Unit 6: Investment Decisions - Practice Quiz

EFIN542 60 Questions
0 Correct 0 Wrong 60 Left
0/60

1 What is the main purpose of discounting future cash flows?

Discounting Techniques of Capital Budgeting Easy
A. To calculate the accounting profit
B. To estimate the physical life of an asset
C. To record every historical expenditure incurred before the investment decision
D. To account for the time value of money

2 Which formula calculates the present value of a cash flow received after periods at discount rate ?

Discounting Techniques of Capital Budgeting Easy
A.
B.
C.
D.

3 What does Net Present Value measure?

Net Present Value Easy
A. The number of years before the project begins producing any accounting revenue
B. The project's annual accounting income
C. The project's total undiscounted receipts
D. The present value of inflows minus outflows

4 Under the NPV rule, when should an independent project generally be accepted?

Net Present Value Easy
A. When its NPV is positive
B. When its undiscounted inflows are lower than its total outflows over the entire project life
C. When its NPV is negative
D. When its NPV equals its initial cost

5 A project requires an initial investment of $1,000 and has cash inflows with a total present value of $1,200. What is its NPV?

Net Present Value Easy
A.
B.
C.
D.

6 What is the Internal Rate of Return of a project?

Internal Rate of Return Easy
A. The firm's annual accounting return
B. The rate that makes revenue equal to zero
C. The interest rate charged on all existing loans of the company
D. The rate that makes NPV equal to zero

7 Under the IRR rule, an independent project is generally accepted when:

Internal Rate of Return Easy
A. Its IRR exceeds every borrowing rate previously paid by the firm on all historical debt
B. Its IRR is below the required return
C. Its IRR exceeds the required return
D. Its IRR equals the initial investment

8 What does the discounted payback period measure?

Discounted Payback Period Method Easy
A. Time required to recover the investment from discounted cash flows
B. Time required to recover only the interest cost
C. Time required to earn the first accounting profit
D. Time required to sell the asset at the end of its physical life

9 How does the discounted payback period differ from the regular payback period?

Discounted Payback Period Method Easy
A. It ignores the initial investment
B. It includes only accounting income
C. It considers the time value of money
D. It includes every cash flow occurring after the investment has already been fully recovered

10 Which cash flows are relevant when evaluating a capital investment?

Estimation of Cash Flows Easy
A. All cash receipts earned by the company before the proposed project's evaluation date
B. Incremental cash flows
C. Historical cash flows
D. Financing cash flows only

11 Why is depreciation added back when estimating operating cash flow using accounting profit?

Estimation of Cash Flows Easy
A. It is an initial investment
B. It is a financing inflow
C. It is a non-cash expense
D. It represents cash collected directly from customers throughout the operating life of the project

12 How should a sunk cost generally be treated in a capital budgeting analysis?

Estimation of Cash Flows Easy
A. Allocated equally across every year in which the proposed investment is expected to operate
B. Included as a future inflow
C. Excluded from project cash flows
D. Discounted at the risk-free rate

13 An increase in net working capital at the beginning of a project is usually treated as:

Estimation of Cash Flows Easy
A. A non-cash accounting entry
B. An operating cash inflow
C. A permanent increase in reported profit with no effect on the project's cash flow
D. An initial cash outflow

14 Which statement correctly compares the usual reinvestment assumptions of NPV and IRR?

NPV versus IRR Easy
A. Both require all intermediate cash flows to be held as cash until the project ends
B. NPV uses the IRR; IRR uses the required return
C. NPV uses the required return; IRR uses the IRR
D. Both assume reinvestment at zero percent

15 If NPV and IRR rank mutually exclusive projects differently, which method is generally preferred for maximizing firm value?

NPV versus IRR Easy
A. Net Present Value
B. The method that selects the project having the longest possible operating and physical life
C. Regular payback period
D. Accounting rate of return

16 What is the main purpose of risk analysis in capital budgeting?

Risk analysis in Capital Budgeting Easy
A. To eliminate the initial investment
B. To assess uncertainty in project outcomes
C. To replace every estimated project cash flow with the firm's historical accounting profit
D. To guarantee a positive project return

17 Which project would generally be considered riskier, all else being equal?

Risk analysis in Capital Budgeting Easy
A. A project with fixed initial cost
B. A project whose expected cash receipts are fully known and contractually guaranteed
C. A project with more uncertain cash flows
D. A project with certain cash flows

