project
Easy
A.Overlapping tasks that were sequential
B.Removing resources from critical tasks
C.Postponing work until dependencies finish
D.Increasing the duration of every task
Correct Answer: Overlapping tasks that were sequential
Explanation:
Fast tracking shortens the schedule by performing some tasks in parallel instead of entirely in sequence.
Incorrect! Try again.
19Which tasks should usually be examined first when trying to shorten the project finish date?
Shortening The Project
Easy
A.Tasks displayed at the top
B.Tasks with the most notes
C.Tasks on the critical path
D.Tasks with the longest names
Correct Answer: Tasks on the critical path
Explanation:
Critical-path tasks directly determine the project duration, so they are the first candidates for schedule reduction.
Incorrect! Try again.
20What is a common risk of fast tracking a project?
Shortening The Project
Easy
A.All resources become unavailable
B.Every dependency becomes stronger
C.All project costs become zero
D.More rework may be required
Correct Answer: More rework may be required
Explanation:
Overlapping dependent tasks can cause rework if an earlier task changes after later work has already begun.
Incorrect! Try again.
21A project manager changes the critical-task threshold from days of total slack to days. Which tasks will now be treated as critical?
Setting The Critical Path
Medium
A.Tasks starting within the next days
B.Tasks with durations longer than days
C.Tasks with free slack of exactly days
D.Tasks with total slack of days or less
Correct Answer: Tasks with total slack of days or less
Explanation:
The critical-task threshold classifies tasks as critical when their total slack is less than or equal to the configured value.
Incorrect! Try again.
22A task has an early finish on day 12 and a late finish on day 15. Assuming no other constraints, what is its total slack and critical status when the threshold is days?
Setting The Critical Path
Medium
A. days of slack; noncritical
B. days of slack; critical
C. days of slack; critical
D. days of slack; noncritical
Correct Answer: days of slack; noncritical
Explanation:
Total slack is days. Since the threshold is days, the task is not critical.
Incorrect! Try again.
23A project contains two independent task networks, but only one network determines the overall project finish date. The manager wants a critical path calculated for each network. Which setting should be enabled?
Setting The Critical Path
Medium
A.Show project summary task
B.Calculate multiple critical paths
C.Move completed task parts
D.Level resources automatically
Correct Answer: Calculate multiple critical paths
Explanation:
The multiple-critical-paths setting allows each independent task network to have its own critical path.
Incorrect! Try again.
24After task dependencies are entered, several tasks unexpectedly show large amounts of slack. Which project setup issue should be checked first?
Setting The Critical Path
Medium
A.Hidden resource names in the Gantt chart
B.Different font sizes in the task table
C.Missing dependency links between task sequences
D.Inconsistent notes attached to task rows
Correct Answer: Missing dependency links between task sequences
Explanation:
Missing links can leave tasks loosely connected to the project finish, producing misleading slack and critical-path calculations.
Incorrect! Try again.
25Task A takes 4 days, Task B takes 6 days, and Task C takes 3 days. A and B start together, and C cannot start until both finish. Which branch is initially critical?
Setting The Critical Path
Medium
A.Task B followed by Task C
B.Tasks A and B without Task C
C.Task A followed by Task C
D.Task C without either predecessor
Correct Answer: Task B followed by Task C
Explanation:
The B-C branch lasts days, while the A-C branch is constrained by the longer predecessor and does not determine C's start.
Incorrect! Try again.
26In a critical-path Gantt view, a critical task bar changes from red to a noncritical color after its duration is reduced. What is the best interpretation?
Using The Critical Path View
Medium
A.The task was removed from the project
B.The task gained slack after recalculation
C.The task lost all predecessor relationships
D.The task became a project milestone
Correct Answer: The task gained slack after recalculation
Explanation:
A shortened task may no longer control the finish date. If it gains slack, the view displays it as noncritical.
Incorrect! Try again.
