Notice: Due to an ongoing migration of our storage and publishing system, material requested since last month will not be uploaded for the time being, and new requests are paused. All existing notes remain available.
You're offline
Unit 6 MCQsInvestment Decisions
EFIN542 ·
60 questions. Pick an option to check it.
Question 1 of 60 · Discounting Techniques of Capital Budgeting · Easy
What is the main purpose of discounting future cash flows?
Not quite. Try another option.
Answer: To account for the time value of money
Discounting converts future cash flows into present values by recognizing the time value of money.
Question 2 of 60 · Discounting Techniques of Capital Budgeting · Easy
Which formula calculates the present value of a cash flow received after periods at discount rate ?
Not quite. Try another option.
Answer:
Present value is found by dividing the future value by the compound discount factor .
Question 3 of 60 · Net Present Value · Easy
What does Net Present Value measure?
Not quite. Try another option.
Answer: The present value of inflows minus outflows
NPV is the difference between the present value of cash inflows and the present value of cash outflows.
Question 4 of 60 · Net Present Value · Easy
Under the NPV rule, when should an independent project generally be accepted?
Not quite. Try another option.
Answer: When its NPV is positive
A positive NPV indicates that the project is expected to add value to the firm.
Question 5 of 60 · Net Present Value · Easy
A project requires an initial investment of $1,000 and has cash inflows with a total present value of $1,200. What is its NPV?
Not quite. Try another option.
Answer:
The NPV is .
Question 6 of 60 · Internal Rate of Return · Easy
What is the Internal Rate of Return of a project?
Not quite. Try another option.
Answer: The rate that makes NPV equal to zero
IRR is the discount rate at which the present value of inflows equals the present value of outflows, making NPV zero.
Question 7 of 60 · Internal Rate of Return · Easy
Under the IRR rule, an independent project is generally accepted when:
Not quite. Try another option.
Answer: Its IRR exceeds the required return
A project is generally acceptable when its IRR is greater than the firm's required rate of return.
Question 8 of 60 · Discounted Payback Period Method · Easy
What does the discounted payback period measure?
Not quite. Try another option.
Answer: Time required to recover the investment from discounted cash flows
The discounted payback period is the time needed for discounted cash inflows to recover the initial investment.
Question 9 of 60 · Discounted Payback Period Method · Easy
How does the discounted payback period differ from the regular payback period?
Not quite. Try another option.
Answer: It considers the time value of money
Unlike the regular payback method, the discounted payback method discounts future cash flows before calculating recovery time.
Question 10 of 60 · Estimation of Cash Flows · Easy
Which cash flows are relevant when evaluating a capital investment?
Not quite. Try another option.
Answer: Incremental cash flows
Relevant cash flows are incremental cash flows that arise specifically because the project is undertaken.
Question 11 of 60 · Estimation of Cash Flows · Easy
Why is depreciation added back when estimating operating cash flow using accounting profit?
Not quite. Try another option.
Answer: It is a non-cash expense
Depreciation reduces accounting profit but does not involve a direct cash payment, so it is added back.
Question 12 of 60 · Estimation of Cash Flows · Easy
How should a sunk cost generally be treated in a capital budgeting analysis?
Not quite. Try another option.
Answer: Excluded from project cash flows
A sunk cost has already been incurred and cannot be changed by the decision, so it is irrelevant.
Question 13 of 60 · Estimation of Cash Flows · Easy
An increase in net working capital at the beginning of a project is usually treated as:
Not quite. Try another option.
Answer: An initial cash outflow
Additional net working capital uses cash at the start of the project and is therefore treated as an outflow.
Question 14 of 60 · NPV versus IRR · Easy
Which statement correctly compares the usual reinvestment assumptions of NPV and IRR?
Not quite. Try another option.
Answer: NPV uses the required return; IRR uses the IRR
NPV assumes reinvestment at the required return, while the traditional IRR assumption uses the project's IRR.
Question 15 of 60 · NPV versus IRR · Easy
If NPV and IRR rank mutually exclusive projects differently, which method is generally preferred for maximizing firm value?
Not quite. Try another option.
Answer: Net Present Value
NPV is generally preferred because it directly measures the expected addition to firm value.