18 In sensitivity analysis, what is typically changed at one time?

Sensitivity Analysis Easy
A. Every input variable
B. The project manager
C. The entire capital budgeting system together with all historical financial statements
D. One input variable

19 What does sensitivity analysis help a financial manager identify?

Sensitivity Analysis Easy
A. Accounting policies used by unrelated companies across every industry and reporting period
B. Projects that contain no uncertainty
C. The exact future value of every cash flow
D. Variables that strongly affect project results

20 What does the certainty equivalent approach do to a risky expected cash flow?

Certainty Equivalent Approach Easy
A. Converts it into an equivalent certain cash flow
B. Assumes that the risky cash flow will always equal the highest possible forecast
C. Converts it into an accounting expense
D. Adds it directly to the initial investment

21 A project costs and generates at the end of each of the next three years. If the required return is , what is the project's approximate NPV?

Net Present Value Medium
A.
B.
C.
D.

22 A project requires an initial investment of and produces at the end of each of the next two years. What is its approximate IRR?

Internal Rate of Return Medium
A.
B.
C.
D.

23 A project costs and generates annually for three years. At a discount rate of , what is its approximate discounted payback period?

Discounted Payback Period Method Medium
A. years
B. years
C. years
D. years

24 A company paid for a feasibility study before deciding whether to undertake a project. How should this amount be treated when estimating the project's cash flows?

Estimation of Cash Flows Medium
A. Include it as annual overhead
B. Discount it as a terminal outflow
C. Exclude it as a sunk cost
D. Include it as an initial outflow

25 A company owns land that can be sold today for . If the land is instead used for a proposed project, what amount should be included in the project's initial cash flow, ignoring taxes?

Estimation of Cash Flows Medium
A. A financing inflow
B. A terminal-value inflow
C. A opportunity-cost outflow
D. A zero initial cash-flow effect

26 Equipment costing is depreciated straight-line to zero over four years. If the corporate tax rate is , what annual depreciation tax shield should be included in operating cash flow?

Estimation of Cash Flows Medium
A.
B.
C.
D.

27 A project requires an additional of net working capital immediately, all of which will be recovered when the project ends. How should this be recorded?

Estimation of Cash Flows Medium
A. A outflow only when the project terminates
B. A expense in every operating year
C. A outflow initially and inflow at termination
D. A inflow initially and outflow at termination

28 Two mutually exclusive projects have conflicting rankings: Project A has the higher IRR, while Project B has the higher positive NPV at the company's required return. Which project should normally be selected?

NPV versus IRR Medium
A. Both projects because both measures are positive
B. Neither project because the rankings conflict
C. Project B because it has the higher NPV
D. Project A because it has the higher IRR

29 Project A pays in one year, while Project B pays in two years. Both require the same initial investment. At approximately what discount rate will the projects have equal NPVs?

NPV versus IRR Medium
A.
B.
C.
D.

30 A project has cash flows of , , and in years 0, 1, and 2, respectively. Why can the IRR method be problematic for this project?

Internal Rate of Return Medium
A. The initial investment cannot be discounted
B. The terminal outflow must be ignored
C. The project may have multiple IRRs
D. The project cannot have a positive NPV

31 A project's base-case NPV is . A decrease in sales volume reduces NPV to . What is the sensitivity of NPV to sales volume, measured as percentage change in NPV divided by percentage change in volume?

Sensitivity Analysis Medium
A.
B.
C.
D.

32 A project's NPV can be expressed as , where is annual unit sales. If base-case sales are units, by what percentage can sales decline before NPV becomes zero?

Sensitivity Analysis Medium
A.
B.
C.
D.

33 A project's possible NPVs are , , and , with probabilities of , , and , respectively. What is the expected NPV?

Risk analysis in Capital Budgeting Medium
A.
B.
C.
D.

34 Project A has an expected NPV of and a standard deviation of . Project B has an expected NPV of and a standard deviation of . Which project has lower relative risk?

Risk analysis in Capital Budgeting Medium
A. Project B, with a coefficient of variation of
B. Project B, with a coefficient of variation of
C. Project A, with a coefficient of variation of
D. Project A, with a coefficient of variation of

35 Under the risk-adjusted discount-rate approach, how should a company normally evaluate a project that is riskier than its average project?

