The Network Diagram view displays project tasks as boxes connected by lines that represent dependencies.
Incorrect! Try again.
2What does a box, also called a node, represent in a Network Diagram?
Examining A Network Diagram
Easy
A.A project report
B.A cost account
C.A resource calendar
D.A project task
Correct Answer: A project task
Explanation:
Each node in a Network Diagram represents a task and can display information such as its name, duration, and dates.
Incorrect! Try again.
3What is the purpose of a summary task in a Network Diagram?
Understanding Summary Tasks In Network Design view
Easy
A.To group related subtasks
B.To delete completed tasks
C.To assign one resource
D.To create a new calendar
Correct Answer: To group related subtasks
Explanation:
A summary task combines and summarizes information from a group of related subtasks.
Incorrect! Try again.
4What is affected when the linkage between two tasks is changed?
Changing Task Linkage
Easy
A.The dependency between the tasks
B.The hourly rate of resources
C.The color of the project calendar
D.The font used for task names
Correct Answer: The dependency between the tasks
Explanation:
Changing task linkage modifies how the timing of one task depends on another task.
Incorrect! Try again.
5Which view should be selected to display tasks as connected boxes?
To change to Network Diagram view
Easy
A.Calendar
B.Network Diagram
C.Resource Sheet
D.Task Usage
Correct Answer: Network Diagram
Explanation:
Selecting Network Diagram changes the project display to task nodes connected by dependency lines.
Incorrect! Try again.
6Which zoom choice is most suitable for displaying the complete project at once?
To ZOOM and see the whole of the project
Easy
A.Custom Timescale
B.One Week
C.Selected Tasks
D.Entire Project
Correct Answer: Entire Project
Explanation:
The Entire Project zoom option adjusts the display so that the full project can be viewed.
Incorrect! Try again.
7What is a common way to open a task node for editing in Network Diagram view?
To open a node for editing
Easy
A.Right-click the scrollbar
B.Double-click the status bar
C.Drag the view divider
D.Double-click the node
Correct Answer: Double-click the node
Explanation:
Double-clicking a node commonly opens its Task Information dialog for editing.
Incorrect! Try again.
8Which information may be edited for a task node in Network Diagram view?
To edit a node directly in Network Diagram view
Easy
A.Task name and duration
B.Application name and version
C.Printer name and location
D.Workbook name and formula
Correct Answer: Task name and duration
Explanation:
Task fields displayed in a node, such as the task name or duration, can be edited.
Incorrect! Try again.
9What is the purpose of laying out boxes in a Network Diagram?
To Layout the boxes
Easy
A.To calculate resource pay rates
B.To create project backup files
C.To change the working calendar
D.To organize task nodes clearly
Correct Answer: To organize task nodes clearly
Explanation:
Arranging the boxes improves readability and makes task relationships easier to follow.
Incorrect! Try again.
10Which dialog is generally used to control the arrangement of Network Diagram boxes?
To control the layout
Easy
A.Layout dialog
B.Save As dialog
C.Print dialog
D.Spelling dialog
Correct Answer: Layout dialog
Explanation:
The Layout dialog provides settings for positioning, spacing, and arranging Network Diagram boxes.
Incorrect! Try again.
11When manual positioning is enabled, how can a node be moved?
To move a node
Easy
A.Drag it to a new position
B.Print it on another page
C.Rename it in the calendar
D.Assign it to another file
Correct Answer: Drag it to a new position
Explanation:
With manual positioning enabled, a node can be moved by dragging it to the required location.
Incorrect! Try again.
12After copying a task node, what must be added to show a dependency involving the copied task?
To copy a node and link to it
Easy
A.A note in the status bar
B.A page break after the node
C.A calendar below the diagram
D.A link between the nodes
Correct Answer: A link between the nodes
Explanation:
A dependency line must connect the copied task to the appropriate predecessor or successor.
Incorrect! Try again.
13Which feature controls the fields displayed inside Network Diagram nodes?