Question 16 of 60 · Risk analysis in Capital Budgeting · Easy
What is the main purpose of risk analysis in capital budgeting?
Not quite. Try another option.
Answer: To assess uncertainty in project outcomes
Risk analysis examines how uncertainty in assumptions and cash flows may affect a project's results.
Question 17 of 60 · Risk analysis in Capital Budgeting · Easy
Which project would generally be considered riskier, all else being equal?
Not quite. Try another option.
Answer: A project with more uncertain cash flows
Greater uncertainty about future cash flows generally means greater project risk.
Question 18 of 60 · Sensitivity Analysis · Easy
In sensitivity analysis, what is typically changed at one time?
Not quite. Try another option.
Answer: One input variable
Sensitivity analysis changes one input at a time while holding other assumptions constant.
Question 19 of 60 · Sensitivity Analysis · Easy
What does sensitivity analysis help a financial manager identify?
Not quite. Try another option.
Answer: Variables that strongly affect project results
Sensitivity analysis highlights the assumptions or variables to which project outcomes are most responsive.
Question 20 of 60 · Certainty Equivalent Approach · Easy
What does the certainty equivalent approach do to a risky expected cash flow?
Not quite. Try another option.
Answer: Converts it into an equivalent certain cash flow
The certainty equivalent approach adjusts a risky expected cash flow to an amount an investor would regard as certain.
Question 21 of 60 · Net Present Value · Medium
A project costs and generates at the end of each of the next three years. If the required return is , what is the project's approximate NPV?
Not quite. Try another option.
Answer:
The present value of the inflows is . Thus, .
Question 22 of 60 · Internal Rate of Return · Medium
A project requires an initial investment of and produces at the end of each of the next two years. What is its approximate IRR?
Not quite. Try another option.
Answer:
The IRR satisfies . Solving gives .
Question 23 of 60 · Discounted Payback Period Method · Medium
A project costs and generates annually for three years. At a discount rate of , what is its approximate discounted payback period?
Not quite. Try another option.
Answer: years
The first two discounted inflows total about . The remaining is of the third year's discounted inflow.
Question 24 of 60 · Estimation of Cash Flows · Medium
A company paid for a feasibility study before deciding whether to undertake a project. How should this amount be treated when estimating the project's cash flows?
Not quite. Try another option.
Answer: Exclude it as a sunk cost
The feasibility study cost has already been incurred and cannot be recovered, so it is a sunk cost and is not incremental to the decision.
Question 25 of 60 · Estimation of Cash Flows · Medium
A company owns land that can be sold today for . If the land is instead used for a proposed project, what amount should be included in the project's initial cash flow, ignoring taxes?
Not quite. Try another option.
Answer: A opportunity-cost outflow
Using the land sacrifices the that could be received from selling it. This forgone benefit is an incremental opportunity cost.
Question 26 of 60 · Estimation of Cash Flows · Medium
Equipment costing is depreciated straight-line to zero over four years. If the corporate tax rate is , what annual depreciation tax shield should be included in operating cash flow?
Not quite. Try another option.
Answer:
Annual depreciation is . The tax shield is .
Question 27 of 60 · Estimation of Cash Flows · Medium
A project requires an additional of net working capital immediately, all of which will be recovered when the project ends. How should this be recorded?
Not quite. Try another option.
Answer: A outflow initially and inflow at termination
The working-capital commitment is an initial cash outflow. Its full recovery is included as a terminal cash inflow.
Question 28 of 60 · NPV versus IRR · Medium
Two mutually exclusive projects have conflicting rankings: Project A has the higher IRR, while Project B has the higher positive NPV at the company's required return. Which project should normally be selected?
Not quite. Try another option.
Answer: Project B because it has the higher NPV
For mutually exclusive projects, NPV is preferred because it directly measures the expected addition to shareholder wealth at the required return.
Question 29 of 60 · NPV versus IRR · Medium
Project A pays in one year, while Project B pays in two years. Both require the same initial investment. At approximately what discount rate will the projects have equal NPVs?
Not quite. Try another option.
Answer:
Equal NPVs require . Therefore, , so the crossover rate is .
Question 30 of 60 · Internal Rate of Return · Medium
A project has cash flows of , , and in years 0, 1, and 2, respectively. Why can the IRR method be problematic for this project?
