Unit 13: Managing Costs - Practice Quiz

INT416 — Software Project Management Laboratory 60 Questions
0 Correct 0 Wrong 60 Left
0/60

1 What does the total cost of a task generally include?

Managing total costs for tasks and resources Easy
A. Only the task's fixed cost
B. Resource costs and fixed costs
C. Baseline costs and deadlines
D. Only resource overtime costs

2 How is the total cost of a work resource generally determined?

Managing total costs for tasks and resources Easy
A. By multiplying deadlines by priority
B. By adding the costs of its assignments
C. By counting the number of milestones
D. By subtracting work from duration

3 What is a fixed cost in project management software?

Managing total costs for tasks and resources Easy
A. A rate assigned to every resource
B. A cost assigned directly to a task
C. A variance calculated after completion
D. A budget distributed across resources

4 Which table is commonly used to review task costs in Microsoft Project?

Managing total costs for tasks and resources Easy
A. Tracking table
B. Entry table
C. Schedule table
D. Cost table

5 What does the total project cost represent?

Managing total costs for the entire project Easy
A. The combined cost of all project work
B. The cost of the first assigned resource
C. The cost of the longest project task
D. The difference between start and finish

6 Which feature can provide a summary of the project's total cost?

Managing total costs for the entire project Easy
A. Resource Calendar
B. Project Statistics
C. Network Diagram
D. Task Notes

7 Why should a cost baseline be saved before tracking begins?

Managing total costs for the entire project Easy
A. To remove all resource assignments
B. To shorten every task duration
C. To preserve the approved cost plan
D. To replace the project calendar

8 If the costs of individual tasks increase, what will usually happen to the total project cost?

Managing total costs for the entire project Easy
A. It will remain unchanged
B. It will usually increase
C. It will become the baseline
D. It will always decrease

9 Which formula is commonly used to calculate cost variance in project scheduling software?

Managing cost variances for tasks, resources, and assignments Easy
A.
B.
C.
D.

10 What does a positive cost variance usually indicate when variance is calculated as current cost minus baseline cost?

Managing cost variances for tasks, resources, and assignments Easy
A. The item has no baseline
B. The item is under budget
C. The item is over budget
D. The item is ahead of schedule

11 What does a negative cost variance usually indicate when variance is current cost minus baseline cost?

Managing cost variances for tasks, resources, and assignments Easy
A. The item has been deleted
B. The item has no duration
C. The item is under budget
D. The item is over budget

12 At which levels can cost variance be reviewed?

Managing cost variances for tasks, resources, and assignments Easy
A. Calendar, filter, and report levels
B. Task, resource, and assignment levels
C. Phase, deadline, and priority levels
D. File, folder, and template levels

13 What does timephased cost data show?

Managing timephased baseline budgeted costs and actual costs Easy
A. Costs stored without project dates
B. Costs grouped only by task priority
C. Costs sorted only by resource name
D. Costs distributed across time periods

14 What is a timephased baseline cost?

Managing timephased baseline budgeted costs and actual costs Easy
A. The completed work listed by priority
B. The current resource list sorted by rate
C. The approved cost plan distributed over time
D. The project duration without task dates

15 What does actual cost represent?

Managing timephased baseline budgeted costs and actual costs Easy
A. The estimated cost of future milestones
B. The cost incurred for completed work
C. The maximum rate allowed for resources
D. The cost planned before work begins

16 Which view type is useful for examining costs across specific time periods?

Managing timephased baseline budgeted costs and actual costs Easy
A. Calendar view
B. Network Diagram view
C. Timeline view
D. Task Usage view

17 A resource performs hours of overtime at an overtime rate of per hour. What is the overtime cost?

Calculate overtime costs Easy
A.
B.
C.
D.

18 Which formula calculates overtime cost?

Calculate overtime costs Easy
A.
B.
C.
D.

19 What is a likely result of updating a resource's pay rate?

Update costs Easy
A. Affected assignment costs are recalculated
B. All task dependencies are removed
C. The project baseline is automatically deleted
D. All incomplete tasks become milestones

20 When project progress is updated, which cost value records the expense already incurred?

Update costs Easy
A. Actual Cost
B. Remaining Cost
C. Baseline Cost
D. Fixed Cost

21 A task has 16 hours of work assigned to a resource whose standard rate is $40 per hour. The task also has a fixed cost of $200. What is the task's total cost?