To change the content of the nodes
Easy
A.Resource calendars
B.Data templates
C.Print margins
D.Cost tables
Correct Answer: Data templates
Explanation:
Data templates determine which task fields appear within Network Diagram boxes.
Incorrect! Try again.
14Which formatting feature is used to change a node's border color and style?
To change border color and style
Easy
A.Page Setup
B.Box Styles
C.Resource Graph
D.Task Notes
Correct Answer: Box Styles
Explanation:
Box Styles controls visual properties of nodes, including their borders, colors, and shapes.
Incorrect! Try again.
15Which feature can change the appearance of summary-task nodes?
To change the way a summary task is displayed
Easy
A.Change Working Time
B.Resource Leveling
C.Box Styles
D.Project Statistics
Correct Answer: Box Styles
Explanation:
Box Styles can apply a distinct border, color, or data template to summary-task nodes.
Incorrect! Try again.
16What can be opened by double-clicking a link line between two task nodes?
To view the type of relationship
Easy
A.Project Properties dialog
B.Task Dependency dialog
C.Resource Information dialog
D.Change Calendar dialog
Correct Answer: Task Dependency dialog
Explanation:
The Task Dependency dialog displays information about the relationship between the connected tasks.
Incorrect! Try again.
17Which of the following is a valid task relationship type?
To change the relationship type
Easy
A.Finish-to-Start
B.Calendar-to-Task
C.Resource-to-Report
D.Budget-to-Cost
Correct Answer: Finish-to-Start
Explanation:
Finish-to-Start is a standard dependency in which the successor starts after the predecessor finishes.
Incorrect! Try again.
18What happens when a link line between two nodes is removed?
To remove a link line
Easy
A.Both task nodes are deleted
B.The task dependency is removed
C.Both task durations become zero
D.The project calendar is cleared
Correct Answer: The task dependency is removed
Explanation:
Deleting a link line removes the dependency but does not delete the connected tasks.
Incorrect! Try again.
19What does manually drawing a link line between two task nodes create?
To manually add a link line
Easy
A.A task dependency
B.A summary report
C.A project calendar
D.A resource assignment
Correct Answer: A task dependency
Explanation:
A link line connects a predecessor and successor, creating a dependency between them.
Incorrect! Try again.
20Why would a user reform the Network Diagram layout after making changes?
Reform the layout
Easy
A.To remove all task dates
B.To rearrange nodes neatly
C.To rename the project file
D.To increase resource rates
Correct Answer: To rearrange nodes neatly
Explanation:
Reforming the layout reorganizes the nodes and link lines so the updated diagram is easier to read.
Incorrect! Try again.
21A project manager wants to focus on task dependencies and the sequence of work rather than dates displayed on a time-scaled chart. Which view is most appropriate?
Understanding The Network Diagram View
Medium
A.Calendar view
B.Network Diagram view
C.Resource Sheet view
D.Task Usage view
Correct Answer: Network Diagram view
Explanation:
Network Diagram view represents tasks as nodes connected by dependency lines, making the logical sequence of work easier to analyze.
Incorrect! Try again.
22While examining a network diagram, Task B has an incoming link from Task A and an outgoing link to Task C. What does this arrangement normally indicate?
Examining A Network Diagram
Medium
A.Task B follows A and precedes C
B.Task B starts independently of A and C
C.Task B contains both A and C
D.Task B uses resources from A and C
Correct Answer: Task B follows A and precedes C
Explanation:
An incoming link identifies a predecessor, while an outgoing link identifies a successor. Therefore, B occurs logically between A and C.
Incorrect! Try again.
23A summary task node appears above several related task nodes in a network diagram. What is the summary task primarily representing?
Understanding Summary Tasks In Network Design view
Medium
A.An automatically inserted deadline
B.A resource assigned across tasks
C.An aggregation of its subtasks
D.A dependency between two milestones
Correct Answer: An aggregation of its subtasks
Explanation:
A summary task groups its indented subtasks and summarizes information such as their overall duration, start date, and finish date.