Not quite. Try another option.
Answer: The project may have multiple IRRs
The cash-flow signs change twice, so the NPV equation may have more than one IRR. An NPV profile is more reliable in this situation.
Question 31 of 60 · Sensitivity Analysis · Medium
A project's base-case NPV is . A decrease in sales volume reduces NPV to . What is the sensitivity of NPV to sales volume, measured as percentage change in NPV divided by percentage change in volume?
Not quite. Try another option.
Answer:
NPV falls by , while volume falls by . The sensitivity measure is .
Question 32 of 60 · Sensitivity Analysis · Medium
A project's NPV can be expressed as , where is annual unit sales. If base-case sales are units, by what percentage can sales decline before NPV becomes zero?
Not quite. Try another option.
Answer:
Setting NPV to zero gives units. The decline from to is .
Question 33 of 60 · Risk analysis in Capital Budgeting · Medium
A project's possible NPVs are , , and , with probabilities of , , and , respectively. What is the expected NPV?
Not quite. Try another option.
Answer:
Expected NPV is .
Question 34 of 60 · Risk analysis in Capital Budgeting · Medium
Project A has an expected NPV of and a standard deviation of . Project B has an expected NPV of and a standard deviation of . Which project has lower relative risk?
Not quite. Try another option.
Answer: Project B, with a coefficient of variation of
The coefficients of variation are for A and for B. A lower value indicates less relative risk.
Question 35 of 60 · Risk analysis in Capital Budgeting · Medium
Under the risk-adjusted discount-rate approach, how should a company normally evaluate a project that is riskier than its average project?
Not quite. Try another option.
Answer: Use a higher discount rate for its cash flows
A higher required return compensates for greater risk and reduces the present value assigned to the project's uncertain future cash flows.
Question 36 of 60 · Certainty Equivalent Approach · Medium
A one-year project has an expected cash inflow of and a certainty-equivalent coefficient of . If the risk-free rate is , what is the present value of the risk-adjusted inflow?
Not quite. Try another option.
Answer:
The certainty-equivalent inflow is . Its present value is .
Question 37 of 60 · Certainty Equivalent Approach · Medium
A project costs and has expected inflows of in year 1 and in year 2. The certainty-equivalent coefficients are and , respectively, and the risk-free rate is . What is the approximate NPV?
Not quite. Try another option.
Answer:
The NPV is .
Question 38 of 60 · Discounting Techniques of Capital Budgeting · Medium
Project A has an NPV of and a two-year life. Project B has an NPV of and a three-year life. If the projects can be repeated and the discount rate is , which has the higher equivalent annual annuity?
Not quite. Try another option.
Answer: Project A, at approximately
Project A's EAA is , while Project B's is .
Question 39 of 60 · Discounting Techniques of Capital Budgeting · Medium
A project requires an initial investment of and has discounted future cash inflows totaling . What is its profitability index, and should it be accepted if projects are independent?
Not quite. Try another option.
Answer: ; accept the project
The profitability index is . An independent project with an index above has a positive NPV and should be accepted.
Question 40 of 60 · Discounting Techniques of Capital Budgeting · Medium
A project's cash flows are forecast in nominal terms, including expected inflation. Which discount rate should be used to calculate a consistent NPV?
Not quite. Try another option.
Answer: A nominal discount rate including inflation
Nominal cash flows must be discounted at a nominal rate. Mixing nominal cash flows with a real discount rate would overstate present value.
Question 41 of 60 · Discounting Techniques of Capital Budgeting · Hard
A project requires an immediate investment of $500 and generates cash inflows of $180, $220, and $260 at the ends of years 1, 2, and 3. The corresponding annually compounded spot rates are 8%, 9%, and 11%. What is the project's NPV?
Not quite. Try another option.
Answer: $41.94
Discount each cash flow at its maturity-specific spot rate:
Question 42 of 60 · Discounting Techniques of Capital Budgeting · Hard
A project will produce a year-3 cash inflow of $500 measured in current purchasing power. Expected annual inflation is 4%, and the real required return is 6%. Assuming the Fisher relation holds exactly, what is the present value of the inflow?
Not quite. Try another option.