Managing total costs for tasks and resources Medium
A. $1,040
B. $640
C. $800
D. $840

22 A resource charges $30 per hour and has a $50 cost per use. The resource is assigned for 10 hours to one task and 15 hours to another task. What is the resource's total cost?

Managing total costs for tasks and resources Medium
A. $850
B. $800
C. $900
D. $750

23 A task uses 25 units of material at $8 per unit and 6 hours of labor at $50 per hour. There is no fixed cost. What is the total task cost?

Managing total costs for tasks and resources Medium
A. $500
B. $450
C. $480
D. $550

24 A project contains summary tasks and their subtasks. Which method correctly calculates total cost without double-counting?

Managing total costs for tasks and resources Medium
A. Add summary-task costs to their detailed subtask costs
B. Add costs of lowest-level tasks and project-level costs
C. Add all summary-task costs and project overheads
D. Add every task and resource cost shown in all views

25 Three lowest-level tasks have current costs of $1,200, $1,800, and $2,500. A project-level fixed cost of $500 is entered on the project summary task. What is the total project cost?

Managing total costs for the entire project Medium
A. $5,500
B. $6,500
C. $6,000
D. $5,000

26 A project baseline was saved at $80,000. New approved work costing $6,000 is added, but the project is not rebaselined. What should happen?

Managing total costs for the entire project Medium
A. Both current and baseline cost become $86,000
B. Current cost remains $80,000 and baseline becomes $86,000
C. Current cost becomes $86,000 and baseline remains $80,000
D. Both current and baseline cost remain at $80,000

27 Which feature is most suitable for quickly reviewing current, baseline, actual, and remaining cost totals for the whole project?

Managing total costs for the entire project Medium
A. The Resource Graph view
B. The Project Statistics dialog
C. The Task Form view
D. The Network Diagram view

28 A task has a baseline cost of $2,400 and a current cost of $2,700. Using the standard Cost Variance field, where , what is the result?

Managing cost variances for tasks, resources, and assignments Medium
A. , over budget
B. , over budget
C. , under budget
D. , under budget

29 A resource has a baseline cost of $5,000 and a current cost of $4,600 across all assignments. What is the resource's cost variance?

Managing cost variances for tasks, resources, and assignments Medium
A. , over budget
B. , under budget
C. , over budget
D. , under budget

30 An assignment was baselined for 30 hours at $60 per hour. It now has 20 hours of actual work and 15 hours of remaining work at the same rate. What is its cost variance?

Managing cost variances for tasks, resources, and assignments Medium
A. $0
B. $-300
C. $300
D. $900

31 A task's total cost variance is high, and the project manager needs to identify which resource assignment caused it. What is the most appropriate approach?

Managing cost variances for tasks, resources, and assignments Medium
A. Review only the task's duration in the Gantt Chart
B. Expand assignment rows in a Usage view and compare cost fields
C. Inspect only the overall project cost in Project Statistics
D. Replace the task's resources with generic resources

32 A task has baseline costs of $1,000 in week 1, $1,500 in week 2, and $500 in week 3. Actual costs through the end of week 2 are $900 and $1,700. What is the cumulative actual-minus-baseline difference through week 2?

Managing timephased baseline budgeted costs and actual costs Medium
A. $-100
B. $0
C. $-400
D. $100

33 Which setup best supports comparing planned and actual costs for each week of a task?

Managing timephased baseline budgeted costs and actual costs Medium
A. Use Task Usage and add Baseline Cost and Actual Cost details
B. Use Resource Sheet and display only standard rates
C. Use Network Diagram and group tasks by total slack
D. Use the Calendar view and display resource initials

34 A task's $1,000 baseline cost was planned entirely in week 1. The same $1,000 actual cost occurred entirely in week 2. Which interpretation is correct?

Managing timephased baseline budgeted costs and actual costs Medium
A. The task has no timing difference because totals are equal
B. The totals match, but the weekly cost distribution differs
C. The baseline automatically moves from week 1 to week 2
D. The actual cost must be moved back into week 1

35 An assignment has 48 hours of total work, including 8 hours of overtime work. The standard rate is $25 per hour and the overtime rate is $40 per hour. What is the total assignment cost?

Calculate overtime costs Medium
A. $1,520
B. $1,200
C. $1,440
D. $1,320

36 A resource completes 6 overtime hours at an overtime rate of $45 per hour. What amount is recorded as the overtime cost?

Calculate overtime costs Medium
A. $270
B. $260
C. $225
D. $240

37 A resource performs 20 regular hours at $30 per hour and 5 overtime hours at $50 per hour. A $100 cost per use applies to the assignment. What is the total cost?

Calculate overtime costs Medium
A. $1,100
B. $950
C. $850
D. $1,000

38 A task has 20 hours of work at $50 per hour. After updating the task, 12 hours are actual work and 8 hours remain. Assuming automatic cost calculation and no rate changes, which cost values are correct?

Update costs Medium
A. Actual $400, remaining $600, total $1,000
B. Actual $600, remaining $800, total $1,400
C. Actual $600, remaining $400, total $1,000
D. Actual $1,000, remaining $400, total $1,400

39 A resource's standard rate is $40 per hour until June 30 and $50 per hour starting July 1. An assignment schedules 10 hours in June and 10 hours in July. What is the updated labor cost?

Update costs Medium
A. $900
B. $800
C. $1,000
D. $1,100

40 A project has a baseline cost of $2,200, an actual cost of $1,400, and a remaining cost of $900. The remaining forecast is then increased by $300. What are the updated current cost and cost variance?

Update costs Medium
A. Current $2,600 and variance $300
B. Current $2,600 and variance $400
C. Current $2,500 and variance $300
D. Current $2,300 and variance $100

41 A task has a fixed cost of $1,200. Resource A performs 30 hours at $80/hour and Resource B performs 24 regular hours at $60/hour plus 6 overtime hours at $90/hour. Resource B also has a $150 per-use cost. What is the task's total cost?

Managing total costs for tasks and resources Hard
A. $6,030
B. $5,880
C. $5,580
D. $5,730

42 A material resource has a rate of $12 per unit and a per-use cost of $80. It is assigned 150 units to one task and 50 units to another task. Assuming each assignment triggers the per-use cost once, what total resource cost rolls up to the project?

Managing total costs for tasks and resources Hard
A. $2,480
B. $2,400
C. $2,560
D. $2,640

43 A summary task contains two subtasks costing $8,000 and $11,500. A separate recurring summary task is shown only as a grouping row and has no assignments or fixed cost of its own. What action correctly increases the summary total by $2,500 without double-counting resource costs?

Managing total costs for tasks and resources Hard
A. Add a $2,500 fixed cost to one appropriate subtask
B. Enter $22,000 directly in the summary Cost field
C. Add a $2,500 resource cost to the summary row
D. Raise both subtask costs by $2,500 each

44 A resource has an effective-dated standard rate of $50/hour through June 30 and $65/hour beginning July 1. One assignment contains 16 regular hours on June 30 and 24 regular hours on July 1. Ignoring other charges, what is the assignment cost?

Managing total costs for tasks and resources Hard
A. $2,000
B. $2,600
C. $2,360
D. $2,200

45 A project contains three top-level deliverables with costs of $42,000, $31,500, and $26,500. A project-level contingency of $5,000 is represented by a separate task. The first deliverable is also displayed through a custom grouping, but grouping rows do not add cost. What is the entire project cost?

Managing total costs for the entire project Hard
A. $100,000
B. $105,000
C. $142,000
D. $147,000

46 The project summary task shows Cost = $480,000 and Baseline Cost = $450,000. An approved but unbaselined scope addition costs $20,000, while unrelated overhead of $12,000 is tracked outside the project file. What cost variance should the project file report?

Managing total costs for the entire project Hard
A. $18,000
B. $20,000
C. $42,000
D. $30,000

47 A project has Actual Cost = $210,000 and Remaining Cost = $145,000. Management approves a $25,000 increase in remaining work, but no new baseline is saved. What are the resulting Cost and Baseline Cost if the original baseline was $330,000?

Managing total costs for the entire project Hard
A. Cost $355,000; Baseline $330,000
B. Cost $380,000; Baseline $355,000
C. Cost $380,000; Baseline $330,000
D. Cost $355,000; Baseline $355,000

48 An assignment has Baseline Cost = $9,600, Actual Cost = $7,200, and Remaining Cost = $3,100. Using the standard project Cost Variance definition, what is its cost variance?

Managing cost variances for tasks, resources, and assignments Hard
A. $700
B. $-2,400
C. $3,100
D. $-700

49 A task contains two assignments. Assignment X has Cost = $18,000 and Baseline Cost = $20,000. Assignment Y has Cost = $27,500 and Baseline Cost = $24,000. The task also has an unbaselined fixed cost of $1,000. What is the task's total cost variance?

Managing cost variances for tasks, resources, and assignments Hard
A. $2,500
B. $4,500
C. $1,500
D. $500

50 A resource's assignment variances are $-1,200, $900, and $650. A fourth assignment has current Cost = $4,000 but no baseline. Assuming an absent baseline contributes zero baseline cost, what variance rolls up for the resource?

Managing cost variances for tasks, resources, and assignments Hard
A. $3,650
B. $4,350
C. $4,000
D. $350

51 A task's Cost Variance is $6,000 unfavorable. After correcting a mistakenly high remaining-work estimate, current Cost falls by $4,500. Its baseline is unchanged. What is the revised variance?

Managing cost variances for tasks, resources, and assignments Hard
A. $1,500 unfavorable
B. $4,500 unfavorable
C. $1,500 favorable
D. $10,500 unfavorable

52 A task's timephased baseline cost is $8,000 in Week 1, $12,000 in Week 2, and $10,000 in Week 3. At the end of Week 2, timephased actual costs are $9,000 and $10,500, respectively. What is the cumulative actual-versus-baseline difference through the status date?

Managing timephased baseline budgeted costs and actual costs Hard
A. $500 over baseline
B. $10,500 under baseline
C. $500 under baseline
D. $10,500 over baseline

53 A $6,000 fixed cost is accrued at task completion. The baseline schedules completion in Week 3, but actual completion occurs in Week 4. Which timephased pattern is correct if the same completion-accrual rule applies to baseline and actual cost?

Managing timephased baseline budgeted costs and actual costs Hard
A. Both baseline and actual in Week 3
B. Both baseline and actual in Week 4
C. Baseline in Week 3; actual in Week 4
D. Baseline in Week 4; actual in Week 3

54 A task has a baseline cost of $40,000 spread uniformly across four weeks. It starts one week late, but the baseline is not changed. By the end of calendar Week 2, only one week of work has occurred and Actual Cost is $9,000. What are cumulative baseline cost and actual cost through Week 2?

Managing timephased baseline budgeted costs and actual costs Hard
A. Baseline $20,000; actual $18,000
B. Baseline $20,000; actual $9,000
C. Baseline $10,000; actual $9,000
D. Baseline $30,000; actual $9,000

55 A task has timephased Baseline Cost values of $5,000, $7,000, and $8,000 for Weeks 1-3. Actual Cost values are $4,800, $7,600, and $0. At the end of Week 2, which statement is correct?

Managing timephased baseline budgeted costs and actual costs Hard
A. Cumulative actual is $400 below cumulative baseline
B. Cumulative actual is $600 above cumulative baseline
C. Cumulative actual is $400 above cumulative baseline
D. Cumulative actual is $600 below cumulative baseline

56 An assignment records 46 total work hours, of which 8 are explicitly designated as overtime work. The standard rate is $55/hour and the overtime rate is $82/hour. What is the labor cost?

Calculate overtime costs Hard
A. $3,402
B. $3,828
C. $2,746
D. $2,910

57 A resource works 12 hours on a day with an 8-hour calendar. The assignment records 12 hours of Work but 0 hours of Overtime Work. The standard rate is $40/hour and the overtime rate is $70/hour. Under explicit overtime accounting, what cost is calculated?

Calculate overtime costs Hard
A. $480
B. $720
C. $600
D. $840

58 A resource performs 20 regular hours and 6 overtime hours. The standard rate is $50/hour, the overtime rate is $75/hour, and a $120 per-use cost applies once to the assignment. What is the assignment's total cost?

Calculate overtime costs Hard
A. $1,870
B. $1,450
C. $1,750
D. $1,570

59 A resource assignment originally has 100 hours of work at $60/hour. After 40 hours are reported complete, the remaining work is revised from 60 to 45 hours, with rates unchanged. What are Actual Cost, Remaining Cost, and total Cost under automatic cost calculation?

Update costs Hard
A. $2,700; $2,400; $5,100
B. $2,400; $3,600; $6,000
C. $3,600; $2,700; $6,300
D. $2,400; $2,700; $5,100

60 Actual costs are being calculated automatically from actual work. A manager needs to enter invoice-based actual costs that differ from work-derived values. Which change is required before those actual costs can be entered directly without immediate recalculation?

Update costs Hard
A. Move the project status date forward
B. Delete the assignment's baseline values
C. Disable automatic actual-cost calculation
D. Change fixed-cost accrual to prorated