Incorrect! Try again.
24Testing should begin only after both coding and documentation are complete. Which linkage change best models this requirement?
Changing Task Linkage
Medium
A.Place all three tasks under one summary task
B.Make testing a predecessor of both tasks
C.Assign the same resource to all three tasks
D.Make both tasks predecessors of testing
Correct Answer: Make both tasks predecessors of testing
Explanation:
Giving testing two predecessors ensures that its scheduling is controlled by the completion requirements of both coding and documentation.
Incorrect! Try again.
25A user is currently working in Gantt Chart view and needs to inspect tasks as connected nodes. What should the user do?
To change to Network Diagram view
Medium
A.Apply the critical-tasks filter to the Gantt chart
B.Insert the predecessors column into the task table
C.Select Network Diagram from the available views
D.Select Resource Graph from the available views
Correct Answer: Select Network Diagram from the available views
Explanation:
Choosing Network Diagram from the view commands changes the display from time-scaled bars to dependency-connected task nodes.
Incorrect! Try again.
26Only a small section of a large network diagram is visible. Which zoom choice is most suitable for obtaining an overall view of the project?
To ZOOM and see the whole of the project
Medium
A.Zoom to Selected Tasks
B.Expand the active summary task
C.Increase the timescale units
D.Zoom to Entire Project
Correct Answer: Zoom to Entire Project
Explanation:
The Entire Project zoom option scales the network diagram so that the complete project structure fits within the available viewing area as closely as possible.
Incorrect! Try again.
27A task node contains an incorrect duration and several other details may also need revision. Which action most directly opens the full task-editing interface?
To open a node for editing
Medium
A.Drag the node to another row
B.Double-click an empty diagram area
C.Click the node's outgoing link
D.Double-click the task node
Correct Answer: Double-click the task node
Explanation:
Double-clicking a node opens its Task Information dialog, where fields such as duration, dates, predecessors, and resources can be edited.
Incorrect! Try again.
28A manager needs to make a quick change to a task name without opening the complete Task Information dialog. What is the appropriate approach?
To edit a node directly in Network Diagram view
Medium
A.Drag the node until the new task name is displayed
B.Select the connecting line and enter the new value
C.Select the editable field in the node and enter the new value
D.Change the diagram's data template for every node
Correct Answer: Select the editable field in the node and enter the new value
Explanation:
When direct editing is supported for the displayed field, selecting that field in the node allows its task value to be changed without opening the full dialog.
Incorrect! Try again.
29After several dependencies are added, task boxes overlap and link lines are difficult to follow. Which operation should be applied first?
To Layout the boxes
Medium
A.Replace links with constraints
B.Convert tasks into milestones
C.Sort tasks by resource name
D.Run the box layout operation
Correct Answer: Run the box layout operation
Explanation:
The layout operation reorganizes task boxes according to the current layout settings and reduces visual overlap.
Incorrect! Try again.
30A user wants to adjust the spacing between network nodes and choose whether boxes are positioned automatically. Which settings should be changed?
To control the layout
Medium
A.Task Constraint settings
B.Resource Leveling settings
C.Network Diagram Layout settings
D.Project Calendar settings
Correct Answer: Network Diagram Layout settings
Explanation:
Layout settings control characteristics such as box arrangement, row and column spacing, link routing, and automatic or manual positioning.
Incorrect! Try again.
31Dragging a task node does not leave it in the selected location because the diagram immediately repositions it. What should be changed before manually arranging the node?
To move a node
Medium
A.Enable manual box positioning
B.Remove the task's assigned resources
C.Disable task dependency links
D.Convert the task to a milestone
Correct Answer: Enable manual box positioning
Explanation:
Automatic layout can override manual placement. Enabling manual box positioning allows a node to remain where it is dragged.
Incorrect! Try again.
32A task must be duplicated and the original task should become the predecessor of the copy. Which sequence best meets the requirement?