27A manager wants to inspect critical tasks while still seeing their relationships with nearby noncritical tasks. Which approach is most appropriate?
Using The Critical Path View
Medium
A.Apply the Critical filter and hide all other tasks
B.Delete noncritical tasks from the current schedule
C.Display critical formatting in the full Gantt view
D.Sort tasks only by assigned resource names
Correct Answer: Display critical formatting in the full Gantt view
Explanation:
Critical formatting highlights critical tasks while retaining noncritical tasks and dependency context in the schedule.
Incorrect! Try again.
28While reviewing a Tracking Gantt, the manager sees that an incomplete critical task's actual progress is behind its baseline bar. What risk does this most directly indicate?
Using The Critical Path View
Medium
A.The project finish date may be delayed
B.The resource rate may be calculated twice
C.The task calendar may be deleted automatically
D.The baseline task may become a summary task
Correct Answer: The project finish date may be delayed
Explanation:
Delay on an incomplete critical task directly threatens the project finish because the task has little or no scheduling flexibility.
Incorrect! Try again.
29Two critical tasks overlap because the second task has a start-to-start dependency with a 2-day lag. What should the manager examine to understand the overlap?
Using The Critical Path View
Medium
A.The resource initials and group name
B.The task font and row height
C.The dependency type and lag value
D.The project title and author fields
Correct Answer: The dependency type and lag value
Explanation:
A start-to-start link permits overlap, while the lag determines how long after the predecessor starts the successor may start.
Incorrect! Try again.
30A manager shortens one task on the displayed critical path, but the project finish date does not change. The view now highlights another sequence as critical. What most likely happened?
Using The Critical Path View
Medium
A.The project calendar stopped calculating time
B.The baseline replaced the current project schedule
C.A parallel path became the controlling path
D.All task dependencies were converted to milestones
Correct Answer: A parallel path became the controlling path
Explanation:
Shortening one critical sequence can expose a parallel sequence of equal or greater duration, making it the new critical path.
Incorrect! Try again.
31After applying the Critical task filter, several summary tasks disappear even though they contain critical subtasks. What is the most likely reason?
Filtering For Critical Tasks Only
Medium
A.The summary tasks themselves are not marked critical
B.The project baseline contains no summary tasks
C.The critical subtasks were automatically deleted
D.The resource sheet is controlling the current view
Correct Answer: The summary tasks themselves are not marked critical
Explanation:
A filter evaluates each displayed row. A summary task may fail the filter even when some of its subtasks are critical.
Incorrect! Try again.
32A manager applies the Critical filter and then needs to restore every task without changing task data. Which action should be taken?
Filtering For Critical Tasks Only
Medium
A.Recalculate resource costs
B.Reopen the saved baseline
C.Undo every scheduling change
D.Clear the current filter
Correct Answer: Clear the current filter
Explanation:
Filtering only controls which rows are displayed. Clearing the filter restores the full task list without modifying schedule data.
Incorrect! Try again.
33The manager needs a list of tasks that are both critical and incomplete. Which filter logic should be used?
Filtering For Critical Tasks Only
Medium
A.Critical equals Yes OR Percent Complete equals
B.Critical equals No AND Percent Complete is less than
C.Critical equals No OR Percent Complete equals
D.Critical equals Yes AND Percent Complete is less than
Correct Answer: Critical equals Yes AND Percent Complete is less than
Explanation:
Both conditions must be satisfied: the task must be critical and must not yet be fully complete.
Incorrect! Try again.
34After applying a critical-task filter, the row numbers are no longer consecutive. What does this indicate?
Filtering For Critical Tasks Only
Medium
A.Critical tasks have been copied to a new project
B.Task identifiers have been permanently renumbered
C.Dependencies between visible tasks are invalid
D.Nonmatching tasks are hidden rather than deleted
Correct Answer: Nonmatching tasks are hidden rather than deleted
Explanation:
A filter hides rows that do not match its criteria, so the remaining task identifiers can appear nonconsecutive.
