Unit 3 - Practice Quiz

CSEB422 60 Questions
0 Correct 0 Wrong 60 Left
0/60

1 Which of the following is the primary purpose of the project planning phase?

Project planning Lifecycle Easy
A. To define the project scope, objectives, and how the work will be done
B. To execute the project work
C. To formally close the project
D. To select a project manager

2 What is the main goal of Project Schedule Management?

Project Schedule Management Easy
A. To calculate the project's final profit
B. To ensure the project is completed on time
C. To manage project stakeholders
D. To hire the project team

3 What does "sequencing activities" in project management involve?

Activities and sequencing Easy
A. Completing the project work
B. Identifying and documenting relationships among project activities
C. Assigning costs to each activity
D. Finalizing the project budget

4 What is the main output of the 'Estimate Activity Durations' process?

Project Duration Estimation Easy
A. An estimate of the work periods needed to complete individual activities
B. The project charter
C. The project budget
D. A list of project stakeholders

5 Which of the following is a common example of a scheduling constraint?

Scheduling Constraints Easy
A. The color of the final product
B. A fixed deadline or end date
C. The number of project meetings
D. The project manager's salary

6 What does a project network diagram visually represent?

Network Diagram Easy
A. The communication plan
B. The project team's organizational structure
C. The project's budget allocation
D. The logical sequence and dependencies of project activities

7 In project scheduling, what is a "lag"?

Leads and Lags Time Easy
A. An acceleration of a successor activity
B. The total duration of the project
C. A required delay between two activities
D. A task that is ahead of schedule

8 Analogous estimating is also known as:

Analogous and Parametric Estimating Easy
A. Top-down estimating
B. Three-point estimating
C. Bottom-up estimating
D. PERT estimating

9 In the Three-Point estimating technique, what three estimates are used to calculate the expected duration?

Three-Point & PERT Estimating Easy
A. Best Case, Worst Case, and Normal
B. Minimum, Maximum, and Average
C. Start, Finish, and Midpoint
D. Optimistic, Pessimistic, and Most Likely

10 What is the main characteristic of bottom-up estimating?

BottomUp Estimating Easy
A. It breaks down work into smaller components and estimates each one individually
B. It is the fastest estimation method
C. It estimates the project as a single unit
D. It relies on the project manager's guess

11 What is a Gantt chart most commonly used for in project management?

Schedule Baseline and Gantt Chart Easy
A. Visualizing the project schedule and task timelines
B. Managing contracts with suppliers
C. Calculating project costs
D. Documenting project risks

12 The schedule compression technique known as "crashing" involves:

Compressing and Schedule Controlling Easy
A. Extending the project deadline
B. Adding more resources to activities to shorten their duration
C. Performing activities in parallel
D. Reducing the project scope

13 What is the primary goal of Project Cost Management?

Project Management Cost and Estimation Easy
A. To finish the project as quickly as possible, regardless of cost
B. To hire the most expensive experts
C. To create the most complex product possible
D. To ensure the project is completed within the approved budget

14 Which of the following is a basic tool used for both cost and time estimation?

Estimating Tools Easy
A. A communication plan
B. A stakeholder register
C. Expert judgment
D. A project charter

15 What is a project budget?

Project Budget Easy
A. The total revenue the project is expected to generate
B. A list of all project team members and their salaries
C. The daily report of project progress
D. The approved estimate for the project used as a baseline for cost control

16 What is the main purpose of project procurement management?

Managing Project Procurement Easy
A. To acquire products or services from outside the project team
B. To market the project's final product
C. To hire internal project team members
D. To manage internal team communications

17 In the procurement process, what is a Request for Proposal (RFP)?

Procurement Process Easy
A. The project's final acceptance document
B. An internal team progress report
C. A document used to solicit proposals from prospective sellers
D. A final invoice sent by a supplier

18 What does the Earned Value (EV) metric represent in a project?

Earned Value Management Easy
A. The actual cost incurred for the work performed
B. The total budget of the project
C. The value of the work actually completed to date
D. The planned cost of the project

19 A key activity in supplier management is:

Supplier Management Easy
A. Training the internal project team
B. Monitoring supplier performance and managing relationships
C. Developing the project schedule
D. Defining the project scope

20 What is a "lead" in project scheduling?

Leads and Lags Time Easy
A. The project manager of a team
B. A required delay between two activities
C. A task that is behind schedule
D. An acceleration of a successor activity

21 A project manager is estimating the duration for a complex task. The team provides three estimates: Optimistic (O) = 10 days, Pessimistic (P) = 28 days, and Most Likely (M) = 15 days. Using the PERT formula, what is the expected duration () of this task?