To copy a node and link to it
Medium
A.Move the original task, then rename its summary task
B.Paste the task as a milestone, then remove its duration
C.Copy and paste the task, then create a link to the copy
D.Copy the link line, then assign another resource
Correct Answer: Copy and paste the task, then create a link to the copy
Explanation:
Copying creates a separate task node, after which a dependency can be drawn or assigned from the original task to the copied task.
Incorrect! Try again.
33Every task node currently shows task name, ID, start, and finish. The manager wants all standard nodes to show duration and total slack instead. What should be modified?
To change the content of the nodes
Medium
A.The node data template
B.The task outline structure
C.The project base calendar
D.The dependency relationship
Correct Answer: The node data template
Explanation:
A node's data template determines which task fields appear inside boxes and how those fields are arranged.
Incorrect! Try again.
34To make milestone nodes visually distinct, a manager wants them to have a blue dashed border without changing the data inside them. Which feature should be used?
To change border color and style
Medium
A.Resource Highlighting
B.Task Dependency editing
C.Box Styles formatting
D.Data Template editing
Correct Answer: Box Styles formatting
Explanation:
Box Styles controls visual properties such as border color, border pattern, shape, and background for selected categories of nodes.
Incorrect! Try again.
35A network diagram is cluttered because summary tasks display too much detail. Which change is most appropriate while preserving the underlying subtasks?
To change the way a summary task is displayed
Medium
A.Remove all links entering the summary task nodes
B.Replace the summary tasks with recurring tasks
C.Apply a simpler box style or template to summary tasks
D.Delete the summary tasks and retain only milestones
Correct Answer: Apply a simpler box style or template to summary tasks
Explanation:
Summary-task appearance can be simplified through its box style or data template without deleting or restructuring the tasks it summarizes.
Incorrect! Try again.
36A link line connects Design to Development, but its dependency type is not obvious from the diagram. What is the most direct way to inspect it?
To view the type of relationship
Medium
A.Open the resource assigned to Development
B.Change the node template used by Design
C.Open the link's Task Dependency information
D.Zoom the diagram to the selected node
Correct Answer: Open the link's Task Dependency information
Explanation:
Opening the dependency information for the link displays its relationship type, such as Finish-to-Start or Start-to-Start, along with any lag.
Incorrect! Try again.
37Two tasks currently use a Finish-to-Start dependency, but the second task should begin when the first task begins. Which relationship should replace the existing one?
To change the relationship type
Medium
A.Finish-to-Finish
B.Start-to-Finish
C.Start-to-Start
D.Finish-to-Start
Correct Answer: Start-to-Start
Explanation:
A Start-to-Start dependency links the start of the successor to the start of the predecessor, subject to any specified lag.
Incorrect! Try again.
38Task B should no longer depend on Task A, but both tasks must remain in the project. What should the project manager remove?
To remove a link line
Medium
A.The summary task containing A and B
B.The dependency link between A and B
C.The node representing Task B
D.The node representing Task A
Correct Answer: The dependency link between A and B
Explanation:
Deleting only the dependency link removes the scheduling relationship while preserving both task records.
Incorrect! Try again.
39Task Review must become the successor of Task Draft in Network Diagram view. How can the dependency be created graphically?
To manually add a link line
Medium
A.Apply the same box style to both tasks
B.Drag a link from Draft to Review
C.Place Draft and Review in the same row
D.Drag Review into the Draft node
Correct Answer: Drag a link from Draft to Review
Explanation:
Dragging from the predecessor node to the successor node creates a dependency link, normally using the default Finish-to-Start relationship.
Incorrect! Try again.
40After nodes have been moved manually and several links have been changed, the diagram is untidy. The manager wants to regenerate the arrangement using the current layout rules. What should be done?
Reform the layout
Medium
A.Replace all links with deadlines
B.Apply the layout command again
C.Create a new project calendar
D.Recalculate only resource assignments
Correct Answer: Apply the layout command again
Explanation:
Reapplying the layout command reforms the diagram according to the current spacing, positioning, and link-routing settings.