Answer: $419.81
Consistent real discounting gives . Equivalently, inflate the cash flow at 4% and discount it at the nominal rate .
Question 43 of 60 · Discounting Techniques of Capital Budgeting · Hard
A project has cash flows of , , , and at times 0 through 3. Positive cash flows are reinvested at 10%, while negative cash flows are financed at 8%. What is the project's modified internal rate of return?
Not quite. Try another option.
Answer:
The terminal value of positive flows is . The present value of negative flows is . Thus, .
Question 44 of 60 · Net Present Value · Hard
Two mutually exclusive machines provide identical services and can be replaced indefinitely under unchanged conditions. At a 10% discount rate, Machine A has an NPV of $120 and a life of 2 years, while Machine B has an NPV of $160 and a life of 3 years. Which choice is correct using the equivalent annual annuity method?
Not quite. Try another option.
Answer: Choose A; its EAA is approximately $69.14
The EAAs are and . For indefinitely repeatable projects, the higher EAA is preferred.
Question 45 of 60 · Internal Rate of Return · Hard
A project has cash flows of at time 0, at time 1, and at time 2. Which statement correctly identifies its internal rates of return?
Not quite. Try another option.
Answer: The project has IRRs of 10% and 20%
Setting NPV to zero and defining gives . Its roots are and , producing IRRs of 10% and 20%.
Question 46 of 60 · Internal Rate of Return · Hard
Project A costs $1,000 and pays $600 in each of years 1 and 2. Project B costs $1,600 and pays $900 in year 1 and $1,000 in year 2. What is the incremental IRR of choosing B over A, and which project is preferred at an 8% required return?
Not quite. Try another option.
Answer: Incremental IRR ; choose B
The incremental cash flows are , , and . Solving gives . Because 8% is below this crossover rate, B has the higher NPV.
Question 47 of 60 · Discounted Payback Period Method · Hard
A project requires $500 immediately and generates $180 at each year-end for five years. Using a 10% discount rate and linear interpolation within the recovery year, what is its discounted payback period?
Not quite. Try another option.
Answer: 3.43 years
Discounted inflows through year 3 total . The remaining is recovered from the year-4 discounted inflow of , so payback is years.
Question 48 of 60 · Estimation of Cash Flows · Hard
A new machine costs $800, requires $40 of installation costs, and increases net working capital by $60. Existing equipment with a book value of $140 can be sold immediately for $100. If the tax rate is 30%, what is the project's initial net cash outlay?
Not quite. Try another option.
Answer: $788
Selling the old equipment creates a $40 tax-deductible loss and a $12 tax shield, so after-tax proceeds are . Initial outlay is .
Question 49 of 60 · Estimation of Cash Flows · Hard
A project adds annual revenue of $500 and cash operating costs of $280 but reduces contribution margin from an existing product by $60. Annual project depreciation is $80, and the corporate tax rate is 25%. What is the annual incremental operating cash flow?
Not quite. Try another option.
Answer: $140
Incremental EBIT is . Therefore, operating cash flow is .
Question 50 of 60 · Estimation of Cash Flows · Hard
At project termination, equipment with a book value of $80 will be sold for $140. Net working capital of $50 will be recovered, and a tax-deductible cleanup payment of $20 will be made. If the tax rate is 30%, what is the total terminal cash flow?
Not quite. Try another option.
Answer: $158
After-tax sale proceeds are . After-tax cleanup costs are . Including working-capital recovery gives .
Question 51 of 60 · NPV versus IRR · Hard
Two one-year projects are mutually exclusive. Project A costs $1,000 and returns $1,400, while Project B costs $5,000 and returns $6,500. The required return is 10%, and capital is unconstrained. Which project should be selected?
Not quite. Try another option.
Answer: Project B because its NPV is approximately $909.09
A has the higher IRR, but B creates more value: and . NPV governs mutually exclusive choices.
Question 52 of 60 · NPV versus IRR · Hard
Projects A and B each cost $1,000. A pays $200 in year 1 and $1,100 in year 2; B pays $900 in year 1 and $300 in year 2. Project B has a slightly higher IRR, and their crossover rate is approximately 14.29%. Which project should be selected at a 10% required return?
Not quite. Try another option.