Three-Point & PERT Estimating Medium
A. 15.0 days
B. 19.0 days
C. 16.3 days
D. 17.7 days

22 A project has a Planned Value (PV) of 45,000, and an Actual Cost (AC) of $60,000. Based on this data, what is the status of the project?

Earned Value Management Medium
A. Ahead of schedule and over budget
B. Behind schedule and over budget
C. Behind schedule and under budget
D. Ahead of schedule and under budget

23 In a project schedule, the 'Testing' activity can begin 5 days before the 'Development' activity is fully completed. This is an example of a:

Leads and Lags Time Medium
A. Lead with a Start-to-Start (SS) relationship
B. Lag with a Finish-to-Start (FS) relationship
C. Lag with a Start-to-Finish (SF) relationship
D. Lead with a Finish-to-Start (FS) relationship

24 A project is behind schedule. The project manager decides to add more resources to critical path activities to shorten the project duration, which will also increase the project cost. This schedule compression technique is known as:

Compressing and Schedule Controlling Medium
A. Crashing
B. Monte Carlo Analysis
C. Resource Leveling
D. Fast Tracking

25 A construction company is estimating the cost to build a 200-unit apartment complex. They know from a previous project that each unit costs, on average, $150,000 to build. They estimate the new project cost by multiplying the number of units by this historical cost per unit. What estimation technique are they using?

Analogous and Parametric Estimating Medium
A. Parametric Estimating
B. Bottom-up Estimating
C. Analogous Estimating
D. Three-Point Estimating

26 In a project network diagram, the critical path is defined as:

Network Diagram Medium
A. The path with the most activities.
B. The shortest path through the network, representing the minimum project duration.
C. The path with the highest number of risks.
D. The path with zero total float.

27 A project manager needs to create a highly accurate cost and duration estimate for developing a new software module. The manager asks the development team to estimate each individual feature, task, and sub-task, which are then aggregated to get a total estimate. This approach is best described as:

BottomUp Estimating Medium
A. Top-Down Estimating
B. Analogous Estimating
C. Parametric Estimating
D. Bottom-Up Estimating

28 Once the project schedule is finalized and approved by key stakeholders, the project manager saves it as the 'Schedule Baseline'. What is the primary purpose of this baseline?

Schedule Baseline and Gantt Chart Medium
A. To provide a fixed reference point against which the project's actual schedule performance is measured and controlled.
B. To serve as the final, unchangeable plan for the project.
C. To list all the possible risks that could affect the project timeline.
D. To be shared with the team as a rough guideline that can be changed daily.

29 A project team must wait for a government permit to be approved before they can begin construction. The permit approval is expected on June 1st. This is an example of what type of dependency and constraint?

Scheduling Constraints Medium
A. A mandatory dependency with no specific date constraint.
B. An internal dependency creating a "Finish No Later Than" constraint.
C. A discretionary dependency with a mandatory finish date.
D. An external dependency creating a "Start No Earlier Than" constraint.

30 During which phase of the procurement process would a project manager issue a Request for Proposal (RFP) and hold bidder conferences?

Procurement Process Medium
A. Plan Procurement Management
B. Control Procurements
C. Conduct Procurements
D. Close Procurements

31 A project has a Budget at Completion (BAC) of 80,000 and the Actual Cost (AC) is $100,000. Assuming the current cost performance trend continues, what is the Estimate at Completion (EAC)?

Earned Value Management Medium
A. $220,000
B. $250,000
C. $200,000
D. $180,000

32 A project's cost estimate is 50,000 for identified risks. This sum ($550,000) is known as the:

Project Budget Medium
A. Project Budget
B. Activity Cost Estimate
C. Cost Baseline
D. Management Reserve

33 After awarding a contract to a key supplier, what is the project manager's most critical activity regarding supplier management during the project execution phase?