Incorrect! Try again.
35A task with 1 day of total slack appears when the Critical filter is applied. Which configuration best explains this result?
Filtering For Critical Tasks Only
Medium
A.The task duration is exactly 1 day
B.The project has only one assigned resource
C.The critical threshold is at least 1 day
D.The task uses a start-to-start dependency
Correct Answer: The critical threshold is at least 1 day
Explanation:
If tasks with slack of 1 day or less are defined as critical, a task with 1 day of total slack will pass the Critical filter.
Incorrect! Try again.
36A critical task requires 12 person-days of work and is assigned to one full-time resource, giving it a 12-day duration. Under ideal divisible-work conditions, what duration would two equally productive full-time resources produce?
Shortening The Project
Medium
A.10 days
B.12 days
C.6 days
D.24 days
Correct Answer: 6 days
Explanation:
Under ideal effort-driven conditions, doubling the resource capacity reduces the duration to days.
Incorrect! Try again.
37A noncritical task has 5 days of total slack. Its duration is reduced by 3 days, but no dependencies change. What is the most likely effect on the project finish date?
Shortening The Project
Medium
A.The finish date remains unchanged
B.The finish date moves earlier by 5 days
C.The finish date moves later by 2 days
D.The finish date moves earlier by 3 days
Correct Answer: The finish date remains unchanged
Explanation:
Shortening a noncritical task within its available slack usually increases its slack without changing the overall project finish.
Incorrect! Try again.
38A project has two parallel paths lasting 18 days and 17 days. The manager shortens the 18-day path by 3 days. What is the new project duration, assuming no other constraints?
Shortening The Project
Medium
A.15 days
B.14 days
C.18 days
D.17 days
Correct Answer: 17 days
Explanation:
After shortening, the first path lasts 15 days, so the unchanged 17-day path becomes critical and determines the project duration.
Incorrect! Try again.
39A task on the critical path can be crashed by 2 days for an additional cost of $800. Another critical task can be crashed by 3 days for $1,800. Which task has the lower crash cost per day?
Shortening The Project
Medium
A.The second task at $600 per day
B.The first task at $400 per day
C.The first task at $800 per day
D.The second task at $900 per day
Correct Answer: The first task at $400 per day
Explanation:
The first task costs dollars per day, while the second costs dollars per day.
Incorrect! Try again.
40A manager wants to shorten a project without changing the required deliverables. Which action should be evaluated first?
Shortening The Project
Medium
A.Reduce the baseline duration of completed tasks
B.Shorten tasks with the greatest positive slack
C.Remove dependencies from every summary task
D.Compress durations of feasible critical tasks
Correct Answer: Compress durations of feasible critical tasks
Explanation:
Only shortening tasks that currently control the finish date can directly reduce project duration, provided the work can be compressed feasibly.
Incorrect! Try again.
41A project network contains the following finish-to-start paths, with all durations in working days: and . If task is delayed by one day and no other condition changes, what is the resulting critical-path situation?
Setting The Critical Path
Hard
A.Both paths become critical, and the project completion date remains unchanged
B.Only the path through remains critical, and completion moves by one day
C.Only the path through becomes critical, and completion moves by one day
D.Both paths become critical, and the project completion date moves by one day
Correct Answer: Both paths become critical, and the project completion date remains unchanged
Explanation:
Before the delay, the paths are and days long. Delaying by one day makes both paths days, consuming the shorter path's one day of slack without changing project completion.
Incorrect! Try again.
42A scheduling application is configured to define tasks as critical when total slack is less than or equal to two days. A task has two days of total slack. Which interpretation is correct?