Incorrect! Try again.
41A project manager needs to determine whether two branches of work can proceed concurrently and where they converge before system testing. Why is the Network Diagram view more suitable than a simple task table for this analysis?
Understanding The Network Diagram View
Hard
A.It displays only milestones that belong to the critical path
B.It replaces dependency logic with chronological task sorting
C.It groups tasks exclusively by assigned resource and hourly cost
D.It represents tasks as nodes and dependencies as directional link lines
Correct Answer: It represents tasks as nodes and dependencies as directional link lines
Explanation:
The Network Diagram exposes the logical flow of the schedule. Parallel branches, dependency paths, and convergence points can be identified from the connected nodes.
Incorrect! Try again.
42In a Network Diagram, tasks B and C both follow task A. Task D cannot start until both B and C finish. Which structure correctly represents the required logic?
Examining A Network Diagram
Hard
A.A links to D, while D links backward to B and C
B.A links to B, B links to C, and C links to D
C.B and C link to A, while A links forward to D
D.A links to B and C, while B and C both link to D
Correct Answer: A links to B and C, while B and C both link to D
Explanation:
The diagram must split after A and merge before D. Separate links from B and C to D ensure that D waits for both predecessor branches.
Incorrect! Try again.
43A summary task appears above several subtasks in the Network Diagram. A user assumes that every subtask is automatically a predecessor of the summary task. Which interpretation is correct?
Understanding Summary Tasks In Network Design view
Hard
A.The summary node aggregates its subtasks but does not create dependency links automatically
B.The summary node creates finish-to-start links in displayed outline order
C.The summary node is automatically linked after every enclosed subtask
D.The summary node replaces all dependency links among its enclosed subtasks
Correct Answer: The summary node aggregates its subtasks but does not create dependency links automatically
Explanation:
Outline hierarchy and dependency logic are separate. A summary task rolls up subtask information, but explicit links determine scheduling relationships.
Incorrect! Try again.
44Task B currently has a finish-to-start dependency on task A. Task B must instead start two working days before task A finishes. Which modification best expresses this requirement?
Changing Task Linkage
Hard
A.Change to start-to-finish and apply a lag of two working days
B.Retain finish-to-start and apply a lead of two working days
C.Retain finish-to-start and apply a lag of two working days
D.Change to finish-to-finish and apply a lead of two working days
Correct Answer: Retain finish-to-start and apply a lead of two working days
Explanation:
A negative lag, commonly called lead, permits the successor to begin before the predecessor finishes. The underlying relationship can remain finish-to-start.
Incorrect! Try again.
45A user is working in Gantt Chart view and switches to Network Diagram view. Which schedule property should remain unchanged solely because of this view change?
To change to Network Diagram view
Hard
A.The box template selected for newly created project files
B.The current zoom percentage used by every project view
C.The stored task dependencies and calculated schedule dates
D.The visual positions of all task bars in the Gantt chart
Correct Answer: The stored task dependencies and calculated schedule dates
Explanation:
Changing views changes the presentation of project data, not the underlying dependency model or calculated schedule.
Incorrect! Try again.
46A large Network Diagram extends beyond the window in both directions. The manager needs an immediate overview of every node without changing task data. Which action is most appropriate?
To ZOOM and see the whole of the project
Hard
A.Apply the zoom option that fits the entire project in the available window
B.Collapse all dependency chains into a single summary task
C.Reduce every task duration until all nodes occupy one screen
D.Change every node to a milestone before reducing the zoom
Correct Answer: Apply the zoom option that fits the entire project in the available window
Explanation:
An entire-project zoom adjusts only the display scale so that all nodes fit in the viewport. It does not alter tasks, durations, or dependencies.
Incorrect! Try again.
47A manager must update a node's calendar, constraints, predecessors, and notes while preserving access to validation controls. Which method is most suitable?