Risk analysis in Capital Budgeting Medium
A. Use a higher discount rate for its cash flows
B. Exclude the project's terminal cash flow
C. Use a lower discount rate for its cash flows
D. Increase every forecast cash inflow equally

36 A one-year project has an expected cash inflow of and a certainty-equivalent coefficient of . If the risk-free rate is , what is the present value of the risk-adjusted inflow?

Certainty Equivalent Approach Medium
A.
B.
C.
D.

37 A project costs and has expected inflows of in year 1 and in year 2. The certainty-equivalent coefficients are and , respectively, and the risk-free rate is . What is the approximate NPV?

Certainty Equivalent Approach Medium
A.
B.
C.
D.

38 Project A has an NPV of and a two-year life. Project B has an NPV of and a three-year life. If the projects can be repeated and the discount rate is , which has the higher equivalent annual annuity?

Discounting Techniques of Capital Budgeting Medium
A. Project A, at approximately
B. Project B, at approximately
C. Project B, at approximately
D. Project A, at approximately

39 A project requires an initial investment of and has discounted future cash inflows totaling . What is its profitability index, and should it be accepted if projects are independent?

Discounting Techniques of Capital Budgeting Medium
A. ; reject the project
B. ; remain indifferent
C. ; accept the project
D. ; accept the project

40 A project's cash flows are forecast in nominal terms, including expected inflation. Which discount rate should be used to calculate a consistent NPV?

Discounting Techniques of Capital Budgeting Medium
A. A historical rate based on book returns
B. A real discount rate excluding inflation
C. A risk-free rate excluding inflation
D. A nominal discount rate including inflation

41 A project requires an immediate investment of $500 and generates cash inflows of $180, $220, and $260 at the ends of years 1, 2, and 3. The corresponding annually compounded spot rates are 8%, 9%, and 11%. What is the project's NPV?

Discounting Techniques of Capital Budgeting Hard
A. $48.61
B. $35.27
C. $52.08
D. $41.94

42 A project will produce a year-3 cash inflow of $500 measured in current purchasing power. Expected annual inflation is 4%, and the real required return is 6%. Assuming the Fisher relation holds exactly, what is the present value of the inflow?

Discounting Techniques of Capital Budgeting Hard
A. $419.81
B. $444.50
C. $396.62
D. $471.70

43 A project has cash flows of , , , and at times 0 through 3. Positive cash flows are reinvested at 10%, while negative cash flows are financed at 8%. What is the project's modified internal rate of return?

Discounting Techniques of Capital Budgeting Hard
A.
B.
C.
D.

44 Two mutually exclusive machines provide identical services and can be replaced indefinitely under unchanged conditions. At a 10% discount rate, Machine A has an NPV of $120 and a life of 2 years, while Machine B has an NPV of $160 and a life of 3 years. Which choice is correct using the equivalent annual annuity method?

Net Present Value Hard
A. Choose A; its EAA is approximately $60.00
B. Choose A; its EAA is approximately $69.14
C. Choose B; its EAA is approximately $64.34
D. Choose B; its EAA is approximately $80.00

45 A project has cash flows of at time 0, at time 1, and at time 2. Which statement correctly identifies its internal rates of return?

Internal Rate of Return Hard
A. The project has a single IRR of 15%
B. The project has IRRs of 12% and 18%
C. The project has IRRs of 10% and 20%
D. The project has no real-valued IRR

46 Project A costs $1,000 and pays $600 in each of years 1 and 2. Project B costs $1,600 and pays $900 in year 1 and $1,000 in year 2. What is the incremental IRR of choosing B over A, and which project is preferred at an 8% required return?

Internal Rate of Return Hard
A. Incremental IRR ; choose B
B. Incremental IRR ; choose A
C. Incremental IRR ; choose A
D. Incremental IRR ; choose B

47 A project requires $500 immediately and generates $180 at each year-end for five years. Using a 10% discount rate and linear interpolation within the recovery year, what is its discounted payback period?

Discounted Payback Period Method Hard
A. 3.43 years
B. 4.00 years
C. 3.67 years
D. 3.18 years

48 A new machine costs $800, requires $40 of installation costs, and increases net working capital by $60. Existing equipment with a book value of $140 can be sold immediately for $100. If the tax rate is 30%, what is the project's initial net cash outlay?

Estimation of Cash Flows Hard
A. $788
B. $776
C. $800
D. $812

49 A project adds annual revenue of $500 and cash operating costs of $280 but reduces contribution margin from an existing product by $60. Annual project depreciation is $80, and the corporate tax rate is 25%. What is the annual incremental operating cash flow?