Supplier Management Medium
A. Closing out the procurement contract after all work is done.
B. Monitoring the supplier's performance against the contract and managing the relationship.
C. Negotiating the initial contract price.
D. Selecting the supplier from a list of bidders.

34 A team is using a triangular distribution for a three-point estimate. Their estimates are: Optimistic (O) = 20 hours, Pessimistic (P) = 35 hours, and Most Likely (M) = 24 hours. What is the expected duration using this method?

Three-Point & PERT Estimating Medium
A. 26.3 hours
B. 24.0 hours
C. 25.8 hours
D. 27.5 hours

35 An activity in a project plan, "Write User Manual," can only begin after the activity "Finalize Software Code" is completed. This type of logical relationship is known as:

Activities and sequencing Medium
A. Start-to-Finish (SF)
B. Finish-to-Finish (FF)
C. Finish-to-Start (FS)
D. Start-to-Start (SS)

36 A project manager is facing pressure to deliver a project earlier than planned but has no additional budget for resources. The manager decides to re-sequence certain critical path activities to be worked on simultaneously instead of sequentially. This approach, which increases risk, is called:

Compressing and Schedule Controlling Medium
A. Crashing
B. Resource Smoothing
C. Critical Chain Method
D. Fast Tracking

37 A project manager needs a quick, rough order of magnitude (ROM) estimate for a new website development project during the initiation phase. The manager looks at a similar website project completed last year that cost $100,000 and uses this figure as the estimate for the new project. This technique is called:

Analogous and Parametric Estimating Medium
A. Parametric Estimating
B. Analogous Estimating
C. Bottom-up Estimating
D. Expert Judgment

38 A project manager has just completed the Work Breakdown Structure (WBS), defined all activities, and created the network diagram. What is the most logical next step in the project planning lifecycle for schedule development?

Project planning Lifecycle Medium
A. Developing the project charter.
B. Estimating the resources and duration for each activity.
C. Executing the project plan.
D. Creating the project budget.

39 In cost estimation, what is the key difference between contingency reserves and management reserves?

Project Management Cost and Estimation Medium
A. Management reserves are part of the cost baseline, while contingency reserves are not.
B. Contingency reserves are controlled by senior management, while management reserves are controlled by the project manager.
C. Contingency reserves are for identified risks ("known unknowns"), while management reserves are for unidentified risks ("unknown unknowns").
D. There is no functional difference; the terms are interchangeable.

40 While reviewing a Gantt chart, a project manager sees a diamond symbol with a specific date but zero duration. What does this symbol most likely represent?

Schedule Baseline and Gantt Chart Medium
A. A critical path activity
B. A project milestone
C. A resource conflict
D. A summary task

41 A critical path activity has an optimistic (O) estimate of 15 days, a pessimistic (P) estimate of 39 days, and a most likely (M) estimate of 24 days. Using PERT analysis, what is the approximate probability of completing this activity between 22 and 30 days, assuming a beta distribution?

Three-Point & PERT Estimating Hard
A. ~89%
B. ~53%
C. ~67%
D. ~34%

42 A project has a Budget at Completion (BAC) of 280,000 and the Planned Value (PV) is 250,000 in value (EV). Due to unforeseen complexity, the project manager has re-estimated that the remaining work (ETC) will cost $350,000. What is the To-Complete Performance Index (TCPI) required to finish the project based on the new Estimate At Completion (EAC)?

Earned Value Management Hard
A. 1.11
B. 1.40
C. 0.71
D. 0.89

43 A project's critical path is 60 days long. A parallel near-critical path is 58 days long. The schedule must be compressed by 5 days. Activities on the critical path that can be crashed are: Task X (3,000/day, max 4 days). The near-critical path can be crashed at a uniform cost of $3,500/day. What is the minimum additional cost to meet the 5-day compression target?

Compressing and Schedule Controlling Hard
A. $10,000
B. $27,500
C. $19,500
D. $22,500

44 During a bidder conference for a complex Fixed-Price Incentive Fee (FPIF) contract, a supplier identifies a significant ambiguity in the Statement of Work (SOW). This ambiguity could lead to a 40% variance in effort. To ensure fair competition and mitigate future claims, what is the most appropriate immediate action for the project manager?

Procurement Process Hard
A. Note the issue and plan to use the incentive fee structure to motivate the selected supplier to adopt the higher-effort interpretation during execution.
B. Halt the process, issue a formal amendment clarifying the SOW to all potential bidders, and extend the proposal deadline.
C. Verbally clarify the requirement to the attendees and distribute minutes, asking bidders to use the clarified basis for their proposals.
D. Ask bidders to include a risk premium and a detailed assumption list in their proposals regarding the ambiguous requirement.

45 A project manager is asked to provide a definitive, fixed-price bid for a large-scale R&D project with many technological uncertainties. The client insists on an estimate with ±5% accuracy. The project manager knows that Bottom-Up estimating is the most accurate method. Why is applying Bottom-Up estimating in this context problematic?

BottomUp Estimating Hard
A. Bottom-Up estimating aggregates risks at the work package level but fails to account for systemic or project-level risks common in R&D.
B. The work cannot be decomposed into small, well-defined work packages due to the high uncertainty, making the basis for a Bottom-Up estimate invalid.
C. Bottom-Up estimating does not align with the iterative, phase-gated funding model typically required for high-uncertainty R&D projects.
D. The time and cost to perform a detailed Bottom-Up estimate on an uncertain project may be prohibitively expensive and offer a false sense of precision.

46 A schedule network diagram includes the path A-B-C. Activity B has a Finish-to-Start (FS) relationship with A, with a 10-day lag. Activity C has an FS relationship with B. The project manager decides to change the A-B relationship to Start-to-Start (SS) with a 12-day lead time to accelerate the project. What is the most significant potential negative risk introduced by this change, assuming activity durations remain constant?

Leads and Lags Time Hard
A. It violates the precedence logic because a successor activity (B) cannot logically start before its predecessor (A) is planned to start.
B. The lead time will consume the project's contingency reserves at a faster rate.
C. It will automatically decrease the total float of the entire path, making it more likely to become critical.
D. It creates a high-risk concurrent dependency where a delay in the early part of Activity A will now have an immediate, unbuffered impact on the start of Activity B.

47 A project has a CPI of 0.80 and an SPI of 1.20. The project manager is confident that the cost overruns are due to one-time startup costs that will not recur, but the schedule acceleration is due to a genuine process innovation that is sustainable. Based on this analysis, which formula should be used to calculate the Estimate at Completion (EAC)?

Earned Value Management Hard
A. EAC = AC + (BAC - EV) / SPI
B. EAC = AC + (BAC - EV)
C. EAC = BAC / CPI
D. EAC = AC + (BAC - EV) / (CPI * SPI)

48 A project's cost baseline is 100k in contingency reserves. The total project budget is 40k. Shortly after, a major, unforeseen market shift forces a significant change to the project's deliverables to maintain business value. This change is estimated to cost $150k. What is the status of the project budget after these two events are accounted for?

Project Budget Hard
A. The cost baseline is 0, and the project is $40k over budget, requiring new funding.
B. The cost baseline is 60k, and the project manager must request the full $150k from the sponsor.
C. The contingency reserve becomes 150k is consumed, and the cost baseline is formally changed to $1.35M to reflect the approved change.
D. The cost baseline is updated to $1.31M, the management reserve is used for the market shift, and the contingency reserve is used for the identified risk.

49 A project to develop a new medical device has a fixed, immovable launch date imposed by the marketing department ('Finish No Later Than' constraint). During planning, the critical path analysis shows a calculated completion date that is two weeks after this deadline. Resource leveling, applied to resolve over-allocations of key engineers, extends the critical path by another week. Which of the following represents the most comprehensive and logical next step for the project manager?

Scheduling Constraints Hard
A. Perform a reverse phase schedule from the deadline to identify where scope must be reduced or quality standards lowered to create a feasible plan.
B. Reject the 'Finish No Later Than' constraint as unrealistic and submit a change request to move the launch date by three weeks based on the resource-leveled schedule.
C. Negotiate with functional managers to accept the resource over-allocations and authorize overtime to meet the original critical path duration.
D. Immediately begin crashing and fast-tracking the new critical path, while formally documenting the increased risks and costs, and requesting additional budget.

50 A key supplier on a project is delivering components that are consistently at the lower bound of the acceptable quality tolerance specified in the contract. While not technically a breach of contract, this is causing downstream integration issues, increasing rework and threatening the schedule. The contract is a Firm-Fixed-Price (FFP) type. What is the project manager's most effective course of action?

Supplier Management Hard
A. Accept the components as they are contractually compliant and use the project's contingency budget to fund the increased rework costs.
B. Leverage the relationship aspect of supplier management by meeting with the supplier's management to discuss the downstream impact and collaboratively find a solution to improve quality, potentially through a no-cost contract modification.
C. Begin documenting the supplier's performance to build a case for termination for cause, even if no explicit breach has occurred.
D. Initiate a formal contract dispute resolution process, claiming constructive change because the downstream impacts effectively change the project's requirements.

51 A company is planning to build its 20th data center. For the previous 19, they have detailed historical data on cost per square foot, cost per server rack, and energy consumption ratios. The new data center will be 30% larger and use a new, more efficient cooling technology not present in previous projects. Which combination of estimating techniques is most appropriate?

Analogous and Parametric Estimating Hard
A. Use primarily Parametric estimating for the entire project, adjusting the model's parameters upward by 30% to account for the size and adding a risk factor for the new technology.
B. Use Bottom-Up estimating for the entire project because the introduction of new technology makes all historical data unreliable.
C. Use Analogous estimating for the entire project by finding a similar project from another company that used the new cooling technology.
D. Use Parametric estimating for the building shell and rack installation, and Analogous estimating for the new cooling system, supplemented by expert judgment.

52 A project is 40% complete when a major change is approved, adding significant new scope. The change increases the total project duration by 25% and the budget by 20%. The steering committee has approved the change. How should the project manager handle the schedule baseline?

Schedule Baseline and Gantt Chart Hard
A. Create a new, secondary baseline for the added scope only, and track performance against both the original and the new baseline separately.
B. Re-baseline the project. The original baseline is no longer a valid measure of performance, and the new baseline will incorporate the approved change for all future performance reporting (e.g., SPI, SV).
C. Update the current schedule with the new activities but do not re-baseline. Instead, manage the 'schedule variance to date' as an accepted deviation.
D. Maintain the original baseline and continue to report a large negative schedule variance (SV) to show the impact of the change throughout the project's lifecycle.

53 In a Precedence Diagramming Method (PDM) network, Activity D can start only after a 5-day delay following the completion of both Activity B and Activity C. Activity B has a duration of 10 days and Activity C has a duration of 15 days. Both B and C start after Activity A finishes. How is this complex relationship best modeled in the network diagram?

Network Diagram Hard
A. Create a zero-duration milestone 'M' with FS dependencies from both B and C. Then create an FS relationship from M to D with a 5-day lag.
B. A Start-to-Start (SS) link from C to D with a 20-day lag (15 days duration + 5 days delay).
C. Two Finish-to-Start (FS) relationships (B->D and C->D), with a 5-day lag applied to the link originating from the activity that finishes later (Activity C).
D. One Finish-to-Finish (FF) relationship and one Start-to-Start (SS) relationship to ensure both predecessors are complete before the successor begins.

54 A project manager is deciding on the sequencing logic for two activities: 'Develop API' and 'Develop User Interface'. The user interface requires the API to be functional for end-to-end testing, but the basic UI layout can be designed and built using mock API data. The team is under pressure to show visible progress early. What is the best dependency type to model this relationship to optimize the schedule?

Activities and sequencing Hard
A. A Start-to-Start (SS) dependency with a lag time, allowing the UI development to begin shortly after the API development starts, and a Finish-to-Finish (FF) dependency to ensure the UI work doesn't complete before the API work.
B. Decompose 'Develop API' into 'Design API' and 'Build API', then link 'Develop User Interface' to 'Design API' with a Finish-to-Start (FS) dependency.
C. A discretionary Finish-to-Start (FS) dependency with a lead time, allowing UI development to start just before the API is officially completed.
D. A hard Finish-to-Start (FS) mandatory dependency, as no UI work should ever begin before the API is 100% complete and verified.

55 A project requires a specialized component. The team can develop it in-house for an estimated 100,000 to the cost. A reliable external vendor has offered to supply the component for a firm-fixed-price of $180,000. However, buying from the vendor means the company will not develop the valuable in-house expertise. Which concept best describes the trade-off the project manager must primarily consider?

Managing Project Procurement Hard
A. Procurement audit requirements versus internal resource allocation constraints.
B. Sunk Cost Fallacy versus the benefits of a Cost Plus Incentive Fee (CPIF) contract.
C. The calculation of Life Cycle Costing for the in-house option versus the vendor option.
D. Expected Monetary Value (EMV) of the make-or-buy decision versus the opportunity cost of not developing strategic capabilities.

56 In an iterative project lifecycle (e.g., spiral or agile), detailed component-level planning for later phases is intentionally deferred. What is the primary reason for this 'rolling wave planning' approach, and what is its main integration challenge?

Project planning Lifecycle Hard
A. Reason: To minimize the upfront cost of the planning phase. Challenge: Integrating the work of multiple teams who may be working on different iterations simultaneously.
B. Reason: To satisfy stakeholders who demand to see early and frequent deliverables. Challenge: Accurately forecasting the final project budget and completion date.
C. Reason: To adhere to the principles of just-in-time (JIT) manufacturing applied to project management. Challenge: Managing the procurement of long-lead items.
D. Reason: To accommodate change and reduce wasted effort on planning for uncertain future work. Challenge: Ensuring that the overall project architecture and high-level requirements are robust enough to support future iterations without requiring significant rework.

57 The Project Schedule Management plan is a subsidiary of the main Project Management Plan. Which of the following statements describes the most critical and often overlooked integration point between the Project Schedule Management plan and the Project Communications Management plan?

Project Schedule Management Hard
A. The communications plan must include a glossary of scheduling terms like 'float', 'critical path', and 'lag' for the stakeholders.
B. The schedule management plan must define the thresholds for schedule variance that will trigger formal communications to specific stakeholders, and the format and frequency of these exception reports.
C. The schedule management plan must list the project team members responsible for updating the schedule, who are then listed in the communications plan.
D. The communications plan must specify the software to be used for distributing the Gantt chart.

58 A project manager is preparing a budget for a project and is currently in the initiation phase. According to best practices, what type of cost estimate should be created at this stage, and what would its expected accuracy range be?

Project Management Cost and Estimation Hard
A. A Rough Order of Magnitude (ROM) estimate with an accuracy range of -25% to +75%.
B. A Definitive Estimate with an accuracy range of -5% to +10%.
C. A Budgetary Estimate with an accuracy range of -10% to +25%.
D. A Phased Estimate based on rolling wave planning with variable accuracy for each phase.

59 A project involves constructing a large, complex chemical processing plant. The project has thousands of activities, complex resource dependencies, and requires sophisticated risk modeling using Monte Carlo simulation. The company is choosing between a standard desktop project scheduling tool and a high-end Enterprise Project Portfolio Management (EPPM) system. What is the most compelling justification for the significant extra cost of the EPPM system in this context?

Estimating Tools Hard
A. The EPPM system's cloud-based platform, which allows for real-time collaboration among geographically dispersed team members.
B. The EPPM system's superior Gantt chart visualization capabilities and user-friendly interface for team members.
C. The EPPM system's integration with the company's financial accounting software for more accurate cost reporting.
D. The EPPM system's ability to perform probabilistic schedule analysis (e.g., Monte Carlo simulation) and its robust resource leveling algorithms across a large, shared resource pool.

60 A project manager is reviewing activity duration estimates from the team. A senior engineer has estimated a testing activity will take 10 days. The project manager knows that Parkinson's Law suggests work expands to fill the time available. Conversely, the manager is also concerned about Student Syndrome, where people start work at the last possible moment. How do these two theories collectively impact project duration estimation and scheduling?

Project Duration Estimation Hard
A. They create a rationale for removing safety buffers from individual tasks and aggregating them into a project-level buffer, which is actively managed by the PM (a core concept of Critical Chain Project Management).
B. They justify adding extra contingency time to every single activity in the schedule to account for both premature and delayed starts.
C. They indicate that Finish-to-Start dependencies are inherently flawed and should be replaced with Start-to-Start dependencies to compel earlier starts.
D. They suggest that all estimates provided by team members should be uniformly reduced by a certain percentage (e.g., 15%) to force efficiency.