To open a node for editing
Hard
A.Open the Layout dialog and modify the node's scheduling fields
B.Open the node's Task Information dialog and edit the relevant tabs
C.Change the node's box style and enter values in the preview
D.Select the incoming link line and edit all node properties there
Correct Answer: Open the node's Task Information dialog and edit the relevant tabs
Explanation:
The Task Information dialog exposes multiple categories of task data and is appropriate when several structured properties must be edited.
Incorrect! Try again.
48A node template displays Task Name, Duration, and Start, but not Constraint Type. The user wants to change only the task name directly in the diagram. What is the least disruptive action?
To edit a node directly in Network Diagram view
Hard
A.Delete the node and create a replacement with the new name
B.Redesign the template to include Constraint Type before editing
C.Select the displayed Task Name field in the node and edit its value
D.Convert the node into a milestone and rename the milestone
Correct Answer: Select the displayed Task Name field in the node and edit its value
Explanation:
A field already exposed by the node template can be edited directly. There is no need to alter the template or recreate the task.
Incorrect! Try again.
49After several dependencies are added, nodes overlap and link lines cross unnecessarily. The logical relationships are correct. What should the user do first?
To Layout the boxes
Hard
A.Delete and recreate the crossing dependencies in alphabetical order
B.Run the diagram's layout command to reposition boxes using current layout rules
C.Change all relationships to finish-to-start before moving any boxes
D.Sort task identifiers and permanently renumber every task in the project
Correct Answer: Run the diagram's layout command to reposition boxes using current layout rules
Explanation:
Reapplying the layout reorganizes the visual arrangement without changing dependency logic. Link deletion or relationship conversion would alter the schedule.
Incorrect! Try again.
50A manager manually positions key nodes for a presentation, but the positions are lost whenever the diagram is recalculated. Which layout configuration best preserves the arrangement?
To control the layout
Hard
A.Enable automatic layout after every task dependency change
B.Use automatic box positioning and increase horizontal spacing
C.Reset the diagram to the default layout before each recalculation
D.Use manual box positioning and disable automatic repositioning
Correct Answer: Use manual box positioning and disable automatic repositioning
Explanation:
Automatic layout can overwrite manually chosen coordinates. Manual positioning must remain active when exact presentation placement needs to be preserved.
Incorrect! Try again.
51Dragging a node to another location in a manually arranged Network Diagram should normally have which effect?
To move a node
Hard
A.It changes the task's start date according to the horizontal distance
B.It inserts the task between the nearest predecessor and successor
C.It changes the task's outline level according to the vertical distance
D.It changes the node's visual position without changing its dependency logic
Correct Answer: It changes the node's visual position without changing its dependency logic
Explanation:
Node coordinates are presentation data. Moving a box does not by itself modify dates, outline hierarchy, or predecessor relationships.
Incorrect! Try again.
52A user duplicates a task node to create a similar task and then links the original to the copy. Which result should be verified most carefully before accepting the schedule?
To copy a node and link to it
Hard
A.The copied task has the intended fields and a valid dependency direction
B.The link line has replaced both task records with one recurring task
C.The copied task has inherited the original task's unique identifier
D.The original and copied tasks occupy exactly the same screen coordinates
Correct Answer: The copied task has the intended fields and a valid dependency direction
Explanation:
A copied task is a separate record and may duplicate properties that require review. The new link must also point from the intended predecessor to the intended successor.
Incorrect! Try again.
53A risk review requires every node to show Task Name, Total Slack, and Finish, while the underlying task records must remain unchanged. Which customization should be made?
To change the content of the nodes
Hard
A.Rename the tasks so each name embeds slack and finish information
B.Change task notes so the notes replace all fields inside each node
C.Create dependency labels containing the three requested field values
D.Modify or select a node data template containing those three fields
Correct Answer: Modify or select a node data template containing those three fields
Explanation:
Node templates control which project fields appear inside boxes. Changing a template affects presentation without rewriting the task data.
Incorrect! Try again.
54The manager wants critical tasks to have a thick red border while preserving the fields displayed inside their nodes. Which approach isolates the required formatting change?