Estimation of Cash Flows Hard
A. $155
B. $170
C. $140
D. $125

50 At project termination, equipment with a book value of $80 will be sold for $140. Net working capital of $50 will be recovered, and a tax-deductible cleanup payment of $20 will be made. If the tax rate is 30%, what is the total terminal cash flow?

Estimation of Cash Flows Hard
A. $170
B. $158
C. $152
D. $164

51 Two one-year projects are mutually exclusive. Project A costs $1,000 and returns $1,400, while Project B costs $5,000 and returns $6,500. The required return is 10%, and capital is unconstrained. Which project should be selected?

NPV versus IRR Hard
A. Project A because its IRR is exactly 40%
B. Project B because its NPV is approximately $909.09
C. Project B because its IRR is exactly 30%
D. Project A because its NPV is approximately $272.73

52 Projects A and B each cost $1,000. A pays $200 in year 1 and $1,100 in year 2; B pays $900 in year 1 and $300 in year 2. Project B has a slightly higher IRR, and their crossover rate is approximately 14.29%. Which project should be selected at a 10% required return?

NPV versus IRR Hard
A. Project B because its NPV is approximately $66.12
B. Project B because its IRR is approximately
C. Project A because its IRR is approximately
D. Project A because its NPV is approximately $90.91

53 A project costs $600. The present value of its inflows will be $900 in a boom, $700 under normal conditions, or $400 in a recession, with probabilities 0.30, 0.50, and 0.20. What are the expected NPV and standard deviation of NPV?

Risk analysis in Capital Budgeting Hard
A. Expected NPV $100; standard deviation $173.21
B. Expected NPV $120; standard deviation $173.21
C. Expected NPV $100; standard deviation $150.00
D. Expected NPV $120; standard deviation $150.00

54 A project costs $500 now and pays $100 at the end of year 1. At that time, demand is observed. With probability 0.60, year-2 cash flow will be $700; with probability 0.40, it will be $100. Instead of continuing, the firm may abandon the project at year 1 for $250. At a 10% discount rate, what is the project's NPV under the optimal abandonment policy?

Risk analysis in Capital Budgeting Hard
A.
B. $45.45
C. $28.93
D.

55 Projects A and B have standard deviations of NPV equal to $100 and $80, respectively. Their NPV correlation is . If both projects are undertaken, what is the standard deviation of their combined NPV?

Risk analysis in Capital Budgeting Hard
A. $140.00
B. $128.06
C. $91.65
D. $180.00

56 A three-year project costs $600,000, has no salvage value, and uses straight-line depreciation. Annual fixed cash costs are $60,000, unit price is $20, unit variable cost is $12, and the tax rate is 25%. At a 10% discount rate, what annual sales volume makes NPV equal to zero? Express volume in units.

Sensitivity Analysis Hard
A. Approximately 42,250 units
B. Approximately 39,378 units
C. Approximately 36,711 units
D. Approximately 45,000 units

57 Project A pays $1,000 in year 1. Project B pays an amount in year 5 chosen so that both cash flows have the same present value at 10%. If the discount rate rises from 10% to 11%, which statement best describes the change in present value?

Sensitivity Analysis Hard
A. Both fall about 0.90% because initial values are equal
B. Both fall about 4.42% because discount rates rise equally
C. B falls about 4.42%, while A falls about 0.90%
D. A falls about 4.42%, while B falls about 0.90%

58 A tornado chart shows that NPV changes more when selling price is moved through its selected range than when any other input is moved through its own selected range. What conclusion is justified?

Sensitivity Analysis Hard
A. Price changes will dominate every correlated multi-variable scenario
B. Price must have the highest variance among all project inputs
C. Price has the largest one-at-a-time NPV effect over the tested ranges
D. Price necessarily contributes the most to the probability of loss

59 A project costs $900 and has expected cash inflows of $300, $400, and $500 in years 1 through 3. The corresponding certainty-equivalent coefficients are 0.90, 0.80, and 0.70. If the risk-free rate is 5%, what is the certainty-equivalent NPV?

Certainty Equivalent Approach Hard
A. $18.46
B.
C.
D. $42.71

60 A single expected cash inflow of $1,000 occurs in year 2. It is valued using a 14% risk-adjusted discount rate. If the risk-free rate is 6%, what year-2 certainty-equivalent coefficient produces the same present value?

Certainty Equivalent Approach Hard
A.
B.
C.
D.