Unit 3 MCQs Project Planning and Scheduling

CSEB422 — Project Management 60 questions. Pick an option to check it.

Read the notes Subjective questions

0 of 60 answered 0 right 0 wrong , 60 left

  1. Question 1 of 60 Project planning Lifecycle Easy

    Which of the following is the primary purpose of the project planning phase?

  2. Question 2 of 60 Project Schedule Management Easy

    What is the main goal of Project Schedule Management?

  3. Question 3 of 60 Activities and sequencing Easy

    What does "sequencing activities" in project management involve?

  4. Question 4 of 60 Project Duration Estimation Easy

    What is the main output of the 'Estimate Activity Durations' process?

  5. Question 5 of 60 Scheduling Constraints Easy

    Which of the following is a common example of a scheduling constraint?

  6. Question 6 of 60 Network Diagram Easy

    What does a project network diagram visually represent?

  7. Question 7 of 60 Leads and Lags Time Easy

    In project scheduling, what is a "lag"?

  8. Question 8 of 60 Analogous and Parametric Estimating Easy

    Analogous estimating is also known as:

  9. Question 9 of 60 Three-Point & PERT Estimating Easy

    In the Three-Point estimating technique, what three estimates are used to calculate the expected duration?

  10. Question 10 of 60 BottomUp Estimating Easy

    What is the main characteristic of bottom-up estimating?

  11. Question 11 of 60 Schedule Baseline and Gantt Chart Easy

    What is a Gantt chart most commonly used for in project management?

  12. Question 12 of 60 Compressing and Schedule Controlling Easy

    The schedule compression technique known as "crashing" involves:

  13. Question 13 of 60 Project Management Cost and Estimation Easy

    What is the primary goal of Project Cost Management?

  14. Question 14 of 60 Estimating Tools Easy

    Which of the following is a basic tool used for both cost and time estimation?

  15. Question 15 of 60 Project Budget Easy

    What is a project budget?

  16. Question 16 of 60 Managing Project Procurement Easy

    What is the main purpose of project procurement management?

  17. Question 17 of 60 Procurement Process Easy

    In the procurement process, what is a Request for Proposal (RFP)?

  18. Question 18 of 60 Earned Value Management Easy

    What does the Earned Value (EV) metric represent in a project?

  19. Question 19 of 60 Supplier Management Easy

    A key activity in supplier management is:

  20. Question 20 of 60 Leads and Lags Time Easy

    What is a "lead" in project scheduling?

  21. Question 21 of 60 Three-Point & PERT Estimating Medium

    A project manager is estimating the duration for a complex task. The team provides three estimates: Optimistic (O) = 10 days, Pessimistic (P) = 28 days, and Most Likely (M) = 15 days. Using the PERT formula, what is the expected duration () of this task?

  22. Question 22 of 60 Earned Value Management Medium

    A project has a Planned Value (PV) of $50,000, an Earned Value (EV) of $45,000, and an Actual Cost (AC) of $60,000. Based on this data, what is the status of the project?

  23. Question 23 of 60 Leads and Lags Time Medium

    In a project schedule, the 'Testing' activity can begin 5 days before the 'Development' activity is fully completed. This is an example of a:

  24. Question 24 of 60 Compressing and Schedule Controlling Medium

    A project is behind schedule. The project manager decides to add more resources to critical path activities to shorten the project duration, which will also increase the project cost. This schedule compression technique is known as:

  25. Question 25 of 60 Analogous and Parametric Estimating Medium

    A construction company is estimating the cost to build a 200-unit apartment complex. They know from a previous project that each unit costs, on average, $150,000 to build. They estimate the new project cost by multiplying the number of units by this historical cost per unit. What estimation technique are they using?

  26. Question 26 of 60 Network Diagram Medium

    In a project network diagram, the critical path is defined as:

  27. Question 27 of 60 BottomUp Estimating Medium

    A project manager needs to create a highly accurate cost and duration estimate for developing a new software module. The manager asks the development team to estimate each individual feature, task, and sub-task, which are then aggregated to get a total estimate. This approach is best described as:

  28. Question 28 of 60 Schedule Baseline and Gantt Chart Medium

    Once the project schedule is finalized and approved by key stakeholders, the project manager saves it as the 'Schedule Baseline'. What is the primary purpose of this baseline?

  29. Question 29 of 60 Scheduling Constraints Medium

    A project team must wait for a government permit to be approved before they can begin construction. The permit approval is expected on June 1st. This is an example of what type of dependency and constraint?

  30. Question 30 of 60 Procurement Process Medium

    During which phase of the procurement process would a project manager issue a Request for Proposal (RFP) and hold bidder conferences?

  31. Question 31 of 60 Earned Value Management Medium

    A project has a Budget at Completion (BAC) of $200,000. Currently, the Earned Value (EV) is $80,000 and the Actual Cost (AC) is $100,000. Assuming the current cost performance trend continues, what is the Estimate at Completion (EAC)?

  32. Question 32 of 60 Project Budget Medium

    A project's cost estimate is $500,000. The project manager adds a contingency reserve of $50,000 for identified risks. This sum ($550,000) is known as the:

  33. Question 33 of 60 Supplier Management Medium

    After awarding a contract to a key supplier, what is the project manager's most critical activity regarding supplier management during the project execution phase?

  34. Question 34 of 60 Three-Point & PERT Estimating Medium

    A team is using a triangular distribution for a three-point estimate. Their estimates are: Optimistic (O) = 20 hours, Pessimistic (P) = 35 hours, and Most Likely (M) = 24 hours. What is the expected duration using this method?

  35. Question 35 of 60 Activities and sequencing Medium

    An activity in a project plan, "Write User Manual," can only begin after the activity "Finalize Software Code" is completed. This type of logical relationship is known as:

  36. Question 36 of 60 Compressing and Schedule Controlling Medium

    A project manager is facing pressure to deliver a project earlier than planned but has no additional budget for resources. The manager decides to re-sequence certain critical path activities to be worked on simultaneously instead of sequentially. This approach, which increases risk, is called:

  37. Question 37 of 60 Analogous and Parametric Estimating Medium

    A project manager needs a quick, rough order of magnitude (ROM) estimate for a new website development project during the initiation phase. The manager looks at a similar website project completed last year that cost $100,000 and uses this figure as the estimate for the new project. This technique is called:

  38. Question 38 of 60 Project planning Lifecycle Medium

    A project manager has just completed the Work Breakdown Structure (WBS), defined all activities, and created the network diagram. What is the most logical next step in the project planning lifecycle for schedule development?

  39. Question 39 of 60 Project Management Cost and Estimation Medium

    In cost estimation, what is the key difference between contingency reserves and management reserves?

  40. Question 40 of 60 Schedule Baseline and Gantt Chart Medium

    While reviewing a Gantt chart, a project manager sees a diamond symbol with a specific date but zero duration. What does this symbol most likely represent?

  41. Question 41 of 60 Three-Point & PERT Estimating Hard

    A critical path activity has an optimistic (O) estimate of 15 days, a pessimistic (P) estimate of 39 days, and a most likely (M) estimate of 24 days. Using PERT analysis, what is the approximate probability of completing this activity between 22 and 30 days, assuming a beta distribution?

  42. Question 42 of 60 Earned Value Management Hard

    A project has a Budget at Completion (BAC) of $500,000. At a status check, the Actual Cost (AC) is $280,000 and the Planned Value (PV) is $300,000. The team has earned $250,000 in value (EV). Due to unforeseen complexity, the project manager has re-estimated that the remaining work (ETC) will cost $350,000. What is the To-Complete Performance Index (TCPI) required to finish the project based on the new Estimate At Completion (EAC)?

  43. Question 43 of 60 Compressing and Schedule Controlling Hard

    A project's critical path is 60 days long. A parallel near-critical path is 58 days long. The schedule must be compressed by 5 days. Activities on the critical path that can be crashed are: Task X (3,000/day, max 4 days). The near-critical path can be crashed at a uniform cost of $3,500/day. What is the minimum additional cost to meet the 5-day compression target?

  44. Question 44 of 60 Procurement Process Hard

    During a bidder conference for a complex Fixed-Price Incentive Fee (FPIF) contract, a supplier identifies a significant ambiguity in the Statement of Work (SOW). This ambiguity could lead to a 40% variance in effort. To ensure fair competition and mitigate future claims, what is the most appropriate immediate action for the project manager?

  45. Question 45 of 60 BottomUp Estimating Hard

    A project manager is asked to provide a definitive, fixed-price bid for a large-scale R&D project with many technological uncertainties. The client insists on an estimate with ±5% accuracy. The project manager knows that Bottom-Up estimating is the most accurate method. Why is applying Bottom-Up estimating in this context problematic?

  46. Question 46 of 60 Leads and Lags Time Hard

    A schedule network diagram includes the path A-B-C. Activity B has a Finish-to-Start (FS) relationship with A, with a 10-day lag. Activity C has an FS relationship with B. The project manager decides to change the A-B relationship to Start-to-Start (SS) with a 12-day lead time to accelerate the project. What is the most significant potential negative risk introduced by this change, assuming activity durations remain constant?

  47. Question 47 of 60 Earned Value Management Hard

    A project has a CPI of 0.80 and an SPI of 1.20. The project manager is confident that the cost overruns are due to one-time startup costs that will not recur, but the schedule acceleration is due to a genuine process innovation that is sustainable. Based on this analysis, which formula should be used to calculate the Estimate at Completion (EAC)?

  48. Question 48 of 60 Project Budget Hard

    A project's cost baseline is $1.2M, which includes $100k in contingency reserves. The total project budget is $1.35M. A risk from the risk register occurs, and the mitigation response costs $40k. Shortly after, a major, unforeseen market shift forces a significant change to the project's deliverables to maintain business value. This change is estimated to cost $150k. What is the status of the project budget after these two events are accounted for?

  49. Question 49 of 60 Scheduling Constraints Hard

    A project to develop a new medical device has a fixed, immovable launch date imposed by the marketing department ('Finish No Later Than' constraint). During planning, the critical path analysis shows a calculated completion date that is two weeks after this deadline. Resource leveling, applied to resolve over-allocations of key engineers, extends the critical path by another week. Which of the following represents the most comprehensive and logical next step for the project manager?

  50. Question 50 of 60 Supplier Management Hard

    A key supplier on a project is delivering components that are consistently at the lower bound of the acceptable quality tolerance specified in the contract. While not technically a breach of contract, this is causing downstream integration issues, increasing rework and threatening the schedule. The contract is a Firm-Fixed-Price (FFP) type. What is the project manager's most effective course of action?

  51. Question 51 of 60 Analogous and Parametric Estimating Hard

    A company is planning to build its 20th data center. For the previous 19, they have detailed historical data on cost per square foot, cost per server rack, and energy consumption ratios. The new data center will be 30% larger and use a new, more efficient cooling technology not present in previous projects. Which combination of estimating techniques is most appropriate?

  52. Question 52 of 60 Schedule Baseline and Gantt Chart Hard

    A project is 40% complete when a major change is approved, adding significant new scope. The change increases the total project duration by 25% and the budget by 20%. The steering committee has approved the change. How should the project manager handle the schedule baseline?

  53. Question 53 of 60 Network Diagram Hard

    In a Precedence Diagramming Method (PDM) network, Activity D can start only after a 5-day delay following the completion of both Activity B and Activity C. Activity B has a duration of 10 days and Activity C has a duration of 15 days. Both B and C start after Activity A finishes. How is this complex relationship best modeled in the network diagram?

  54. Question 54 of 60 Activities and sequencing Hard

    A project manager is deciding on the sequencing logic for two activities: 'Develop API' and 'Develop User Interface'. The user interface requires the API to be functional for end-to-end testing, but the basic UI layout can be designed and built using mock API data. The team is under pressure to show visible progress early. What is the best dependency type to model this relationship to optimize the schedule?

  55. Question 55 of 60 Managing Project Procurement Hard

    A project requires a specialized component. The team can develop it in-house for an estimated $150,000, with a 20% probability of a major setback that would add $100,000 to the cost. A reliable external vendor has offered to supply the component for a firm-fixed-price of $180,000. However, buying from the vendor means the company will not develop the valuable in-house expertise. Which concept best describes the trade-off the project manager must primarily consider?

  56. Question 56 of 60 Project planning Lifecycle Hard

    In an iterative project lifecycle (e.g., spiral or agile), detailed component-level planning for later phases is intentionally deferred. What is the primary reason for this 'rolling wave planning' approach, and what is its main integration challenge?

  57. Question 57 of 60 Project Schedule Management Hard

    The Project Schedule Management plan is a subsidiary of the main Project Management Plan. Which of the following statements describes the most critical and often overlooked integration point between the Project Schedule Management plan and the Project Communications Management plan?

  58. Question 58 of 60 Project Management Cost and Estimation Hard

    A project manager is preparing a budget for a project and is currently in the initiation phase. According to best practices, what type of cost estimate should be created at this stage, and what would its expected accuracy range be?

  59. Question 59 of 60 Estimating Tools Hard

    A project involves constructing a large, complex chemical processing plant. The project has thousands of activities, complex resource dependencies, and requires sophisticated risk modeling using Monte Carlo simulation. The company is choosing between a standard desktop project scheduling tool and a high-end Enterprise Project Portfolio Management (EPPM) system. What is the most compelling justification for the significant extra cost of the EPPM system in this context?

  60. Question 60 of 60 Project Duration Estimation Hard

    A project manager is reviewing activity duration estimates from the team. A senior engineer has estimated a testing activity will take 10 days. The project manager knows that Parkinson's Law suggests work expands to fill the time available. Conversely, the manager is also concerned about Student Syndrome, where people start work at the last possible moment. How do these two theories collectively impact project duration estimation and scheduling?

That's unit 3