Answer: Project A because its NPV is approximately $90.91
At 10%, A's NPV is , while B's is . Below the 14.29% crossover rate, A's later, larger cash flow produces the higher NPV despite B's higher IRR.
Question 53 of 60 · Risk analysis in Capital Budgeting · Hard
A project costs $600. The present value of its inflows will be $900 in a boom, $700 under normal conditions, or $400 in a recession, with probabilities 0.30, 0.50, and 0.20. What are the expected NPV and standard deviation of NPV?
Not quite. Try another option.
Answer: Expected NPV $100; standard deviation $173.21
Possible NPVs are , , and , giving . The variance is , so the standard deviation is .
Question 54 of 60 · Risk analysis in Capital Budgeting · Hard
A project costs $500 now and pays $100 at the end of year 1. At that time, demand is observed. With probability 0.60, year-2 cash flow will be $700; with probability 0.40, it will be $100. Instead of continuing, the firm may abandon the project at year 1 for $250. At a 10% discount rate, what is the project's NPV under the optimal abandonment policy?
Not quite. Try another option.
Answer: $28.93
At year 1, continue in the high state because , but abandon in the low state because . Thus, .
Question 55 of 60 · Risk analysis in Capital Budgeting · Hard
Projects A and B have standard deviations of NPV equal to $100 and $80, respectively. Their NPV correlation is . If both projects are undertaken, what is the standard deviation of their combined NPV?
Not quite. Try another option.
Answer: $91.65
Combined variance is . Therefore, the combined standard deviation is .
Question 56 of 60 · Sensitivity Analysis · Hard
A three-year project costs $600,000, has no salvage value, and uses straight-line depreciation. Annual fixed cash costs are $60,000, unit price is $20, unit variable cost is $12, and the tax rate is 25%. At a 10% discount rate, what annual sales volume makes NPV equal to zero? Express volume in units.
Not quite. Try another option.
Answer: Approximately 39,378 units
With measured in thousands, annual cash flow is . The required annuity is , giving thousand units.
Question 57 of 60 · Sensitivity Analysis · Hard
Project A pays $1,000 in year 1. Project B pays an amount in year 5 chosen so that both cash flows have the same present value at 10%. If the discount rate rises from 10% to 11%, which statement best describes the change in present value?
Not quite. Try another option.
Answer: B falls about 4.42%, while A falls about 0.90%
A's value changes by the factor , a decline of about 0.90%. B's value changes by , a decline of about 4.42%, showing greater rate sensitivity for distant cash flows.
Question 58 of 60 · Sensitivity Analysis · Hard
A tornado chart shows that NPV changes more when selling price is moved through its selected range than when any other input is moved through its own selected range. What conclusion is justified?
Not quite. Try another option.
Answer: Price has the largest one-at-a-time NPV effect over the tested ranges
A tornado chart measures one-at-a-time sensitivity over specified ranges. It does not incorporate input probabilities, variances, correlations, or simultaneous changes.
Question 59 of 60 · Certainty Equivalent Approach · Hard
A project costs $900 and has expected cash inflows of $300, $400, and $500 in years 1 through 3. The corresponding certainty-equivalent coefficients are 0.90, 0.80, and 0.70. If the risk-free rate is 5%, what is the certainty-equivalent NPV?
Not quite. Try another option.
Answer:
Risk-adjusted cash flows are , , and . Discounting them at the risk-free rate gives , so NPV is .
Question 60 of 60 · Certainty Equivalent Approach · Hard
A single expected cash inflow of $1,000 occurs in year 2. It is valued using a 14% risk-adjusted discount rate. If the risk-free rate is 6%, what year-2 certainty-equivalent coefficient produces the same present value?
Not quite. Try another option.
Answer:
Equating the two valuation methods gives . Therefore, .
That's unit 6
Answer a few questions and your score shows up here.
Nearly through. Did unit 6 of EFIN542 save you a night before the exam?
LPU Notes is free. A student pays for the servers.
Did unit 6 of EFIN542 save you a night before the exam?
Then you can help keep it free for the next batch. Ads cover part of the server bill;
the rest comes out of a student's own pocket: the domain, the storage, and keeping
the site up through the weeks everyone needs it at once.
The payment button didn't load. An ad blocker or a filtered network is the usual reason.
to try again.