Setting The Critical Path
Hard
A.The task is noncritical unless its free slack is also exactly zero days
B.The task is displayed as critical only after one day of actual delay occurs
C.The task is displayed as critical even though it can currently slip by two days
D.The task is noncritical because only zero-slack tasks can be marked critical
Correct Answer: The task is displayed as critical even though it can currently slip by two days
Explanation:
The configured critical-task threshold controls classification. With a two-day threshold, a task having two days of total slack is marked critical despite retaining that amount of scheduling flexibility.
Incorrect! Try again.
43A master schedule has three independent delivery chains, each ending in a different milestone. Only one chain controls the overall project finish. What is the primary effect of enabling the option to calculate multiple critical paths?
Setting The Critical Path
Hard
A.It combines the three endpoint milestones into one mandatory finish milestone
B.It identifies a critical path terminating at each independent chain's endpoint
C.It marks every task with zero free slack as critical across all chains
D.It marks only the longest chain while displaying its near-critical alternatives
Correct Answer: It identifies a critical path terminating at each independent chain's endpoint
Explanation:
Multiple-critical-path calculation treats each independent network endpoint as a finish point and identifies the driving path to each endpoint, not merely the path controlling the latest project finish.
Incorrect! Try again.
44A task has a deadline on day 20 but is currently scheduled to finish on day 23. No date constraint was assigned to the task. Which result is most consistent with critical-path scheduling?
Setting The Critical Path
Hard
A.The deadline converts the task automatically to a must-finish-on constraint
B.The deadline changes only free slack and cannot affect critical classification
C.The deadline forces the task to finish on day 20 and removes negative slack
D.The deadline leaves the dates unchanged but can produce negative total slack
Correct Answer: The deadline leaves the dates unchanged but can produce negative total slack
Explanation:
A deadline normally acts as a monitoring target rather than a scheduling constraint. Missing it can create negative total slack and cause affected tasks to be classified as critical.
Incorrect! Try again.
45Two otherwise identical predecessor tasks start together and feed the same successor. Task uses a seven-day calendar and takes four days; task uses a weekday-only calendar and takes four working days. Why can their total slack differ even though their entered durations are equal?
Setting The Critical Path
Hard
A.A seven-day calendar always adds two days of total slack to its assigned task
B.Slack is computed from scheduled dates produced by the applicable calendars
C.Calendar differences affect resource cost but never affect network path length
D.Critical-path calculations compare task names when entered durations are equal
Correct Answer: Slack is computed from scheduled dates produced by the applicable calendars
Explanation:
Equal entered durations do not guarantee equal elapsed finish dates. Task, resource, and project calendars influence scheduled dates, which in turn influence path length and slack.
Incorrect! Try again.
46A task shown as critical in the Critical Path view is completed three days early, but no successor date changes. What is the most likely explanation?
Using The Critical Path View
Hard
A.The successor has an inflexible constraint or another predecessor still controls it
B.The view permanently preserves the baseline critical path after execution begins
C.Completed critical tasks never transmit early finishes to their successor tasks
D.Early completion increases task duration while decreasing its remaining duration
Correct Answer: The successor has an inflexible constraint or another predecessor still controls it
Explanation:
An early finish helps only if the task is currently driving its successor. A constraint or a later-finishing predecessor can prevent the successor and project finish from moving earlier.
Incorrect! Try again.
47After resource leveling, a previously noncritical task appears critical in the Critical Path view even though none of its logical dependencies changed. Which explanation is strongest?
Using The Critical Path View
Hard
A.Leveling changed the baseline duration and therefore redefined the original network
B.Leveling replaced the task's logical predecessors with resource-driven dependencies
C.Leveling marks every task using an overallocated resource as permanently critical
D.Leveling delays changed scheduled dates and consumed the task's available total slack
Correct Answer: Leveling delays changed scheduled dates and consumed the task's available total slack
Explanation:
Resource leveling can insert delays or split work. Those scheduling changes may consume total slack and create a new critical path without altering the underlying dependency links.
Incorrect! Try again.
48In a Critical Path view, a summary task is marked critical while one of its subtasks is noncritical. Which conclusion is valid?