To change border color and style
Hard
A.Change the critical tasks to milestones and assign a red link-line style
B.Apply a red text highlight to every predecessor of a critical task
C.Edit the data template for all tasks and replace the Task Name field
D.Edit the box style for the critical-task category and retain its data template
Correct Answer: Edit the box style for the critical-task category and retain its data template
Explanation:
Box styles control visual properties such as border color and line style. Keeping the data template unchanged preserves the node's displayed fields.
Incorrect! Try again.
55Summary tasks must be visually distinct from ordinary tasks, but all summary nodes should continue showing the same fields they currently display. What should be changed?
To change the way a summary task is displayed
Hard
A.Add predecessor links from every subtask to its own summary task
B.Change the summary-task box style while retaining its assigned data template
C.Change every summary task into a milestone with zero duration
D.Remove the subtasks and represent each phase with one ordinary task
Correct Answer: Change the summary-task box style while retaining its assigned data template
Explanation:
The summary-task box style determines its visual treatment. Retaining the assigned template keeps the existing node contents intact.
Incorrect! Try again.
56Two connected nodes are close together, and the link-line geometry does not clearly reveal whether the relationship is finish-to-start or start-to-start. What is the most reliable inspection method?
To view the type of relationship
Hard
A.Compare the border styles assigned to the predecessor and successor
B.Open the link's dependency information and inspect its relationship type
C.Infer the relationship from the horizontal positions of the two nodes
D.Assume finish-to-start because every visible link uses that relationship
Correct Answer: Open the link's dependency information and inspect its relationship type
Explanation:
Node positions and line routing are not authoritative indicators of dependency type. The dependency information explicitly records the relationship and any lead or lag.
Incorrect! Try again.
57Testing may begin when development begins, but testing must remain two working days behind development. Which relationship should connect Development to Testing?
To change the relationship type
Hard
A.Start-to-finish with a lead of two working days
B.Finish-to-start with a lead of two working days
C.Start-to-start with a lag of two working days
D.Finish-to-finish with a lag of two working days
Correct Answer: Start-to-start with a lag of two working days
Explanation:
Both tasks are coordinated by their start events. A two-day positive lag delays Testing until two working days after Development starts.
Incorrect! Try again.
58A successor has two valid predecessors and one obsolete predecessor. The user wants to remove only the obsolete dependency without deleting either task. What should be selected and removed?
To remove a link line
Hard
A.The successor node and all of its displayed task information
B.The diagram row containing both the predecessor and successor
C.The predecessor node and every outgoing dependency attached to it
D.The obsolete link line or its corresponding predecessor entry
Correct Answer: The obsolete link line or its corresponding predecessor entry
Explanation:
A dependency is a separate relationship between two tasks. Removing that specific link preserves both tasks and the successor's other valid predecessors.
Incorrect! Try again.
59While drawing a dependency manually, a user drags from task X to task Y. Which interpretation must be confirmed before completing the operation?
To manually add a link line
Hard
A.X and Y are intended to receive the same unique task identifier
B.X is intended as the successor and Y as the summary task
C.X is intended as the predecessor and Y as the successor
D.X and Y are intended to exchange their scheduled durations
Correct Answer: X is intended as the predecessor and Y as the successor
Explanation:
The drag direction establishes the logical direction of the new dependency. Reversing it can significantly change scheduling calculations or create a circular relationship.
Incorrect! Try again.
60After extensive manual movement, the diagram has uneven spacing and long link routes. The manager wants to restore a consistent arrangement without altering task logic. Which operation is appropriate?
Reform the layout
Hard
A.Remove every dependency and rebuild links from left to right
B.Reapply the configured layout rules to the entire Network Diagram
C.Convert all manually scheduled tasks into summary tasks
D.Recalculate all durations from the current horizontal node positions
Correct Answer: Reapply the configured layout rules to the entire Network Diagram
Explanation:
Reforming the layout recalculates node placement and link routing according to the selected layout settings. It does not modify tasks or dependencies.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →