1What does the total cost of a task generally include?
Managing total costs for tasks and resources
Easy
A.Only the task's fixed cost
B.Resource costs and fixed costs
C.Baseline costs and deadlines
D.Only resource overtime costs
Correct Answer: Resource costs and fixed costs
Explanation:
A task's total cost generally combines its resource assignment costs and any fixed cost entered for the task.
Incorrect! Try again.
2How is the total cost of a work resource generally determined?
Managing total costs for tasks and resources
Easy
A.By multiplying deadlines by priority
B.By adding the costs of its assignments
C.By counting the number of milestones
D.By subtracting work from duration
Correct Answer: By adding the costs of its assignments
Explanation:
A resource's total cost is the sum of the costs generated by all its project assignments.
Incorrect! Try again.
3What is a fixed cost in project management software?
Managing total costs for tasks and resources
Easy
A.A rate assigned to every resource
B.A cost assigned directly to a task
C.A variance calculated after completion
D.A budget distributed across resources
Correct Answer: A cost assigned directly to a task
Explanation:
A fixed cost is entered directly for a task and does not depend on the amount of resource work.
Incorrect! Try again.
4Which table is commonly used to review task costs in Microsoft Project?
Managing total costs for tasks and resources
Easy
A.Tracking table
B.Entry table
C.Schedule table
D.Cost table
Correct Answer: Cost table
Explanation:
The Cost table displays fields such as Cost, Baseline Cost, Actual Cost, Remaining Cost, and Cost Variance.
Incorrect! Try again.
5What does the total project cost represent?
Managing total costs for the entire project
Easy
A.The combined cost of all project work
B.The cost of the first assigned resource
C.The cost of the longest project task
D.The difference between start and finish
Correct Answer: The combined cost of all project work
Explanation:
The total project cost combines the costs associated with all tasks, assignments, resources, and applicable fixed costs.
Incorrect! Try again.
6Which feature can provide a summary of the project's total cost?
Managing total costs for the entire project
Easy
A.Resource Calendar
B.Project Statistics
C.Network Diagram
D.Task Notes
Correct Answer: Project Statistics
Explanation:
Project Statistics provides summary information such as current, baseline, actual, and remaining project costs.
Incorrect! Try again.
7Why should a cost baseline be saved before tracking begins?
Managing total costs for the entire project
Easy
A.To remove all resource assignments
B.To shorten every task duration
C.To preserve the approved cost plan
D.To replace the project calendar
Correct Answer: To preserve the approved cost plan
Explanation:
A baseline stores the approved cost plan so that current and actual costs can later be compared with it.
Incorrect! Try again.
8If the costs of individual tasks increase, what will usually happen to the total project cost?
Managing total costs for the entire project
Easy
A.It will remain unchanged
B.It will usually increase
C.It will become the baseline
D.It will always decrease
Correct Answer: It will usually increase
Explanation:
Because task costs contribute to the overall project cost, increases in task costs generally increase the project total.
Incorrect! Try again.
9Which formula is commonly used to calculate cost variance in project scheduling software?
Managing cost variances for tasks, resources, and assignments
Easy
A.
B.
C.
D.
Correct Answer:
Explanation:
Cost variance compares the current scheduled cost with the saved baseline cost.
Incorrect! Try again.
10What does a positive cost variance usually indicate when variance is calculated as current cost minus baseline cost?
Managing cost variances for tasks, resources, and assignments
Easy
A.The item has no baseline
B.The item is under budget
C.The item is over budget
D.The item is ahead of schedule
Correct Answer: The item is over budget
Explanation:
A positive variance means the current cost is greater than the baseline cost, indicating an over-budget condition.
Incorrect! Try again.
11What does a negative cost variance usually indicate when variance is current cost minus baseline cost?
Managing cost variances for tasks, resources, and assignments
Easy
A.The item has been deleted
B.The item has no duration
C.The item is under budget
D.The item is over budget
Correct Answer: The item is under budget
Explanation:
A negative variance means the current cost is lower than the baseline cost, indicating an under-budget condition.
Incorrect! Try again.
12At which levels can cost variance be reviewed?
Managing cost variances for tasks, resources, and assignments
Easy
A.Calendar, filter, and report levels
B.Task, resource, and assignment levels
C.Phase, deadline, and priority levels
D.File, folder, and template levels
Correct Answer: Task, resource, and assignment levels
Explanation:
Cost variance can be examined for tasks, resources, and individual resource assignments.
Incorrect! Try again.
13What does timephased cost data show?
Managing timephased baseline budgeted costs and actual costs
Easy
A.Costs stored without project dates
B.Costs grouped only by task priority
C.Costs sorted only by resource name
D.Costs distributed across time periods
Correct Answer: Costs distributed across time periods
Explanation:
Timephased data shows how costs are planned or incurred over days, weeks, months, or other periods.
Incorrect! Try again.
14What is a timephased baseline cost?
Managing timephased baseline budgeted costs and actual costs
Easy
A.The completed work listed by priority
B.The current resource list sorted by rate
C.The approved cost plan distributed over time
D.The project duration without task dates
Correct Answer: The approved cost plan distributed over time
Explanation:
A timephased baseline cost shows when the approved budget was originally planned to be spent.
Incorrect! Try again.
15What does actual cost represent?
Managing timephased baseline budgeted costs and actual costs
Easy
A.The estimated cost of future milestones
B.The cost incurred for completed work
C.The maximum rate allowed for resources
D.The cost planned before work begins
Correct Answer: The cost incurred for completed work
Explanation:
Actual cost records the cost already incurred as project work is performed.
Incorrect! Try again.
16Which view type is useful for examining costs across specific time periods?
Managing timephased baseline budgeted costs and actual costs
Easy
A.Calendar view
B.Network Diagram view
C.Timeline view
D.Task Usage view
Correct Answer: Task Usage view
Explanation:
The Task Usage view can display timephased fields, allowing costs to be examined by day, week, month, or another period.
Incorrect! Try again.
17A resource performs hours of overtime at an overtime rate of per hour. What is the overtime cost?
Calculate overtime costs
Easy
A.
B.
C.
D.
Correct Answer:
Explanation:
Overtime cost is .
Incorrect! Try again.
18Which formula calculates overtime cost?
Calculate overtime costs
Easy
A.
B.
C.
D.
Correct Answer:
Explanation:
Overtime cost is calculated by multiplying overtime work hours by the resource's overtime rate.
Incorrect! Try again.
19What is a likely result of updating a resource's pay rate?
Update costs
Easy
A.Affected assignment costs are recalculated
B.All task dependencies are removed
C.The project baseline is automatically deleted
D.All incomplete tasks become milestones
Correct Answer: Affected assignment costs are recalculated
Explanation:
When a resource rate changes, the software can recalculate costs for the assignments affected by that rate.
Incorrect! Try again.
20When project progress is updated, which cost value records the expense already incurred?
Update costs
Easy
A.Actual Cost
B.Remaining Cost
C.Baseline Cost
D.Fixed Cost
Correct Answer: Actual Cost
Explanation:
Actual Cost represents the expense incurred for work that has already been performed.
Incorrect! Try again.
21A task has 16 hours of work assigned to a resource whose standard rate is $40 per hour. The task also has a fixed cost of $200. What is the task's total cost?
Managing total costs for tasks and resources
Medium
A.$1,040
B.$640
C.$800
D.$840
Correct Answer: $840
Explanation:
The resource cost is . Adding the fixed cost gives .
Incorrect! Try again.
22A resource charges $30 per hour and has a $50 cost per use. The resource is assigned for 10 hours to one task and 15 hours to another task. What is the resource's total cost?
Managing total costs for tasks and resources
Medium
A.$850
B.$800
C.$900
D.$750
Correct Answer: $850
Explanation:
Work cost is . The $50 cost per use applies to each of the two assignments, so the total is $750 + 100 = 850$.
Incorrect! Try again.
23A task uses 25 units of material at $8 per unit and 6 hours of labor at $50 per hour. There is no fixed cost. What is the total task cost?
Managing total costs for tasks and resources
Medium
A.$500
B.$450
C.$480
D.$550
Correct Answer: $500
Explanation:
Material cost is , and labor cost is . Therefore, total cost is .
Incorrect! Try again.
24A project contains summary tasks and their subtasks. Which method correctly calculates total cost without double-counting?
Managing total costs for tasks and resources
Medium
A.Add summary-task costs to their detailed subtask costs
B.Add costs of lowest-level tasks and project-level costs
C.Add all summary-task costs and project overheads
D.Add every task and resource cost shown in all views
Correct Answer: Add costs of lowest-level tasks and project-level costs
Explanation:
Summary-task costs already roll up costs from their subtasks. Adding both summary tasks and subtasks would count the same costs twice.
Incorrect! Try again.
25Three lowest-level tasks have current costs of $1,200, $1,800, and $2,500. A project-level fixed cost of $500 is entered on the project summary task. What is the total project cost?
Managing total costs for the entire project
Medium
A.$5,500
B.$6,500
C.$6,000
D.$5,000
Correct Answer: $6,000
Explanation:
The total is .
Incorrect! Try again.
26A project baseline was saved at $80,000. New approved work costing $6,000 is added, but the project is not rebaselined. What should happen?
Managing total costs for the entire project
Medium
A.Both current and baseline cost become $86,000
B.Current cost remains $80,000 and baseline becomes $86,000
C.Current cost becomes $86,000 and baseline remains $80,000
D.Both current and baseline cost remain at $80,000
Correct Answer: Current cost becomes $86,000 and baseline remains $80,000
Explanation:
Adding work updates the current forecast. The saved baseline remains unchanged until the relevant tasks or the project are explicitly rebaselined.
Incorrect! Try again.
27Which feature is most suitable for quickly reviewing current, baseline, actual, and remaining cost totals for the whole project?
Managing total costs for the entire project
Medium
A.The Resource Graph view
B.The Project Statistics dialog
C.The Task Form view
D.The Network Diagram view
Correct Answer: The Project Statistics dialog
Explanation:
The Project Statistics dialog summarizes major project-level values, including current, baseline, actual, and remaining costs.
Incorrect! Try again.
28A task has a baseline cost of $2,400 and a current cost of $2,700. Using the standard Cost Variance field, where , what is the result?
Managing cost variances for tasks, resources, and assignments
Medium
A., over budget
B., over budget
C., under budget
D., under budget
Correct Answer: , over budget
Explanation:
The variance is . A positive value means the current cost is above the baseline.
Incorrect! Try again.
29A resource has a baseline cost of $5,000 and a current cost of $4,600 across all assignments. What is the resource's cost variance?
Managing cost variances for tasks, resources, and assignments
Medium
A., over budget
B., under budget
C., over budget
D., under budget
Correct Answer: , under budget
Explanation:
Cost variance is . The negative value indicates that the resource is currently $400 under budget.
Incorrect! Try again.
30An assignment was baselined for 30 hours at $60 per hour. It now has 20 hours of actual work and 15 hours of remaining work at the same rate. What is its cost variance?
Managing cost variances for tasks, resources, and assignments
Medium
A.$0
B.$-300
C.$300
D.$900
Correct Answer: $300
Explanation:
Baseline cost is . Current cost is , so variance is .
Incorrect! Try again.
31A task's total cost variance is high, and the project manager needs to identify which resource assignment caused it. What is the most appropriate approach?
Managing cost variances for tasks, resources, and assignments
Medium
A.Review only the task's duration in the Gantt Chart
B.Expand assignment rows in a Usage view and compare cost fields
C.Inspect only the overall project cost in Project Statistics
D.Replace the task's resources with generic resources
Correct Answer: Expand assignment rows in a Usage view and compare cost fields
Explanation:
Task Usage or Resource Usage views expose assignment-level values. Comparing Cost, Baseline Cost, and Cost Variance identifies the assignment causing the variance.
Incorrect! Try again.
32A task has baseline costs of $1,000 in week 1, $1,500 in week 2, and $500 in week 3. Actual costs through the end of week 2 are $900 and $1,700. What is the cumulative actual-minus-baseline difference through week 2?
Managing timephased baseline budgeted costs and actual costs
Medium
A.$-100
B.$0
C.$-400
D.$100
Correct Answer: $100
Explanation:
Baseline through week 2 is . Actual cost is , so the difference is .
Incorrect! Try again.
33Which setup best supports comparing planned and actual costs for each week of a task?
Managing timephased baseline budgeted costs and actual costs
Medium
A.Use Task Usage and add Baseline Cost and Actual Cost details
B.Use Resource Sheet and display only standard rates
C.Use Network Diagram and group tasks by total slack
D.Use the Calendar view and display resource initials
Correct Answer: Use Task Usage and add Baseline Cost and Actual Cost details
Explanation:
The timephased grid in Task Usage can display Baseline Cost and Actual Cost by day, week, month, or another selected timescale.
Incorrect! Try again.
34A task's $1,000 baseline cost was planned entirely in week 1. The same $1,000 actual cost occurred entirely in week 2. Which interpretation is correct?
Managing timephased baseline budgeted costs and actual costs
Medium
A.The task has no timing difference because totals are equal
B.The totals match, but the weekly cost distribution differs
C.The baseline automatically moves from week 1 to week 2
D.The actual cost must be moved back into week 1
Correct Answer: The totals match, but the weekly cost distribution differs
Explanation:
Cumulative totals are equal, but timephased comparison shows no actual cost in week 1 and an unplanned $1,000 actual cost in week 2.
Incorrect! Try again.
35An assignment has 48 hours of total work, including 8 hours of overtime work. The standard rate is $25 per hour and the overtime rate is $40 per hour. What is the total assignment cost?
Calculate overtime costs
Medium
A.$1,520
B.$1,200
C.$1,440
D.$1,320
Correct Answer: $1,320
Explanation:
Regular work is hours. Total cost is .
Incorrect! Try again.
36A resource completes 6 overtime hours at an overtime rate of $45 per hour. What amount is recorded as the overtime cost?
Calculate overtime costs
Medium
A.$270
B.$260
C.$225
D.$240
Correct Answer: $270
Explanation:
Overtime cost equals overtime work multiplied by the overtime rate: .
Incorrect! Try again.
37A resource performs 20 regular hours at $30 per hour and 5 overtime hours at $50 per hour. A $100 cost per use applies to the assignment. What is the total cost?
Calculate overtime costs
Medium
A.$1,100
B.$950
C.$850
D.$1,000
Correct Answer: $950
Explanation:
The total is .
Incorrect! Try again.
38A task has 20 hours of work at $50 per hour. After updating the task, 12 hours are actual work and 8 hours remain. Assuming automatic cost calculation and no rate changes, which cost values are correct?
Update costs
Medium
A.Actual $400, remaining $600, total $1,000
B.Actual $600, remaining $800, total $1,400
C.Actual $600, remaining $400, total $1,000
D.Actual $1,000, remaining $400, total $1,400
Correct Answer: Actual $600, remaining $400, total $1,000
Explanation:
Actual cost is , and remaining cost is . Current total cost is .
Incorrect! Try again.
39A resource's standard rate is $40 per hour until June 30 and $50 per hour starting July 1. An assignment schedules 10 hours in June and 10 hours in July. What is the updated labor cost?
Update costs
Medium
A.$900
B.$800
C.$1,000
D.$1,100
Correct Answer: $900
Explanation:
The date-effective rates produce a cost of .
Incorrect! Try again.
40A project has a baseline cost of $2,200, an actual cost of $1,400, and a remaining cost of $900. The remaining forecast is then increased by $300. What are the updated current cost and cost variance?
Update costs
Medium
A.Current $2,600 and variance $300
B.Current $2,600 and variance $400
C.Current $2,500 and variance $300
D.Current $2,300 and variance $100
Correct Answer: Current $2,600 and variance $400
Explanation:
Updated remaining cost is . Current cost becomes , and variance is .
Incorrect! Try again.
41A task has a fixed cost of $1,200. Resource A performs 30 hours at $80/hour and Resource B performs 24 regular hours at $60/hour plus 6 overtime hours at $90/hour. Resource B also has a $150 per-use cost. What is the task's total cost?
Managing total costs for tasks and resources
Hard
A.$6,030
B.$5,880
C.$5,580
D.$5,730
Correct Answer: $5,730
Explanation:
The total is .
Incorrect! Try again.
42A material resource has a rate of $12 per unit and a per-use cost of $80. It is assigned 150 units to one task and 50 units to another task. Assuming each assignment triggers the per-use cost once, what total resource cost rolls up to the project?
Managing total costs for tasks and resources
Hard
A.$2,480
B.$2,400
C.$2,560
D.$2,640
Correct Answer: $2,560
Explanation:
Usage costs are . Two assignment-level per-use charges add , producing .
Incorrect! Try again.
43A summary task contains two subtasks costing $8,000 and $11,500. A separate recurring summary task is shown only as a grouping row and has no assignments or fixed cost of its own. What action correctly increases the summary total by $2,500 without double-counting resource costs?
Managing total costs for tasks and resources
Hard
A.Add a $2,500 fixed cost to one appropriate subtask
B.Enter $22,000 directly in the summary Cost field
C.Add a $2,500 resource cost to the summary row
D.Raise both subtask costs by $2,500 each
Correct Answer: Add a $2,500 fixed cost to one appropriate subtask
Explanation:
Summary costs roll up from subtasks. Placing the fixed cost on the relevant subtask adds it once and preserves the rollup structure.
Incorrect! Try again.
44A resource has an effective-dated standard rate of $50/hour through June 30 and $65/hour beginning July 1. One assignment contains 16 regular hours on June 30 and 24 regular hours on July 1. Ignoring other charges, what is the assignment cost?
Managing total costs for tasks and resources
Hard
A.$2,000
B.$2,600
C.$2,360
D.$2,200
Correct Answer: $2,360
Explanation:
Timephased work uses the rate effective on each date: .
Incorrect! Try again.
45A project contains three top-level deliverables with costs of $42,000, $31,500, and $26,500. A project-level contingency of $5,000 is represented by a separate task. The first deliverable is also displayed through a custom grouping, but grouping rows do not add cost. What is the entire project cost?
Managing total costs for the entire project
Hard
A.$100,000
B.$105,000
C.$142,000
D.$147,000
Correct Answer: $105,000
Explanation:
Project cost is the rollup of real tasks: . A grouping row does not duplicate cost.
Incorrect! Try again.
46The project summary task shows Cost = $480,000 and Baseline Cost = $450,000. An approved but unbaselined scope addition costs $20,000, while unrelated overhead of $12,000 is tracked outside the project file. What cost variance should the project file report?
Managing total costs for the entire project
Hard
A.$18,000
B.$20,000
C.$42,000
D.$30,000
Correct Answer: $30,000
Explanation:
The project Cost Variance field is . External overhead is not part of either project field.
Incorrect! Try again.
47A project has Actual Cost = $210,000 and Remaining Cost = $145,000. Management approves a $25,000 increase in remaining work, but no new baseline is saved. What are the resulting Cost and Baseline Cost if the original baseline was $330,000?
Managing total costs for the entire project
Hard
A.Cost $355,000; Baseline $330,000
B.Cost $380,000; Baseline $355,000
C.Cost $380,000; Baseline $330,000
D.Cost $355,000; Baseline $355,000
Correct Answer: Cost $380,000; Baseline $330,000
Explanation:
New remaining cost is , so total Cost is . The baseline remains $330,000 until explicitly resaved.
Incorrect! Try again.
48An assignment has Baseline Cost = $9,600, Actual Cost = $7,200, and Remaining Cost = $3,100. Using the standard project Cost Variance definition, what is its cost variance?
Managing cost variances for tasks, resources, and assignments
Hard
A.$700
B.$-2,400
C.$3,100
D.$-700
Correct Answer: $700
Explanation:
Current Cost is . Therefore, , indicating an overrun.
Incorrect! Try again.
49A task contains two assignments. Assignment X has Cost = $18,000 and Baseline Cost = $20,000. Assignment Y has Cost = $27,500 and Baseline Cost = $24,000. The task also has an unbaselined fixed cost of $1,000. What is the task's total cost variance?
Managing cost variances for tasks, resources, and assignments
Hard
A.$2,500
B.$4,500
C.$1,500
D.$500
Correct Answer: $2,500
Explanation:
Task Cost is , while Baseline Cost is . The variance is .
Incorrect! Try again.
50A resource's assignment variances are $-1,200, $900, and $650. A fourth assignment has current Cost = $4,000 but no baseline. Assuming an absent baseline contributes zero baseline cost, what variance rolls up for the resource?
Managing cost variances for tasks, resources, and assignments
Hard
A.$3,650
B.$4,350
C.$4,000
D.$350
Correct Answer: $4,350
Explanation:
The unbaselined assignment contributes a $4,000 variance. The rollup is $-1,200+900+650+4,000=$4,350$.
Incorrect! Try again.
51A task's Cost Variance is $6,000 unfavorable. After correcting a mistakenly high remaining-work estimate, current Cost falls by $4,500. Its baseline is unchanged. What is the revised variance?
Managing cost variances for tasks, resources, and assignments
Hard
A.$1,500 unfavorable
B.$4,500 unfavorable
C.$1,500 favorable
D.$10,500 unfavorable
Correct Answer: $1,500 unfavorable
Explanation:
Because variance is , reducing Cost by $4,500 reduces the unfavorable variance from $6,000 to .
Incorrect! Try again.
52A task's timephased baseline cost is $8,000 in Week 1, $12,000 in Week 2, and $10,000 in Week 3. At the end of Week 2, timephased actual costs are $9,000 and $10,500, respectively. What is the cumulative actual-versus-baseline difference through the status date?
Managing timephased baseline budgeted costs and actual costs
Hard
A.$500 over baseline
B.$10,500 under baseline
C.$500 under baseline
D.$10,500 over baseline
Correct Answer: $500 under baseline
Explanation:
Through Week 2, baseline cost is and actual cost is . Actual cost is therefore $500 below the timephased baseline.
Incorrect! Try again.
53A $6,000 fixed cost is accrued at task completion. The baseline schedules completion in Week 3, but actual completion occurs in Week 4. Which timephased pattern is correct if the same completion-accrual rule applies to baseline and actual cost?
Managing timephased baseline budgeted costs and actual costs
Hard
A.Both baseline and actual in Week 3
B.Both baseline and actual in Week 4
C.Baseline in Week 3; actual in Week 4
D.Baseline in Week 4; actual in Week 3
Correct Answer: Baseline in Week 3; actual in Week 4
Explanation:
The baseline preserves the planned completion timing, while actual cost follows the actual completion timing. Completion-accrued cost therefore appears in different weeks.
Incorrect! Try again.
54A task has a baseline cost of $40,000 spread uniformly across four weeks. It starts one week late, but the baseline is not changed. By the end of calendar Week 2, only one week of work has occurred and Actual Cost is $9,000. What are cumulative baseline cost and actual cost through Week 2?
Managing timephased baseline budgeted costs and actual costs
Hard
A.Baseline $20,000; actual $18,000
B.Baseline $20,000; actual $9,000
C.Baseline $10,000; actual $9,000
D.Baseline $30,000; actual $9,000
Correct Answer: Baseline $20,000; actual $9,000
Explanation:
The saved baseline remains $10,000 per planned week, so two planned weeks total $20,000. Actual cost reflects the one week actually worked, totaling $9,000.
Incorrect! Try again.
55A task has timephased Baseline Cost values of $5,000, $7,000, and $8,000 for Weeks 1-3. Actual Cost values are $4,800, $7,600, and $0. At the end of Week 2, which statement is correct?
Managing timephased baseline budgeted costs and actual costs
Hard
A.Cumulative actual is $400 below cumulative baseline
B.Cumulative actual is $600 above cumulative baseline
C.Cumulative actual is $400 above cumulative baseline
D.Cumulative actual is $600 below cumulative baseline
Correct Answer: Cumulative actual is $400 above cumulative baseline
Explanation:
Through Week 2, actual cost is and baseline cost is , giving a $400 overrun.
Incorrect! Try again.
56An assignment records 46 total work hours, of which 8 are explicitly designated as overtime work. The standard rate is $55/hour and the overtime rate is $82/hour. What is the labor cost?
Calculate overtime costs
Hard
A.$3,402
B.$3,828
C.$2,746
D.$2,910
Correct Answer: $2,746
Explanation:
Regular work is hours. The cost is .
Incorrect! Try again.
57A resource works 12 hours on a day with an 8-hour calendar. The assignment records 12 hours of Work but 0 hours of Overtime Work. The standard rate is $40/hour and the overtime rate is $70/hour. Under explicit overtime accounting, what cost is calculated?
Calculate overtime costs
Hard
A.$480
B.$720
C.$600
D.$840
Correct Answer: $480
Explanation:
Hours beyond the calendar are not automatically priced at the overtime rate. With zero Overtime Work, all 12 hours use the standard rate: .
Incorrect! Try again.
58A resource performs 20 regular hours and 6 overtime hours. The standard rate is $50/hour, the overtime rate is $75/hour, and a $120 per-use cost applies once to the assignment. What is the assignment's total cost?
Calculate overtime costs
Hard
A.$1,870
B.$1,450
C.$1,750
D.$1,570
Correct Answer: $1,570
Explanation:
The total is .
Incorrect! Try again.
59A resource assignment originally has 100 hours of work at $60/hour. After 40 hours are reported complete, the remaining work is revised from 60 to 45 hours, with rates unchanged. What are Actual Cost, Remaining Cost, and total Cost under automatic cost calculation?
Update costs
Hard
A.$2,700; $2,400; $5,100
B.$2,400; $3,600; $6,000
C.$3,600; $2,700; $6,300
D.$2,400; $2,700; $5,100
Correct Answer: $2,400; $2,700; $5,100
Explanation:
Actual Cost is and Remaining Cost is . Total Cost becomes .
Incorrect! Try again.
60Actual costs are being calculated automatically from actual work. A manager needs to enter invoice-based actual costs that differ from work-derived values. Which change is required before those actual costs can be entered directly without immediate recalculation?
Automatic actual-cost calculation derives costs from reported work and rates. It must be disabled when actual costs need to be entered independently from invoice data.
Incorrect! Try again.
Did this save you a night before the exam?
LPU Notes is free, and it stays free. Ads cover part of the server bill.
The rest comes out of a student's own pocket: the domain, the storage,
and keeping the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.
Nothing here is ever locked, and nothing unlocks. Chip in only if it was worth it.
What it pays for →