Using The Critical Path View
Hard
A.Summary tasks are always marked critical regardless of the status of their subtasks
B.The schedule is corrupted because every subtask of a critical summary must be critical
C.The summary span is critical, but that particular subtask retains scheduling flexibility
D.The subtask must have negative free slack even though its total slack is positive
Correct Answer: The summary span is critical, but that particular subtask retains scheduling flexibility
Explanation:
A critical summary reflects the scheduling status of its overall span. Individual subtasks can still have slack when another subtask or chain within that summary drives its finish.
Incorrect! Try again.
49A task has zero free slack and five days of total slack. How should it normally appear when the Critical Path view uses the standard zero-total-slack definition?
Using The Critical Path View
Hard
A.Noncritical, because only tasks with negative free slack can be classified critical
B.Noncritical, because critical classification normally depends on total slack
C.Critical, because every task directly driving a successor controls project finish
D.Critical, because zero free slack always overrides positive total slack
Correct Answer: Noncritical, because critical classification normally depends on total slack
Explanation:
Zero free slack means the task cannot slip without affecting an immediate successor. Its five days of total slack mean it can still slip without affecting project completion, so it is normally noncritical.
Incorrect! Try again.
50A manager saves a baseline and later changes task logic. The current Critical Path view differs from the critical sequence visible in baseline-related bars. Which statement best explains the difference?
Using The Critical Path View
Hard
A.Both paths must remain identical unless the project finish date itself has changed
B.The baseline path is recalculated from actual dates, while current bars preserve original logic
C.The current path is recalculated from live dates, while baseline values preserve the earlier plan
D.Baseline bars control current slack calculations whenever a saved baseline is available
Correct Answer: The current path is recalculated from live dates, while baseline values preserve the earlier plan
Explanation:
The current critical path responds to current dependencies, durations, calendars, and constraints. Baseline data remains a snapshot for comparison and does not drive current slack calculations.
Incorrect! Try again.
51After applying a Critical Tasks filter, a visible critical task seems to have no predecessor because its predecessor row disappeared. What should the scheduler infer first?
Filtering For Critical Tasks Only
Hard
A.The dependency was deleted automatically when the filter was applied
B.The predecessor must be a milestone because filters suppress all milestone rows
C.The successor became critical only because filtering recalculated its total slack
D.The hidden predecessor may be noncritical even though the visible successor is critical
Correct Answer: The hidden predecessor may be noncritical even though the visible successor is critical
Explanation:
Filtering hides rows but does not remove dependencies or recalculate the schedule. A critical task can have a noncritical predecessor, especially when another predecessor controls its start.
Incorrect! Try again.
52A schedule defines critical tasks as those with total slack of at most three days. Which custom filter most faithfully reproduces the built-in critical classification?
Filtering For Critical Tasks Only
Hard
A.Select tasks where Critical = Yes
B.Select tasks where Finish Variance >= 3 days
C.Select tasks where Free Slack <= 3 days
D.Select tasks where Total Slack = 0 days
Correct Answer: Select tasks where Critical = Yes
Explanation:
The Critical field incorporates the schedule's configured critical-slack threshold. A hard-coded slack test may diverge if settings, calendars, or application rules change.
Incorrect! Try again.
53A scheduler needs to see all tasks while making critical tasks visually prominent. Why is highlighting generally preferable to applying a Critical Tasks filter?
Filtering For Critical Tasks Only
Hard
A.Highlighting changes critical task durations while preserving every dependency row
B.Highlighting recalculates slack more accurately than filtering the same task field
C.Highlighting permanently formats critical tasks in every project view and report
D.Highlighting retains surrounding task context while emphasizing matching critical rows
A filter removes nonmatching rows from view, which can obscure dependency context. Highlighting preserves all rows and visually distinguishes tasks that satisfy the critical criterion.
Incorrect! Try again.
54A custom filter requests tasks where Critical = YesANDRemaining Duration > 0. Which critical tasks will be omitted?
Filtering For Critical Tasks Only
Hard
A.Critical tasks that have zero free slack but positive total slack
B.Critical tasks that have successors with positive remaining duration
C.Critical tasks whose baseline duration differs from current duration
D.Critical tasks that are complete or have no remaining duration
Correct Answer: Critical tasks that are complete or have no remaining duration
Explanation:
Both filter conditions must be true. Completed critical tasks and zero-duration critical milestones with no remaining duration fail the second condition and are therefore omitted.
Incorrect! Try again.
55A filtered view shows only one critical path, but the project manager expects two. Which diagnostic action is most appropriate before concluding that the second path was deleted?
Filtering For Critical Tasks Only
Hard
A.Verify critical-slack settings, multiple-path settings, and any additional filter criteria
B.Delete all constraints and assign every task the project's default calendar
C.Set every task's free slack to zero and then reapply the current filter
D.Save a new baseline so both expected paths inherit identical baseline dates
Correct Answer: Verify critical-slack settings, multiple-path settings, and any additional filter criteria
Explanation:
A missing path may result from the critical threshold, disabled multiple-path calculation, or compound filter conditions. These settings should be checked before modifying schedule logic.
Incorrect! Try again.
56A project has two parallel paths: and . All links are finish-to-start, and both paths start together. What is the maximum project reduction obtainable by shortening only task by four days?
Shortening The Project
Hard
A.One day
B.Two days
C.Three days
D.Four days
Correct Answer: Two days
Explanation:
The paths initially take and days. Shortening can reduce the first path only until both paths reach days, so the overall project can improve by at most two days.
Incorrect! Try again.
57A critical task can be crashed from eight to five days for an additional cost of . A second critical task can be crashed from six to four days for . Assuming either reduction directly shortens the project, which task has the lower crash cost per day?
Shortening The Project
Hard
A.The first task at per day
B.The second task at per day
C.The first task at per day
D.The second task at per day
Correct Answer: The first task at per day
Explanation:
The first task costs per day shortened. The second costs per day, so the first is more economical.
Incorrect! Try again.
58A finish-to-start link from testing to deployment contains a three-day lag for approval processing. The approval can now occur in one day without changing either task's work. Which schedule change most directly shortens the path with the least distortion?
Shortening The Project
Hard
A.Reduce the dependency lag from three days to one day
B.Reduce the testing duration by two days without changing scope
C.Increase deployment resources until its start moves two days earlier
D.Apply a two-day lead while retaining the three-day approval lag
Correct Answer: Reduce the dependency lag from three days to one day
Explanation:
The changed business condition concerns approval waiting time, which is represented by the lag. Reducing that lag models the real change directly without falsifying task duration or resource productivity.
Incorrect! Try again.
59A project has two critical paths that share only the final milestone. Management needs to shorten project completion by two days. Which strategy is sufficient?
Shortening The Project
Hard
A.Shorten any noncritical task whose free slack is less than two days
B.Shorten the final zero-duration milestone by two working days
C.Shorten a task on either critical path by two days
D.Shorten tasks on both critical paths by at least two days each
Correct Answer: Shorten tasks on both critical paths by at least two days each
Explanation:
With two independent critical paths, shortening only one leaves the other controlling the finish. Each path must be reduced by the required amount, unless a shortened activity is common to both paths.
Incorrect! Try again.
60A task on the critical path is changed from a five-day finish-to-start predecessor of integration to a five-day start-to-start predecessor with a two-day lag. Assuming calendars permit the overlap, by how much can integration start earlier?
Shortening The Project
Hard
A.Five days earlier
B.Two days earlier
C.Three days earlier
D.Seven days earlier
Correct Answer: Three days earlier
Explanation:
Originally integration starts after day . With a start-to-start link and two-day lag, it starts after day , producing a three-day advance. This is fast tracking and may introduce rework risk.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →